20 persons completed 13rd of the work in 12 days. How many more person are required to finish rest work in next 12 days?

A

20

B

12

C

18

D

40

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step by step, we will use the information given in the question and apply the concept of work done by a certain number of persons in a given number of days.

Step 1: Understand the Work Done
We know that 20 persons completed 13 of the work in 12 days.

Step 2: Calculate the Total Work
Let’s denote the total work as W. Since 13 of the work is completed in 12 days, we can express the work done in terms of the total work:
Work done=13W

Step 3: Calculate the Work Rate
The work done by 20 persons in 12 days can be represented as:
Work done=Number of persons×Number of days×Work rate
Let’s denote the work rate as R. Therefore:
13W=20×12×R
13W=240R
From this, we can express the total work W:
W=720R

Step 4: Calculate the Remaining Work
The remaining work is:
Remaining work=W13W=23W
Substituting W:
Remaining work=23×720R=480R

Step 5: Determine the Number of Persons Required
We need to finish the remaining work (480R) in the next 12 days. Let X be the number of persons required to complete this work:
Remaining work=X×12×R
Setting the two expressions for remaining work equal gives:
480R=X×12×R
Dividing both sides by R (assuming R0):
480=12X
Now, solving for X:
X=48012=40

Step 6: Calculate the Additional Persons Required
Initially, there were 20 persons. The additional persons required will be:
Additional persons=X20=4020=20

Final Answer
Therefore, 20 more persons are required to finish the remaining work in the next 12 days.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    20 persons completed 13rd of the work in 24 days. How many more person are required to finish the rest of the work in next 12 days?

    A20
    B12
    C18
    D40
  • Question 2 - Select One

    100 workers finish a work in 20, days. How many workers are required to finish the work in 25 days ?

    A100
    B60
    C80
    D40
  • Question 3 - Select One

    Two persons can complete a piece of work in 9 days. How many more persons are needed to complete double the work in 12 days?

    A3
    B2
    C4
    D1