18 persons working 8 hours a day can complete 3 units of works in 10 days. How many persons are required to complete 5 units of that work in 16 days working 6 hours a day?
25
15
20
9
The correct Answer is:A
To solve the problem step by step, we will use the concept of work done, which can be calculated using the formula:
Work=Number of Persons×Hours per Day×Days
Step 1: Calculate the total work done in the first scenario
Given:
- Number of persons (M1) = 18
- Hours per day (H1) = 8
- Days (D1) = 10
- Units of work (W1) = 3
Using the formula, we can calculate the total work done in terms of person-hours:
Total Work=M1×H1×D1=18×8×10=1440 person-hours
Step 2: Calculate the work done per unit
Since 3 units of work are completed in 1440 person-hours, the work done per unit can be calculated as:
Work per unit=Total WorkUnits of Work=14403=480 person-hours per unit
Step 3: Calculate the total work required for the second scenario
Now, we need to find out how much work is required for 5 units of work:
Total Work Required=5×Work per unit=5×480=2400 person-hours
Step 4: Set up the equation for the second scenario
Now we need to find out how many persons (M2) are required to complete this work in the second scenario:
- Hours per day (H2) = 6
- Days (D2) = 16
Using the formula for work, we have:
Total Work Required=M2×H2×D2
Substituting the known values:
2400=M2×6×16
Step 5: Solve for M2
Now, we can solve for M2:
2400=M2×96
M2=240096=25
Conclusion
Thus, the number of persons required to complete 5 units of work in 16 days working 6 hours a day is 25.
---
Given:
- Number of persons (M1) = 18
- Hours per day (H1) = 8
- Days (D1) = 10
- Units of work (W1) = 3
Total Work=M1×H1×D1=18×8×10=1440 person-hours
Since 3 units of work are completed in 1440 person-hours, the work done per unit can be calculated as:
Work per unit=Total WorkUnits of Work=14403=480 person-hours per unit
Now, we need to find out how much work is required for 5 units of work:
Total Work Required=5×Work per unit=5×480=2400 person-hours
Now we need to find out how many persons (M2) are required to complete this work in the second scenario:
- Hours per day (H2) = 6
- Days (D2) = 16
Total Work Required=M2×H2×D2
Substituting the known values:
2400=M2×6×16
Now, we can solve for M2:
2400=M2×96
M2=240096=25
Thus, the number of persons required to complete 5 units of work in 16 days working 6 hours a day is 25.
Topper's Solved these Questions
Similar Questions
Fifteen men can complete a piece of work in 10 days, working 8 hours per day. How many persons are required to complete double the work in 25 days, working 6 hours per day ?
View SolutionFifteen men can complete a piece of work in 10 days, working 8 hours per day. How many persons are required to complete double the work in 25 days, working 6 hours per day ?
View Solution
Knowledge Check
24 persons working 8 hours a day can complete 2 units of a work in 10 days. How many persons are required to complete 4 units of that work, if they work 6 hours a day for 16 days?
एक दिन में 8 घंटे कार्य करते हुए 24 व्यक्ति किसी कार्य की 2 इकाई 10 दिनों में समाप्त कर सकते हैं | इस कार्य की 4 इकाई समाप्त करने के लिए कितने लोगों की आवश्यकता होगी यदि वे 16 दिनों तक एक दिन में 6 घंटे कार्य करते हैं ?A48B36C40D3236 persons working 8 hours a day can do 3 units of work in 12 days. How many persons are required to do 5 units of that work in 16 days, if they work for 6 hours a day?
A50B55C60D4536 persons working 8 hours a day can do 3 units of work in 12 days. How many persons are required to do 5 units of that work in 16 days, if they work for 6 hours a day?
प्रतिदिन 8 घंटे कार्य करके 36 लोग किसी कार्य की 3 इकाई 12 दिनों में कर सकते हैं| यदि वे एक दिन में 6 घंटे कार्य करें तो 16 दिन में इस कार्य की 5 इकाई समाप्त करने के लिए कितने लोगों की आवश्यकता होगी ?A50B55C60D45
15 persons working 8 hours a day can complete a work in 21 days. How many days will 14 persons take to complete a work 112 times as great, if they work 6 hours a day?
View SolutionFifteen men can complete a piece of work in 10 days, working 8 hours per day. How many persons are required to complete double the work in 25 days, working 6 hours per day ?
View Solution10 men working 6 hours a day can complete a work in 18 days. How many hours a day must 15 men work to complete the same work in 12 days.
View Solution36 personn working 8 hours a day can do 3 units of working in 12 days. How many persons are required to complete 4 units of that work, if they work 6 hours a day for 16 days?
View Solution16 persons working 6 hours a day can complete a work in 10 days. In how many days 24 persons working 8 hours a day will complete 80% of that work?
एक दिन में 6 घंटे कार्य करके 16 व्यक्ति किसी कार्य को 10 दिनों में समाप्त कर सकते हैं | एक दिन में 8 घंटे कार्य करके 24 व्यक्ति इस कार्य का 80% भाग कितने दिनों में समाप्त कर सकते हैं ?
View Solution