(x−2) men can do a piece of work in x days and (x+7) men can do 75% of the same work in (x−10) days. Then in how many days can (x+10) men finish the work?
27 days
12 days
25 days
18 days
The correct Answer is:B
To solve the problem step by step, let's break it down:
Step 1: Understand the Work Done
Let the total work be denoted as W.
From the problem, we know:
- (x−2) men can complete the work in x days.
- Therefore, the work done by (x−2) men in x days is:
W=(x−2)×x
Step 2: Work Done by (x+7) Men
Next, we know that (x+7) men can complete 75% of the work in (x−10) days. Thus:
0.75W=(x+7)×(x−10)
Step 3: Substitute W in the Second Equation
Substituting W from Step 1 into the second equation:
0.75×(x−2)×x=(x+7)×(x−10)
Step 4: Expand Both Sides
Expanding both sides:
- Left side:
0.75(x2−2x)=0.75x2−1.5x
- Right side:
(x+7)(x−10)=x2−10x+7x−70=x2−3x−70
Step 5: Set the Equation
Setting the two sides equal:
0.75x2−1.5x=x2−3x−70
Step 6: Rearrange the Equation
Rearranging gives:
0.75x2−x2+3x−1.5x+70=0
−0.25x2+1.5x+70=0
Multiplying through by -4 to eliminate the decimal:
x2−6x−280=0
Step 7: Factor the Quadratic Equation
Now we need to factor the quadratic equation:
x2−6x−280=0
To factor, we look for two numbers that multiply to -280 and add to -6. The numbers are -20 and 14:
(x−20)(x+14)=0
Thus, x=20 or x=−14. Since x must be positive, we take x=20.
Step 8: Calculate the Number of Days for (x+10) Men
Now substituting x=20:
- The number of men becomes:
x+10=20+10=30 men
- The total work W is:
W=(20−2)×20=18×20=360
- The number of days D for 30 men to finish the work is:
D=WNumber of Men=36030=12 days
Final Answer
Thus, (x+10) men can finish the work in 12 days.
---
Let the total work be denoted as W.
- (x−2) men can complete the work in x days.
- Therefore, the work done by (x−2) men in x days is:
W=(x−2)×x
Next, we know that (x+7) men can complete 75% of the work in (x−10) days. Thus:
0.75W=(x+7)×(x−10)
Substituting W from Step 1 into the second equation:
0.75×(x−2)×x=(x+7)×(x−10)
Expanding both sides:
- Left side:
0.75(x2−2x)=0.75x2−1.5x
- Right side:
(x+7)(x−10)=x2−10x+7x−70=x2−3x−70
Setting the two sides equal:
0.75x2−1.5x=x2−3x−70
Rearranging gives:
0.75x2−x2+3x−1.5x+70=0
−0.25x2+1.5x+70=0
Multiplying through by -4 to eliminate the decimal:
x2−6x−280=0
Now we need to factor the quadratic equation:
x2−6x−280=0
To factor, we look for two numbers that multiply to -280 and add to -6. The numbers are -20 and 14:
(x−20)(x+14)=0
Thus, x=20 or x=−14. Since x must be positive, we take x=20.
Now substituting x=20:
- The number of men becomes:
x+10=20+10=30 men
- The total work W is:
W=(20−2)×20=18×20=360
- The number of days D for 30 men to finish the work is:
D=WNumber of Men=36030=12 days
Thus, (x+10) men can finish the work in 12 days.
Topper's Solved these Questions
Similar Questions
Knowledge Check
If six men can do a piece of work in 6 days, then 3 men can do same work in 10 days (b) 12 days (c) 15 days (d) 18 days
A10B12C15D18If x men can do a piece of work in y days, in how many days will x men do the same work ?
AxzyBxyzCyzxDxyz2 men and 3 boys can do a piece of work in 10 days while 3 men and 2 boys can do the same work in 8 days. In how many days can 2 men and 1 boy do the same work ?
A1212 daysB1112 daysC1512 daysD1312 days
If 4 men or 7 women can do a work in 60 days, then in how many days will 8 men and 7 women finish the same work?
View SolutionIf 300 men can do a piece of work in 16 days. How many men would do (1/5) of the work in 15 days ?
View Solution3 men can do a piece of worki n 18 days , 6 boys can also do the same work in 18 days. In how many days, 4 men and 4 boys together will finish the work?
View SolutionIf 35 men can finish a piece of work in 8 days, then the number of men who can do the same work in 10 days is :
View SolutionIf 10 men can do a work in 20 days, then how many men can do the same work in 4 days?
(a)60 men
(b)20 men
(c)50 men
(d)40 men
View Solution