C is twice efficient as A. B takes thrice as many days as C. A takes 12 days to finish the work alone. If they work in pairs (ie, AB, BC, CA) starting with AB on the first day then BC on the second day and AC on the third day and so on, then how many days are required to finish the work?
615 days
4.5 days
519 days
8 days
The correct Answer is:C
To solve the problem step by step, let's break down the information given and calculate the required work completion time.
Step 1: Determine the efficiencies of A, B, and C
1. Efficiency of A: A takes 12 days to complete the work alone. Therefore, A's efficiency is:
Efficiency of A=1 work12 days=112 work/day
2. Efficiency of C: C is twice as efficient as A. Therefore, C's efficiency is:
Efficiency of C=2×Efficiency of A=2×112=16 work/day
3. Efficiency of B: B takes thrice as many days as C. Since C takes 6 days to complete the work alone, B takes:
Days taken by B=3×6=18 days
Thus, B's efficiency is:
Efficiency of B=1 work18 days=118 work/day
Step 2: Calculate the total work
The total work can be calculated using A's efficiency:
Total Work=Efficiency of A×Days taken by A=112×12=1 work unit
Step 3: Calculate the work done in pairs
1. Day 1 (A and B):
Work done=Efficiency of A+Efficiency of B=112+118
To add these fractions, find a common denominator (36):
=336+236=536 work units
2. Day 2 (B and C):
Work done=Efficiency of B+Efficiency of C=118+16
Common denominator (18):
=118+318=418=29 work units
3. Day 3 (C and A):
Work done=Efficiency of C+Efficiency of A=16+112
Common denominator (12):
=212+112=312=14 work units
Step 4: Total work done in three days
Now, let's calculate the total work done in three days:
Total work in 3 days=536+29+14
Finding a common denominator (36):
=536+836+936=2236=1118 work units
Step 5: Calculate remaining work and days needed
After 3 days, the remaining work is:
Remaining work=1−1118=718 work units
Step 6: Work done in the next cycles
1. Day 4 (A and B):
Work done=536
Remaining work after Day 4:
718−536=1436−536=936=14
2. Day 5 (B and C):
Work done=29
Remaining work after Day 5:
14−29=936−836=136
3. Day 6 (C and A):
Work done=14
On Day 6, they will complete the remaining work of 136.
Final Calculation of Total Days
Total days taken:
- 5 full days + a fraction of the 6th day.
Thus, the total time taken to complete the work is:
Total Days=6 days
Final Answer
The total number of days required to finish the work is 6 days.
Efficiency of A=1 work12 days=112 work/day
Efficiency of C=2×Efficiency of A=2×112=16 work/day
Days taken by B=3×6=18 days
Thus, B's efficiency is:
Efficiency of B=1 work18 days=118 work/day
Total Work=Efficiency of A×Days taken by A=112×12=1 work unit
Work done=Efficiency of A+Efficiency of B=112+118
To add these fractions, find a common denominator (36):
=336+236=536 work units
Work done=Efficiency of B+Efficiency of C=118+16
Common denominator (18):
=118+318=418=29 work units
Work done=Efficiency of C+Efficiency of A=16+112
Common denominator (12):
=212+112=312=14 work units
Total work in 3 days=536+29+14
Finding a common denominator (36):
=536+836+936=2236=1118 work units
Remaining work=1−1118=718 work units
Work done=536
Remaining work after Day 4:
718−536=1436−536=936=14
Work done=29
Remaining work after Day 5:
14−29=936−836=136
Work done=14
On Day 6, they will complete the remaining work of 136.
- 5 full days + a fraction of the 6th day.
Total Days=6 days
The total number of days required to finish the work is 6 days.
Topper's Solved these Questions
Similar Questions
Knowledge Check
A is thrice as efficient as B. If B takes 8 days more than A, what is the number of days taken by A to finish the whole work, alone?
A4B2C12D16A and B together finish a work in 4 day while Aalone finishes the work girl 12 day In how many days will B finish the san work ?
A5B6C7D8A is twice as fast a workman as B and together they finish a piece of work in 14 days. In how many days can A alone finish the work ?
A18 daysB21 daysC24 daysD27 days
A can do a work in 12 days. B works60% more fast than A then in how many days B alone could finish this work ?
View SolutionBy working together, A and B can finish a work in 15 days. If B alone can finish the work in 20 days, in how many days can A alone finish the work?
View SolutionBy working together, A and B can finish a work in 15 days. If B alone can finish the work in 20 days, in how many days can A alone finish the work?
View SolutionA is twice as good a workman as B and together they finish a piece of work in 7 days. In how many days can A alone finish the work?
View SolutionA is twice as good a workman as B and together they finish a piece of work in 14 days. In how many days can A alone finish the work?
View Solution