A, B and C working together can finish a piece of work in 32 days. They worked for 24 days and after that the C left. Rest of the work is completed by A and B in 28 days. Work done by A in 1 day is equal to work done by B in 2 days. In how many days working alone each one will finish the work?

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A168 days, B336 days, C4445 days


To solve the problem step by step, we will first determine the work done by A, B, and C together, then find their individual efficiencies, and finally calculate how many days each one would take to finish the work alone.

Step 1: Determine the total work done
A, B, and C together can finish the work in 32 days. Therefore, the total work can be represented in terms of work units:
Total Work=Work Rate×Time=132×32=1 unit of work

Step 2: Calculate the work done in 24 days
In 24 days, A, B, and C will complete:
Work done in 24 days=132×24=2432=34 units of work

Step 3: Calculate the remaining work
The remaining work after 24 days is:
Remaining Work=134=14 units of work

Step 4: Work done by A and B in 28 days
A and B complete the remaining work in 28 days. Therefore, their combined work rate can be calculated as:
Work Rate of A and B=14÷28=1112 units of work per day

Step 5: Establish the relationship between A and B
We know that the work done by A in 1 day is equal to the work done by B in 2 days. Therefore, if A's work in one day is a, then B's work in one day is a2.

Let the work done by A in one day be a and the work done by B in one day be b. Thus:
b=a2

Step 6: Combine the efficiencies of A and B
The combined work done by A and B in one day is:
a+b=a+a2=3a2
We know from step 4 that:
3a2=1112
Solving for a:
3a=2112=156a=1168
Thus, A's work rate is 1168 units of work per day.

Step 7: Calculate B's work rate
Using b=a2:
b=1/1682=1336
So, B's work rate is 1336 units of work per day.

Step 8: Calculate C's work rate
We already know the combined work rate of A, B, and C:
Work Rate of A + B + C=132
Now substituting A and B's work rates:
1168+1336+c=132
Finding a common denominator for 1168 and 1336 (which is 336):
2336+1336+c=132
3336+c=132
Converting 132 to a fraction with a denominator of 336:
132=10.5336
Thus:
c=10.53363336=7.5336=15672

Step 9: Calculate the time taken by each worker to finish the work alone
- For A:
Time taken by A=11168=168 days
- For B:
Time taken by B=11336=336 days
- For C:
Time taken by C=115672=67215=44.8 days

Final Answer:
- A can finish the work alone in 168 days.
- B can finish the work alone in 336 days.
- C can finish the work alone in 44.8 days.

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A and B can together finish a work in 30 days. They worked for it for 20 days and then B left. The remaining work was done by A alone in 20 more days. A alone can finish the work in…

    A48 days
    B50 days
    C54 days
    D60 days
  • A and B together can complete a piece of work in 12 days. They worked together for 5 days and then A alone finished the rest of the work in 14 days. A alone can complete the work in

    A24 days
    B22 days
    C20 days
    D18 days
  • A and B complete a work in 16 days, while A alone can finish that work in 24 days. In how many days, B alone can finish that work ?

    A56 days
    B48 days
    C36 days
    D64 days