A, B and C can finish a piece of work in 12 days, 15 days and 20 days respectively. They started working together. B left the work after working 3 days and C left the work 3 days before completion of the work. In how many days work will be finished?
The correct Answer is: days
To solve the problem step-by-step, we will follow these steps:
Step 1: Calculate the work done by A, B, and C in one day.
- A can finish the work in 12 days, so in one day, A does:
Work done by A in one day=112 of the work
- B can finish the work in 15 days, so in one day, B does:
Work done by B in one day=115 of the work
- C can finish the work in 20 days, so in one day, C does:
Work done by C in one day=120 of the work
Step 2: Find the total work done in one day by A, B, and C together.
To find the total work done by A, B, and C together in one day, we need to find the least common multiple (LCM) of their days to work out the total work in terms of a common unit. The LCM of 12, 15, and 20 is 60.
- A's work in one day:
A's work in one day=6012=5 units
- B's work in one day:
B's work in one day=6015=4 units
- C's work in one day:
C's work in one day=6020=3 units
Total work done by A, B, and C in one day:
Total work in one day=5+4+3=12 units
Step 3: Calculate the work done in the first 3 days.
Since they all worked together for the first 3 days:
Work done in 3 days=3×12=36 units
Step 4: Calculate the remaining work after B leaves.
Total work is 60 units. After 3 days, the remaining work is:
Remaining work=60−36=24 units
Step 5: Determine the work done after B leaves.
After 3 days, B leaves, and only A and C continue working. Together, A and C can do:
Work done by A and C in one day=5+3=8 units
Step 6: Calculate how many days A and C work together before C leaves.
Let x be the number of days A and C work together before C leaves. The work done by A and C in x days is:
8x units
Since C leaves 3 days before the entire work is completed, they will work together for x days, and then A will continue working alone for 3 more days. The total work equation is:
8x+5(3)=24
8x+15=24
8x=24−15
8x=9⟹x=98=1.125 days
Step 7: Calculate the total time taken to finish the work.
The total time taken to finish the work is:
Total time=3 (initial days)+1.125 (days A and C worked together)+3 (days A worked alone)=3+1.125+3=7.125 days
Final Answer:
The work will be finished in 7.125 days.
- A can finish the work in 12 days, so in one day, A does:
Work done by A in one day=112 of the work
- B can finish the work in 15 days, so in one day, B does:
Work done by B in one day=115 of the work
- C can finish the work in 20 days, so in one day, C does:
Work done by C in one day=120 of the work
To find the total work done by A, B, and C together in one day, we need to find the least common multiple (LCM) of their days to work out the total work in terms of a common unit. The LCM of 12, 15, and 20 is 60.
A's work in one day=6012=5 units
- B's work in one day:
B's work in one day=6015=4 units
- C's work in one day:
C's work in one day=6020=3 units
Total work in one day=5+4+3=12 units
Since they all worked together for the first 3 days:
Work done in 3 days=3×12=36 units
Total work is 60 units. After 3 days, the remaining work is:
Remaining work=60−36=24 units
After 3 days, B leaves, and only A and C continue working. Together, A and C can do:
Work done by A and C in one day=5+3=8 units
Let x be the number of days A and C work together before C leaves. The work done by A and C in x days is:
8x units
Since C leaves 3 days before the entire work is completed, they will work together for x days, and then A will continue working alone for 3 more days. The total work equation is:
8x+5(3)=24
8x+15=24
8x=24−15
8x=9⟹x=98=1.125 days
The total time taken to finish the work is:
Total time=3 (initial days)+1.125 (days A and C worked together)+3 (days A worked alone)=3+1.125+3=7.125 days
The work will be finished in 7.125 days.
Topper's Solved these Questions
Similar Questions
A, B and C can finish a piece of work in 16 days, 20 days and 24 days respectively. They started working together. How many days before B should leave the work so that work must complete in 7 days?
View SolutionA, B and C can finish a piece of work in 20 days, 25 days and 30 days respectively. They started working together. After how many days A should leave the work so that total work will be complete in 12 days?
View Solution
Knowledge Check
A , B and C can do a piece of work in 24days,36 days and 108 days, respectively. They started the work together but A left 9 days after the start of the work and B left 3 days before the work was completed. For how many days did C work ?
Aa)20Bb)19Cc)30Dd)31A, B and C can complete a piece of work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?
A7310B1025C10730Dnone of theseA, B and C can complete a piece of-work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?
A7310B10215C10730Dnone of these
A, B and C can do a work in 12, 15 and 18 days respectively. They started the work together but A left after 2 days and B left the work 3 days before the competition of work. Find the number of days it took them to complete the work.
View SolutionA, B and C can do a piece of work in 10 days, 12 days and 15 days respectively. How long will they take to finish it if they work together?
View SolutionA, B and C can complete a work in 10, 12 and 15 days respectively. They started the work together. But A left the work before 5 days of its completion. B also left the work 2 days after A left. In how many days was the work completed?
View Solution3 men A, B and C can complete the work in 10, 12 and 15 days. A, B, C start work together but A left the work after two days. and B left the work 1 day before the completion of the work. In how much time the whole work will be completed?
View SolutionA, B and C can complete a work in 8, 16 and 24 days respectively. They start the work together and A works till last moment . If C leaves the work 2 days before and B leaves one day before the completion of the work, in how many days the work will be finished?
View Solution