20 persons completed 13rd of the work in 12 days. How many more person are required to finish rest work in next 12 days?
20
12
18
40
The correct Answer is:A
To solve the problem step by step, we will use the information given in the question and apply the concept of work done by a certain number of persons in a given number of days.
Step 1: Understand the Work Done
We know that 20 persons completed 13 of the work in 12 days.
Step 2: Calculate the Total Work
Let’s denote the total work as W. Since 13 of the work is completed in 12 days, we can express the work done in terms of the total work:
Work done=13W
Step 3: Calculate the Work Rate
The work done by 20 persons in 12 days can be represented as:
Work done=Number of persons×Number of days×Work rate
Let’s denote the work rate as R. Therefore:
13W=20×12×R
13W=240R
From this, we can express the total work W:
W=720R
Step 4: Calculate the Remaining Work
The remaining work is:
Remaining work=W−13W=23W
Substituting W:
Remaining work=23×720R=480R
Step 5: Determine the Number of Persons Required
We need to finish the remaining work (480R) in the next 12 days. Let X be the number of persons required to complete this work:
Remaining work=X×12×R
Setting the two expressions for remaining work equal gives:
480R=X×12×R
Dividing both sides by R (assuming R≠0):
480=12X
Now, solving for X:
X=48012=40
Step 6: Calculate the Additional Persons Required
Initially, there were 20 persons. The additional persons required will be:
Additional persons=X−20=40−20=20
Final Answer
Therefore, 20 more persons are required to finish the remaining work in the next 12 days.
---
We know that 20 persons completed 13 of the work in 12 days.
Let’s denote the total work as W. Since 13 of the work is completed in 12 days, we can express the work done in terms of the total work:
Work done=13W
The work done by 20 persons in 12 days can be represented as:
Work done=Number of persons×Number of days×Work rate
Let’s denote the work rate as R. Therefore:
13W=20×12×R
13W=240R
From this, we can express the total work W:
W=720R
The remaining work is:
Remaining work=W−13W=23W
Substituting W:
Remaining work=23×720R=480R
We need to finish the remaining work (480R) in the next 12 days. Let X be the number of persons required to complete this work:
Remaining work=X×12×R
Setting the two expressions for remaining work equal gives:
480R=X×12×R
Dividing both sides by R (assuming R≠0):
480=12X
Now, solving for X:
X=48012=40
Initially, there were 20 persons. The additional persons required will be:
Additional persons=X−20=40−20=20
Therefore, 20 more persons are required to finish the remaining work in the next 12 days.
Topper's Solved these Questions
Similar Questions
20 men complete one- third of a piece of work in 20 days. How many more men should be employed to finish the rest of the work in 25 more days? 10 b. 12 c. 15 d. 20
View SolutionTwo persons can complete a piece of work in 9 days. How many more persons are needed to complete double the work in 12 days?
View Solution
Knowledge Check
- Question 1 - Select One
20 persons completed 13rd of the work in 24 days. How many more person are required to finish the rest of the work in next 12 days?
A20B12C18D40 - Question 2 - Select One
100 workers finish a work in 20, days. How many workers are required to finish the work in 25 days ?
A100B60C80D40 - Question 3 - Select One
Two persons can complete a piece of work in 9 days. How many more persons are needed to complete double the work in 12 days?
A3B2C4D1
15 persons can do a piece of work in 12 days. How many more people are required to complete the work in 10 days?
View Solution30 persons can do a piece of work in 24 days. How many more people are required to complete the work in 20 days?
View Solution18 persons working 8 hours a day can complete 3 units of works in 10 days. How many persons are required to complete 5 units of that work in 16 days working 6 hours a day?
View Solution18 persons working 8 hours a day can complete 3 units of works in 10 days. How many persons are required to complete 5 units of that work in 16 days working 6 hours a day?
View Solution40 men complete one-third of a work in 40 days. How many more men should be employed to finish the rest of the work in 50 more days ?
View Solution