Abhishek can do a piece of work in 40 days. He alone worked at it for 8 days and then Bacchhan completed alone the rest work in 24 days. In how many days they will complete the whole work, working together?

A

1717 days

B

1817 days

C

916 days

D

14 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem, we will follow these steps:

Step 1: Determine Abhishek's Work Rate
Abhishek can complete the work in 40 days. Therefore, his work rate per day is:
Work Rate of Abhishek=140 (work per day)

Step 2: Calculate the Work Done by Abhishek in 8 Days
In 8 days, the amount of work done by Abhishek is:
Work Done by Abhishek=8×140=840=15

Step 3: Determine the Remaining Work
The total work can be considered as 1 unit. After Abhishek's contribution, the remaining work is:
Remaining Work=115=45

Step 4: Calculate Bacchhan's Work Rate
Bacchhan completed the remaining work in 24 days. Therefore, his work rate per day is:
Work Rate of Bacchhan=4/524=4120=130 (work per day)

Step 5: Calculate Combined Work Rate of Abhishek and Bacchhan
Now, we can find their combined work rate:
Combined Work Rate=Work Rate of Abhishek+Work Rate of Bacchhan=140+130

To add these fractions, we need a common denominator. The least common multiple of 40 and 30 is 120.
140=3120,130=4120
Thus,
Combined Work Rate=3120+4120=7120

Step 6: Calculate the Time Taken to Complete the Whole Work Together
The time taken to complete the whole work together is the reciprocal of their combined work rate:
Time=1Combined Work Rate=17120=120717.14 days

Conclusion
Abhishek and Bacchhan, working together, will complete the whole work in approximately 17.14 days.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A can do a piece of work in 34 days. He worked for 14 days and then left. B completed the remaining work in 30 days. In how many days can B alone complete the work?

    A38
    B51
    C46
    D62
  • A and B together can complete a work in 12 days. A alone works for 8 days and B alone can complete the remaining work in 20 days. Then in how many days B alone can complete the whole work?

    A60 days
    B36 days
    C45 days
    D24 days
  • A can do a piece of work in 8 days, B can do it in 16 days, while C can do it in 80 days. In how many days they can complete the whole work, working together?

    A5
    B6
    C823
    D2025