A certain number of persons can complete a piece of work in 55 days. If there were 6 persons more, the work could be finished 11 days Earlier. How many persons were there when the work started?
1. 17
2. 24
3. 30
4. 22
The correct Answer is:B
To solve the problem step-by-step, let's denote the number of persons initially as x.
Step 1: Understand the work done
The problem states that a certain number of persons can complete the work in 55 days. This means that the total work can be expressed in terms of person-days. The total work W can be calculated as:
W=x×55
Step 2: Work done with additional persons
If there were 6 more persons, the number of persons becomes x+6. The work can then be completed in 11 days earlier, which means it can be completed in:
55−11=44 days
Thus, the total work can also be expressed as:
W=(x+6)×44
Step 3: Set up the equation
Since both expressions represent the same total work W, we can set them equal to each other:
x×55=(x+6)×44
Step 4: Expand and simplify the equation
Expanding the right side of the equation gives:
55x=44x+264
Now, we can isolate x by moving 44x to the left side:
55x−44x=264
This simplifies to:
11x=264
Step 5: Solve for x
Now, divide both sides by 11 to find x:
x=26411=24
Conclusion
Thus, the number of persons when the work started was 24.
The problem states that a certain number of persons can complete the work in 55 days. This means that the total work can be expressed in terms of person-days. The total work W can be calculated as:
W=x×55
If there were 6 more persons, the number of persons becomes x+6. The work can then be completed in 11 days earlier, which means it can be completed in:
55−11=44 days
Thus, the total work can also be expressed as:
W=(x+6)×44
Since both expressions represent the same total work W, we can set them equal to each other:
x×55=(x+6)×44
Expanding the right side of the equation gives:
55x=44x+264
Now, we can isolate x by moving 44x to the left side:
55x−44x=264
This simplifies to:
11x=264
Now, divide both sides by 11 to find x:
x=26411=24
Thus, the number of persons when the work started was 24.
Topper's Solved these Questions
Similar Questions
A certain number of persons can complete a piece of work in 55 days. If there were 6 persons more, the work could be finished in 11 days less. How many persons were originally there?
View SolutionA certain number of men can do a plece of work in 60 days. If there were 6 men more, the work can be finished 20 days earlier. The number of men working is :
View Solution
Knowledge Check
A certain number of persons can complete a piece of work in 55 days. If there were 6 persons more, the work could be finished in 11 days less. How many persons were originally there?
A17B24C30D22a certain number of persons can complete a piece of work in 55 days. If there were 6 persons more the work could be finished in 11 days less. How many persons were originally there ?
A17B24C30D22A certain number of men com plete a piece of work in 60 days. If there were 8 men more, the work can be finished in 10 days less. The number of men originally is:
A30B40C32D36
A certain number of men complete a work in 45 days. If there were 5 men more, the work could be fin- ished in 9 days less How many men were originally there?
View Solution'x' number of men can finish a piece of work in 30 days. If there were 6 men more, the work could be finished in 10 days less. The original number of men is
View Solution'x' number of men can finish a piece of work in 30 days. If there were 6 men more, the work could be finished in 10 days less. The original number of men is
View SolutionA certain number of men can do a piece of work in 80 days. If there were 10 men less, It could be finished in 20 days more. How many men are there in the starting?
View SolutionA certain number of men can do a work in 35 days. If there were 10 men more it could be finished in 10 days less. How many men are there?
View Solution