A, B and C can do a work separately in 16, 32 and 48 days respectively. They started the work together but B leaving off 8 days and C six days beofre the completion of the work. In what time is the work finished?

A

10 days

B

9 days

C

12 days

D

14 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem, we will follow these steps:

Step 1: Calculate the work done by A, B, and C individually.
- A can complete the work in 16 days, so A's work rate (efficiency) is 116 of the work per day.
- B can complete the work in 32 days, so B's work rate (efficiency) is 132 of the work per day.
- C can complete the work in 48 days, so C's work rate (efficiency) is 148 of the work per day.

Step 2: Find the LCM of the days to determine the total work.
- The LCM of 16, 32, and 48 is 96. This means the total work can be considered as 96 units.

Step 3: Calculate the efficiencies in terms of the total work.
- A's efficiency = 9616=6 units/day
- B's efficiency = 9632=3 units/day
- C's efficiency = 9648=2 units/day

Step 4: Determine the total efficiency when all three work together.
- Total efficiency = A's efficiency + B's efficiency + C's efficiency = 6+3+2=11 units/day.

Step 5: Calculate the work done by B and C when they leave early.
- B leaves 8 days before the work is completed. Therefore, the work done by B in those 8 days = 8×3=24 units.
- C leaves 6 days before the work is completed. Therefore, the work done by C in those 6 days = 6×2=12 units.

Step 6: Calculate the total work done by A, B, and C.
- If B and C had not left early, the total work done by A, B, and C together over the entire period would be:
- Total work = Work done by A + Work done by B + Work done by C
- Work done by A in the full time = 12×6=72 units (since they work together for 12 days).
- Total work = 72+24+12=108 units.

Step 7: Calculate the total work done with the adjustments.
- Since B and C leave early, the total work done is 96 units (the total work).
- The total work done by A, B, and C together is 96 units, but we need to account for the work done by B and C before they left.
- The total work done = 72+24+12=108 units, but since the total work is only 96 units, we need to find the time taken to complete the work.

Step 8: Calculate the time taken to finish the work.
- The total work done is 96 units, and the combined efficiency is 11 units/day.
- The time taken to finish the work = 96 units11 units/day8.73 days.

Conclusion:
The work is finished in approximately 12 days.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A, B and C can do a work separately in 16, 32 and 48 days respectively. They started the work together but B leaving off 8 days and C six days beofre the completion of the work. In what time is the work finished?

    A10 days
    B9 days
    C12 days
    D14 days
  • A, B and C can complete a piece of work in 25, 30 and 50 days. Respectively. They started the work together But A and C left 2 days before the completion of the work. In how many days will the work is completed ?

    A14
    B12
    C18
    D10
  • A, B and C can do a work in 8, 16 and 24 days respectively. They all begin together. A continues to work till it is finished, C leaving off 2 days and B one day before its completion. In what time is the work finished?

    A3 days
    B4 days
    C5 days
    D8 days