A, B and C working together can finish a piece of work in 32 days. They worked for 24 days and after that the C left. Rest of the work is completed by A and B in 28 days. Work done by A in 1 day is equal to work done by B in 2 days. In how many days working alone each one will finish the work?
The correct Answer is:A→168 days, B→336 days, C→4445 days
To solve the problem step by step, we will first determine the work done by A, B, and C together, then find their individual efficiencies, and finally calculate how many days each one would take to finish the work alone.
Step 1: Determine the total work done
A, B, and C together can finish the work in 32 days. Therefore, the total work can be represented in terms of work units:
Total Work=Work Rate×Time=132×32=1 unit of work
Step 2: Calculate the work done in 24 days
In 24 days, A, B, and C will complete:
Work done in 24 days=132×24=2432=34 units of work
Step 3: Calculate the remaining work
The remaining work after 24 days is:
Remaining Work=1−34=14 units of work
Step 4: Work done by A and B in 28 days
A and B complete the remaining work in 28 days. Therefore, their combined work rate can be calculated as:
Work Rate of A and B=14÷28=1112 units of work per day
Step 5: Establish the relationship between A and B
We know that the work done by A in 1 day is equal to the work done by B in 2 days. Therefore, if A's work in one day is a, then B's work in one day is a2.
Let the work done by A in one day be a and the work done by B in one day be b. Thus:
b=a2
Step 6: Combine the efficiencies of A and B
The combined work done by A and B in one day is:
a+b=a+a2=3a2
We know from step 4 that:
3a2=1112
Solving for a:
3a=2112=156⟹a=1168
Thus, A's work rate is 1168 units of work per day.
Step 7: Calculate B's work rate
Using b=a2:
b=1/1682=1336
So, B's work rate is 1336 units of work per day.
Step 8: Calculate C's work rate
We already know the combined work rate of A, B, and C:
Work Rate of A + B + C=132
Now substituting A and B's work rates:
1168+1336+c=132
Finding a common denominator for 1168 and 1336 (which is 336):
2336+1336+c=132
3336+c=132
Converting 132 to a fraction with a denominator of 336:
132=10.5336
Thus:
c=10.5336−3336=7.5336=15672
Step 9: Calculate the time taken by each worker to finish the work alone
- For A:
Time taken by A=11168=168 days
- For B:
Time taken by B=11336=336 days
- For C:
Time taken by C=115672=67215=44.8 days
Final Answer:
- A can finish the work alone in 168 days.
- B can finish the work alone in 336 days.
- C can finish the work alone in 44.8 days.
A, B, and C together can finish the work in 32 days. Therefore, the total work can be represented in terms of work units:
Total Work=Work Rate×Time=132×32=1 unit of work
In 24 days, A, B, and C will complete:
Work done in 24 days=132×24=2432=34 units of work
The remaining work after 24 days is:
Remaining Work=1−34=14 units of work
A and B complete the remaining work in 28 days. Therefore, their combined work rate can be calculated as:
Work Rate of A and B=14÷28=1112 units of work per day
We know that the work done by A in 1 day is equal to the work done by B in 2 days. Therefore, if A's work in one day is a, then B's work in one day is a2.
b=a2
The combined work done by A and B in one day is:
a+b=a+a2=3a2
We know from step 4 that:
3a2=1112
Solving for a:
3a=2112=156⟹a=1168
Thus, A's work rate is 1168 units of work per day.
Using b=a2:
b=1/1682=1336
So, B's work rate is 1336 units of work per day.
We already know the combined work rate of A, B, and C:
Work Rate of A + B + C=132
Now substituting A and B's work rates:
1168+1336+c=132
Finding a common denominator for 1168 and 1336 (which is 336):
2336+1336+c=132
3336+c=132
Converting 132 to a fraction with a denominator of 336:
132=10.5336
Thus:
c=10.5336−3336=7.5336=15672
- For A:
Time taken by A=11168=168 days
- For B:
Time taken by B=11336=336 days
- For C:
Time taken by C=115672=67215=44.8 days
- A can finish the work alone in 168 days.
- B can finish the work alone in 336 days.
- C can finish the work alone in 44.8 days.
Topper's Solved these Questions
Similar Questions
A, B and C working together can finish certain piece of work in 28 days. They work together for 18 days, then B left. If rest work done by A and C in 25 days. Work done by A in 2 days is equal to work done by C in 3 days, then find in how many days A, B and C working alone will finish the work?
View SolutionA, B and C working together can finish a certain piece of work in 40 days. They work for 25 days and then B left and rest work done by A and C in 20 days. If efficiency of C is half of B's efficiency. Then in how many days A will finish the working alone?
View Solution
Knowledge Check
A and B can together finish a work in 30 days. They worked for it for 20 days and then B left. The remaining work was done by A alone in 20 more days. A alone can finish the work in…
A48 daysB50 daysC54 daysD60 daysA and B together can complete a piece of work in 12 days. They worked together for 5 days and then A alone finished the rest of the work in 14 days. A alone can complete the work in
A24 daysB22 daysC20 daysD18 daysA and B complete a work in 16 days, while A alone can finish that work in 24 days. In how many days, B alone can finish that work ?
A56 daysB48 daysC36 daysD64 days
A, B and C working together can finish a piece of work in 32 days. They started working together and worked for 20 days then A left the work. Rest work done by B and C in 20 days. In how many days A working alone will finish the work?
View SolutionA is twice as good as B and together they finish a piece of work in 16 days. The number of days taken by A alone to finish the work is
View SolutionA and C working together can finish certain piece of work in 12 days. A and B can finish same piece of work in 20 days. If A work for 24 days and B for 6 days then rest work done by C in 2 days. Then find in how many days A, B and C can finish same piece of work, working together?
View SolutionA is twice as good a workman as B and together they finish a piece of work in 18 days. In how many days will A alone finish the work?
View SolutionA is twice as good a workman as B and together they finish a piece of work in 20 days. In how many days will A alone finish the work?
View Solution