A, B and C working together can finish certain piece of work in 40 days. If (A + B) work together then take 13 less time than that of C takes alone. If (A + C) work together then they take 14 less time than that of B takes alone. In how many days (B + C) working together will finish the work?

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:48829 days


To solve the problem step by step, we will first define the efficiencies of A, B, and C based on the information provided in the question.

Step 1: Define the work done by A, B, and C
Let the work done by A in one day be a, by B be b, and by C be c.

Given that A, B, and C together can finish the work in 40 days, we can express this as:
a+b+c=140(work done in one day)

Step 2: Relationship between A + B and C
The problem states that A + B take 13 less time than C alone.
Let the time taken by C alone be x days. Then, the time taken by A + B is:
xx3=2x3
Thus, we can express the work done by A + B as:
a+b=12x3=32x

Step 3: Relationship between A + C and B
Similarly, A + C take 14 less time than B alone.
Let the time taken by B alone be y days. Then, the time taken by A + C is:
yy4=3y4
Thus, we can express the work done by A + C as:
a+c=13y4=43y

Step 4: Set up equations
Now we have three equations:
1. a+b+c=140
2. a+b=32x
3. a+c=43y

Step 5: Express C's work in terms of A + B
From equation 1, we can express c:
c=140(a+b)

Substituting a+b from equation 2:
c=14032x

Step 6: Express A in terms of B and C
From equation 1, we can also express a:
a=140bc

Step 7: Solve for efficiencies
Now, we can find the efficiencies of A, B, and C. We know:
- a+b=32x
- a+c=43y

Using the ratios of time taken, we can express the efficiencies in terms of a common factor.

Step 8: Find the efficiency of B + C
Now we need to find the efficiency of B + C:
b+c=(a+b+c)a=140a

Step 9: Calculate total work done
The total work done can be calculated as:
Total Work=Efficiency×Time
Using the total efficiency of A, B, and C, we can find the total work done.

Step 10: Calculate days taken by B + C
Finally, we can find the time taken by B + C to finish the work:
Time taken by B+C=Total Workb+c

Final Calculation
Substituting the values will give us the final answer.

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A and B working together can finish a piece of work in 6 days, while A alone can do it in 9 days. How much time will B alone take to finish it?

    A18 days
    B28 days
    C38 days
    D08 days
  • A and B together can do a piece of work in 9 days. If A does thrice the work of B in a given time, the time A alone will take to finish the work is

    A4 days
    B6 days
    C8 days
    D12 days
  • A is twice as good a workman as B and together they finish a piece of work in 14 days. In how many days can A alone finish the work?

    A11 days
    B21 days
    C28 days
    D30 days