A, B and C working together can finish certain piece of work in 40 days. If (A + B) work together then take 13 less time than that of C takes alone. If (A + C) work together then they take 14 less time than that of B takes alone. In how many days (B + C) working together will finish the work?
The correct Answer is:48829 days
To solve the problem step by step, we will first define the efficiencies of A, B, and C based on the information provided in the question.
Step 1: Define the work done by A, B, and C
Let the work done by A in one day be a, by B be b, and by C be c.
Given that A, B, and C together can finish the work in 40 days, we can express this as:
a+b+c=140(work done in one day)
Step 2: Relationship between A + B and C
The problem states that A + B take 13 less time than C alone.
Let the time taken by C alone be x days. Then, the time taken by A + B is:
x−x3=2x3
Thus, we can express the work done by A + B as:
a+b=12x3=32x
Step 3: Relationship between A + C and B
Similarly, A + C take 14 less time than B alone.
Let the time taken by B alone be y days. Then, the time taken by A + C is:
y−y4=3y4
Thus, we can express the work done by A + C as:
a+c=13y4=43y
Step 4: Set up equations
Now we have three equations:
1. a+b+c=140
2. a+b=32x
3. a+c=43y
Step 5: Express C's work in terms of A + B
From equation 1, we can express c:
c=140−(a+b)
Substituting a+b from equation 2:
c=140−32x
Step 6: Express A in terms of B and C
From equation 1, we can also express a:
a=140−b−c
Step 7: Solve for efficiencies
Now, we can find the efficiencies of A, B, and C. We know:
- a+b=32x
- a+c=43y
Using the ratios of time taken, we can express the efficiencies in terms of a common factor.
Step 8: Find the efficiency of B + C
Now we need to find the efficiency of B + C:
b+c=(a+b+c)−a=140−a
Step 9: Calculate total work done
The total work done can be calculated as:
Total Work=Efficiency×Time
Using the total efficiency of A, B, and C, we can find the total work done.
Step 10: Calculate days taken by B + C
Finally, we can find the time taken by B + C to finish the work:
Time taken by B+C=Total Workb+c
Final Calculation
Substituting the values will give us the final answer.
Let the work done by A in one day be a, by B be b, and by C be c.
a+b+c=140(work done in one day)
The problem states that A + B take 13 less time than C alone.
Let the time taken by C alone be x days. Then, the time taken by A + B is:
x−x3=2x3
Thus, we can express the work done by A + B as:
a+b=12x3=32x
Similarly, A + C take 14 less time than B alone.
Let the time taken by B alone be y days. Then, the time taken by A + C is:
y−y4=3y4
Thus, we can express the work done by A + C as:
a+c=13y4=43y
Now we have three equations:
1. a+b+c=140
2. a+b=32x
3. a+c=43y
From equation 1, we can express c:
c=140−(a+b)
c=140−32x
From equation 1, we can also express a:
a=140−b−c
Now, we can find the efficiencies of A, B, and C. We know:
- a+b=32x
- a+c=43y
Now we need to find the efficiency of B + C:
b+c=(a+b+c)−a=140−a
The total work done can be calculated as:
Total Work=Efficiency×Time
Using the total efficiency of A, B, and C, we can find the total work done.
Finally, we can find the time taken by B + C to finish the work:
Time taken by B+C=Total Workb+c
Substituting the values will give us the final answer.
Topper's Solved these Questions
Similar Questions
A takes 4 hours more than that of A and B working together to finish certain piece of work. While B takes 9 hours more than that of A and B working together. Then find in how many hours A and B working together can finish the work?
View SolutionA takes 4 days more to finish certain piece of work than that of B. If working together they can finish the work in 889 days. Then in how many days working alone each can finish the work?
View Solution
Knowledge Check
A and B working together can finish a piece of work in 6 days, while A alone can do it in 9 days. How much time will B alone take to finish it?
A18 daysB28 daysC38 daysD08 daysA and B together can do a piece of work in 9 days. If A does thrice the work of B in a given time, the time A alone will take to finish the work is
A4 daysB6 daysC8 daysD12 daysA is twice as good a workman as B and together they finish a piece of work in 14 days. In how many days can A alone finish the work?
A11 daysB21 daysC28 daysD30 days
A, B and C working together can finish a piece of work in 32 days. They started working together and worked for 20 days then A left the work. Rest work done by B and C in 20 days. In how many days A working alone will finish the work?
View SolutionA is twice as good a workman as B and together they finish a piece of work in 20 days. In how many days will A alone finish the work?
View SolutionA, B and C working together can finish a certain piece of work in 40 days. They work for 25 days and then B left and rest work done by A and C in 20 days. If efficiency of C is half of B's efficiency. Then in how many days A will finish the working alone?
View SolutionA can do a piece of work in 6 days. B takes 8 days and Ctakes as long as A and B would take working together. B and C working together will complete the work in
View SolutionA is twice as good a workman as B and together they finish a piece of work in 7 days. In how many days can B alone finish the work?
View Solution