'x' number of men can finish a piece of work in 30 days. If there were 6 men more, the work could be finished in 10 days less. The original number of men is
6
10
12
15
The correct Answer is:C
To solve the problem step by step, let's define the variables and set up the equations based on the information provided.
Step 1: Define the variables
Let x be the original number of men. According to the problem, these x men can complete the work in 30 days.
Step 2: Calculate the total work
The total work can be expressed in terms of man-days. Since x men complete the work in 30 days, the total work W is:
W=x×30
Step 3: Set up the equation for the new scenario
If there are 6 more men, the total number of men becomes x+6. The work can now be completed in 20 days (30 days - 10 days). Therefore, the total work can also be expressed as:
W=(x+6)×20
Step 4: Set the two expressions for work equal to each other
Since both expressions represent the same total work W, we can set them equal:
x×30=(x+6)×20
Step 5: Expand and simplify the equation
Expanding the right side:
30x=20x+120
Step 6: Rearranging the equation
Now, we can rearrange the equation to isolate x:
30x−20x=120
10x=120
Step 7: Solve for x
Dividing both sides by 10 gives:
x=12
Conclusion
The original number of men is 12.
---
Let x be the original number of men. According to the problem, these x men can complete the work in 30 days.
The total work can be expressed in terms of man-days. Since x men complete the work in 30 days, the total work W is:
W=x×30
If there are 6 more men, the total number of men becomes x+6. The work can now be completed in 20 days (30 days - 10 days). Therefore, the total work can also be expressed as:
W=(x+6)×20
Since both expressions represent the same total work W, we can set them equal:
x×30=(x+6)×20
Expanding the right side:
30x=20x+120
Now, we can rearrange the equation to isolate x:
30x−20x=120
10x=120
Dividing both sides by 10 gives:
x=12
The original number of men is 12.
Similar Questions
A certain number of men can do a piece of work in 40 days. If there were 45 men more the work could have been finished in 25 days. Find the original number of men employed in the work (A) 70 (B) 85 (C) 65 (D) 75
View SolutionA certain number of persons can complete a piece of work in 55 days. If there were 6 persons more, the work could be finished in 11 days less. How many persons were originally there?
View Solution
Knowledge Check
A certain number of men com plete a piece of work in 60 days. If there were 8 men more, the work can be finished in 10 days less. The number of men originally is:
A36B40C30D32A certain number of men can do a plece of work in 60 days. If there were 6 men more, the work can be finished 20 days earlier. The number of men working is :
A6B12C18D24A certain number of men com plete a piece of work in 60 days. If there were 8 men more, the work can be finished in 10 days less. The number of men originally is:
A30B40C32D36
a certain number of persons can complete a piece of work in 55 days. If there were 6 persons more the work could be finished in 11 days less. How many persons were originally there ?
View SolutionA certain number of persons can complete a piece of work in 55 days. If there were 6 persons more, the work could be finished in 11 days less. How many persons were originally there?
View SolutionA certain number of men can do a work in 60 days. If there were 8 men more it could be finished in 10 days less. How many men are there?
View SolutionA certain number of men can do a work in 35 days. If there were 10 men more it could be finished in 10 days less. How many men are there?
View SolutionA certain number of men complete a work in 45 days. If there were 5 men more, the work could be fin- ished in 9 days less How many men were originally there?
View Solution