38 men can complete a work by working 6 Hrs per day in 12 days then calculate in how many days 51 men can do double of the work by work ing 8 hrs per day?
56 days
22817 days
14 days
12817 days
The correct Answer is:B
To solve the problem, we will follow these steps:
Step 1: Calculate the total work done by 38 men in 12 days working 6 hours a day.
Total work (W) can be calculated using the formula:
W=Number of Men×Hours per Day×Number of Days
Here, we have:
- Number of Men (M1) = 38
- Hours per Day (H1) = 6
- Number of Days (D1) = 12
So,
W=38×6×12
Step 2: Calculate the total work.
Calculating the total work:
W=38×6=228
W=228×12=2736 hours
Step 3: Since we need to find out how many days 51 men can do double the work, we first calculate double the work.
Double the work (W2) is:
W2=2×W=2×2736=5472 hours
Step 4: Calculate how many days it will take for 51 men working 8 hours a day to complete double the work.
Using the formula for work again:
W2=Number of Men×Hours per Day×Number of Days
Let D2 be the number of days required. We have:
- Number of Men (M2) = 51
- Hours per Day (H2) = 8
So,
5472=51×8×D2
Step 5: Rearranging the equation to find D2.
Rearranging gives us:
D2=547251×8
Step 6: Calculate the value of D2.
Calculating the denominator:
51×8=408
Now substituting back:
D2=5472408
Step 7: Simplifying the fraction.
Calculating:
D2=13.4 days
Final Answer:
Thus, it will take approximately 13.4 days for 51 men to complete double the work working 8 hours a day.
---
W=Number of Men×Hours per Day×Number of Days
Here, we have:
- Number of Men (M1) = 38
- Hours per Day (H1) = 6
- Number of Days (D1) = 12
W=38×6×12
W=38×6=228
W=228×12=2736 hours
W2=2×W=2×2736=5472 hours
W2=Number of Men×Hours per Day×Number of Days
Let D2 be the number of days required. We have:
- Number of Men (M2) = 51
- Hours per Day (H2) = 8
5472=51×8×D2
D2=547251×8
51×8=408
Now substituting back:
D2=5472408
D2=13.4 days
Thus, it will take approximately 13.4 days for 51 men to complete double the work working 8 hours a day.
Topper's Solved these Questions
Similar Questions
Fifteen men can complete a piece of work in 10 days, working 8 hours per day. How many persons are required to complete double the work in 25 days, working 6 hours per day ?
View SolutionIf 25 men can do a piece of work in 36 days working 10 hours a day, then how many men are required to complete the work working 6 hours a day in 20 days?
View Solution
Knowledge Check
If 10 men can complete a piece of work in 12 days by working 7 hours a day, then in how many days can 14 mendo the same work by working 6 hours a day?
AA. 16BB. 15CC. 10DD. 12If 30 men working 9 h per day can reap a field in 16 days, in how many days, will 36 men reap the field working 8 h per day ?
A15B25C18D1015 men can complete a piece of work in 32 days. How many men can complete the work in 12 days ?
A40B42C38D32
Fifteen men can complete a piece of work in 10 days, working 8 hours per day. How many persons are required to complete double the work in 25 days, working 6 hours per day ?
View SolutionFifteen men can complete a piece of work in 10 days, working 8 hours per day. How many persons are required to complete double the work in 25 days, working 6 hours per day ?
View SolutionIf 12 men or 18 women can do a work in 14 days, then in how many days will 8 men and 16 women do the same work?
View SolutionIf 30men working 18h per day can reap a field in 32 days, in how many days can 36 men reap the field working 16h per day ?
View SolutionIf 12 men or 20 women can do a work in 54 days, then in how many days can 9 men and 12 women together do the work?
View Solution