38 men can complete a work by working 6 Hrs per day in 12 days then calculate in how many days 51 men can do double of the work by work ing 8 hrs per day?

A

56 days

B

22817 days

C

14 days

D

12817 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem, we will follow these steps:

Step 1: Calculate the total work done by 38 men in 12 days working 6 hours a day.

Total work (W) can be calculated using the formula:
W=Number of Men×Hours per Day×Number of Days
Here, we have:
- Number of Men (M1) = 38
- Hours per Day (H1) = 6
- Number of Days (D1) = 12

So,
W=38×6×12

Step 2: Calculate the total work.

Calculating the total work:
W=38×6=228
W=228×12=2736 hours

Step 3: Since we need to find out how many days 51 men can do double the work, we first calculate double the work.

Double the work (W2) is:
W2=2×W=2×2736=5472 hours

Step 4: Calculate how many days it will take for 51 men working 8 hours a day to complete double the work.

Using the formula for work again:
W2=Number of Men×Hours per Day×Number of Days
Let D2 be the number of days required. We have:
- Number of Men (M2) = 51
- Hours per Day (H2) = 8

So,
5472=51×8×D2

Step 5: Rearranging the equation to find D2.

Rearranging gives us:
D2=547251×8

Step 6: Calculate the value of D2.

Calculating the denominator:
51×8=408
Now substituting back:
D2=5472408

Step 7: Simplifying the fraction.

Calculating:
D2=13.4 days

Final Answer:
Thus, it will take approximately 13.4 days for 51 men to complete double the work working 8 hours a day.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • If 10 men can complete a piece of work in 12 days by working 7 hours a day, then in how many days can 14 mendo the same work by working 6 hours a day?

    AA. 16
    BB. 15
    CC. 10
    DD. 12
  • If 30 men working 9 h per day can reap a field in 16 days, in how many days, will 36 men reap the field working 8 h per day ?

    A15
    B25
    C18
    D10
  • 15 men can complete a piece of work in 32 days. How many men can complete the work in 12 days ?

    A40
    B42
    C38
    D32