A certain number of persons can complete a piece of work in 55 days. If there were 6 persons more, the work could be finished in 11 days less. How many persons were originally there?
The correct Answer is:24
To solve the problem step by step, we will define the variables and set up equations based on the information given in the question.
Step 1: Define the variables
Let x be the original number of persons.
Step 2: Calculate the total work done
The total work can be calculated as the product of the number of persons and the number of days they work. If x persons can complete the work in 55 days, then the total work W is:
W=55×x
Step 3: Set up the equation for the new scenario
If there are 6 more persons, the total number of persons becomes x+6. The work can now be completed in 11 days less, which means it takes 55−11=44 days. Therefore, the total work can also be expressed as:
W=44×(x+6)
Step 4: Set the two expressions for work equal to each other
Since both expressions represent the same total work, we can set them equal:
55x=44(x+6)
Step 5: Expand and simplify the equation
Expanding the right side:
55x=44x+264
Now, subtract 44x from both sides:
55x−44x=264
This simplifies to:
11x=264
Step 6: Solve for x
Now, divide both sides by 11 to find x:
x=26411=24
Step 7: Conclusion
The original number of persons was 24.
Let x be the original number of persons.
The total work can be calculated as the product of the number of persons and the number of days they work. If x persons can complete the work in 55 days, then the total work W is:
W=55×x
If there are 6 more persons, the total number of persons becomes x+6. The work can now be completed in 11 days less, which means it takes 55−11=44 days. Therefore, the total work can also be expressed as:
W=44×(x+6)
Since both expressions represent the same total work, we can set them equal:
55x=44(x+6)
Expanding the right side:
55x=44x+264
Now, subtract 44x from both sides:
55x−44x=264
This simplifies to:
11x=264
Now, divide both sides by 11 to find x:
x=26411=24
The original number of persons was 24.
Topper's Solved these Questions
Similar Questions
A certain number of men com plete a piece of work in 60 days. If there were 8 men more, the work can be finished in 10 days less. The number of men originally is:
View Solution'x' number of men can finish a piece of work in 30 days. If there were 6 men more, the work could be finished in 10 days less. The original number of men is
View Solution
Knowledge Check
A certain number of persons can complete a piece of work in 55 days. If there were 6 persons more, the work could be finished 11 days Earlier. How many persons were there when the work started?
A1. 17B2. 24C3. 30D4. 22A certain number of men com plete a piece of work in 60 days. If there were 8 men more, the work can be finished in 10 days less. The number of men originally is:
A30B40C32D36A certain number of men complete a work in 45 days. If there were 5 men more, the work could be fin- ished in 9 days less How many men were originally there?
A30B15C25D20
'x' number of men can finish a piece of work in 30 days. If there were 6 men more, the work could be finished in 10 days less. The original number of men is
View SolutionA certain number of men can do a work in 40 days. If there were 8 men more, it could be finished in 10 days less. How many men were there initially ?
View SolutionA certain number of men can complete a book in 10 days. If there were three more men, then book could be completed in 2 days less. How many men were there in the beginning?
View SolutionA certain number of men can complete a book in 10 days. If there were three more men, then book could be completed in 2 days less. How many men were there in the beginning?
View SolutionA certain number of men can do a plece of work in 60 days. If there were 6 men more, the work can be finished 20 days earlier. The number of men working is :
View Solution