Abhishek can do a piece of work in 40 days. He alone worked at it for 8 days and then Bacchhan completed alone the rest work in 24 days. In how many days they will complete the whole work, working together?
1717 days
1817 days
916 days
14 days
The correct Answer is:A
To solve the problem, we will follow these steps:
Step 1: Determine Abhishek's Work Rate
Abhishek can complete the work in 40 days. Therefore, his work rate per day is:
Work Rate of Abhishek=140 (work per day)
Step 2: Calculate the Work Done by Abhishek in 8 Days
In 8 days, the amount of work done by Abhishek is:
Work Done by Abhishek=8×140=840=15
Step 3: Determine the Remaining Work
The total work can be considered as 1 unit. After Abhishek's contribution, the remaining work is:
Remaining Work=1−15=45
Step 4: Calculate Bacchhan's Work Rate
Bacchhan completed the remaining work in 24 days. Therefore, his work rate per day is:
Work Rate of Bacchhan=4/524=4120=130 (work per day)
Step 5: Calculate Combined Work Rate of Abhishek and Bacchhan
Now, we can find their combined work rate:
Combined Work Rate=Work Rate of Abhishek+Work Rate of Bacchhan=140+130
To add these fractions, we need a common denominator. The least common multiple of 40 and 30 is 120.
140=3120,130=4120
Thus,
Combined Work Rate=3120+4120=7120
Step 6: Calculate the Time Taken to Complete the Whole Work Together
The time taken to complete the whole work together is the reciprocal of their combined work rate:
Time=1Combined Work Rate=17120=1207≈17.14 days
Conclusion
Abhishek and Bacchhan, working together, will complete the whole work in approximately 17.14 days.
---
Abhishek can complete the work in 40 days. Therefore, his work rate per day is:
Work Rate of Abhishek=140 (work per day)
In 8 days, the amount of work done by Abhishek is:
Work Done by Abhishek=8×140=840=15
The total work can be considered as 1 unit. After Abhishek's contribution, the remaining work is:
Remaining Work=1−15=45
Bacchhan completed the remaining work in 24 days. Therefore, his work rate per day is:
Work Rate of Bacchhan=4/524=4120=130 (work per day)
Now, we can find their combined work rate:
Combined Work Rate=Work Rate of Abhishek+Work Rate of Bacchhan=140+130
140=3120,130=4120
Thus,
Combined Work Rate=3120+4120=7120
The time taken to complete the whole work together is the reciprocal of their combined work rate:
Time=1Combined Work Rate=17120=1207≈17.14 days
Abhishek and Bacchhan, working together, will complete the whole work in approximately 17.14 days.
Topper's Solved these Questions
Similar Questions
Knowledge Check
A can do a piece of work in 34 days. He worked for 14 days and then left. B completed the remaining work in 30 days. In how many days can B alone complete the work?
A38B51C46D62A and B together can complete a work in 12 days. A alone works for 8 days and B alone can complete the remaining work in 20 days. Then in how many days B alone can complete the whole work?
A60 daysB36 daysC45 daysD24 daysA can do a piece of work in 8 days, B can do it in 16 days, while C can do it in 80 days. In how many days they can complete the whole work, working together?
A5B6C823D2025
A is twice as fast as B and together they can complete a work in 20 days. In how many days can A alone complete the work?
View SolutionA and B complete a work in 6 days. A alone can complete the work in 10 days. In how many days can B alone complete the work ?
View SolutionVaibhav can do a piece of work in 60 days. He works there for 15 days and then Sandeep alone finishes the remaining work in 30 days. In how many days will Vaibhav and Sandeep working together finish the work?
View SolutionIf Rohit alone can complete one-fourth of a work in 32 days, then in how many days Rohit alone can complete the whole work?
View SolutionA can do a piece of work in 6 days. B can do it in 9 days. With the assistance of C they completed the work in 3 days. In how many days can C alone do the work? /
A 6 दिनों में एक काम कर सकता है। B इसे 9 दिनों में कर सकता हैं। C की सहायता से उन्होंने 3 दिनों में काम पूरा कर लिया। तो C अकेले कितने दिनों में यह काम करेगा?
View Solution