A, B and C can finish a piece of work in 12 days, 15 days and 20 days respectively. They started working together. B left the work after working 3 days and C left the work 3 days before completion of the work. In how many days work will be finished?

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is: 7 1 8 days


To solve the problem step-by-step, we will follow these steps:

Step 1: Calculate the work done by A, B, and C in one day.
- A can finish the work in 12 days, so in one day, A does:
Work done by A in one day=112 of the work
- B can finish the work in 15 days, so in one day, B does:
Work done by B in one day=115 of the work
- C can finish the work in 20 days, so in one day, C does:
Work done by C in one day=120 of the work

Step 2: Find the total work done in one day by A, B, and C together.
To find the total work done by A, B, and C together in one day, we need to find the least common multiple (LCM) of their days to work out the total work in terms of a common unit. The LCM of 12, 15, and 20 is 60.

- A's work in one day:
A's work in one day=6012=5 units
- B's work in one day:
B's work in one day=6015=4 units
- C's work in one day:
C's work in one day=6020=3 units

Total work done by A, B, and C in one day:
Total work in one day=5+4+3=12 units

Step 3: Calculate the work done in the first 3 days.
Since they all worked together for the first 3 days:
Work done in 3 days=3×12=36 units

Step 4: Calculate the remaining work after B leaves.
Total work is 60 units. After 3 days, the remaining work is:
Remaining work=6036=24 units

Step 5: Determine the work done after B leaves.
After 3 days, B leaves, and only A and C continue working. Together, A and C can do:
Work done by A and C in one day=5+3=8 units

Step 6: Calculate how many days A and C work together before C leaves.
Let x be the number of days A and C work together before C leaves. The work done by A and C in x days is:
8x units
Since C leaves 3 days before the entire work is completed, they will work together for x days, and then A will continue working alone for 3 more days. The total work equation is:
8x+5(3)=24
8x+15=24
8x=2415
8x=9x=98=1.125 days

Step 7: Calculate the total time taken to finish the work.
The total time taken to finish the work is:
Total time=3 (initial days)+1.125 (days A and C worked together)+3 (days A worked alone)=3+1.125+3=7.125 days

Final Answer:
The work will be finished in 7.125 days.

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A , B and C can do a piece of work in 24days,36 days and 108 days, respectively. They started the work together but A left 9 days after the start of the work and B left 3 days before the work was completed. For how many days did C work ?

    Aa)20
    Bb)19
    Cc)30
    Dd)31
  • A, B and C can complete a piece of work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?

    A7310
    B1025
    C10730
    Dnone of these
  • A, B and C can complete a piece of-work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?

    A7310
    B10215
    C10730
    Dnone of these