It takes six technicians a total of 10 hr to build a new server from Direct Computer, with each working at the same rate. If six technicians start to build the server at 11 am, and one tech nician per hour is added beginning at 5 pm, at what time will the server be completed?

A

6.40 pm

B

7pm

C

7.20 pm

D

8pm

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:D

Updated on:21/07/2023
|
Answer

Step by step video, text & image solution for It takes six technicians a total of 10 hr to build a new server from Direct Computer, with each working at the same rate. If six technicians start to build the server at 11 am, and one tech nician per hour is added beginning at 5 pm, at what time will the server be completed? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.

Updated on:21/07/2023


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Two men start walking from same point at same time in same direction to take a round of circular route. If one take 10 min and second take 15 min complete the round, at what time will they meet each other ?

    A30 min
    B33 min
    C40 min
    D45 min
  • Machine P can print one lakh books in 8 hours, machine Q can print the same number of books in 10 hours while machine R can print the same number of books in 12 hours. All the machines are started at 9 a.m. while machine P is closed at 11 a.m. and the remaining two machines complete the work. Approximately at what time will the work be finished ?

    A11:30 AM
    B12 noon
    C12 :30 p.m.
    D1 p.m.
  • Study the following information Carefully and answer the given questions : Given an input, a machine generates pass codes for the six batches each day as follows :
    Input : these icons were taken out from the sea
    Pass codes :
    Batch I : from sea the out taken were incons these
    Batch II : from icons these were taken out the sea
    Batch III : from icons out sea the taken were these
    Batch IV : from icons out sea these were taken the
    and so on.
    First batch starts at 10.00 a.m. and each batch is for one hour. There is a rest period of one hour after the end of the fourth batch.
    What will be the pass code for the batch at 3.00 p.m. if input is 'four of the following five form a group' ?

    Aa five following form four group the of
    Ba five following form group the of four
    Ca five following form four of the group
    Da five following form four group of the