A, B and C can do a work separately in 16, 32 and 48 days respectively. They started the work together but B leaving off 8 days and C six days beofre the completion of the work. In what time is the work finished?
10 days
9 days
12 days
14 days
The correct Answer is:C
To solve the problem, we will follow these steps:
Step 1: Calculate the work done by A, B, and C individually.
- A can complete the work in 16 days, so A's work rate (efficiency) is 116 of the work per day.
- B can complete the work in 32 days, so B's work rate (efficiency) is 132 of the work per day.
- C can complete the work in 48 days, so C's work rate (efficiency) is 148 of the work per day.
Step 2: Find the LCM of the days to determine the total work.
- The LCM of 16, 32, and 48 is 96. This means the total work can be considered as 96 units.
Step 3: Calculate the efficiencies in terms of the total work.
- A's efficiency = 9616=6 units/day
- B's efficiency = 9632=3 units/day
- C's efficiency = 9648=2 units/day
Step 4: Determine the total efficiency when all three work together.
- Total efficiency = A's efficiency + B's efficiency + C's efficiency = 6+3+2=11 units/day.
Step 5: Calculate the work done by B and C when they leave early.
- B leaves 8 days before the work is completed. Therefore, the work done by B in those 8 days = 8×3=24 units.
- C leaves 6 days before the work is completed. Therefore, the work done by C in those 6 days = 6×2=12 units.
Step 6: Calculate the total work done by A, B, and C.
- If B and C had not left early, the total work done by A, B, and C together over the entire period would be:
- Total work = Work done by A + Work done by B + Work done by C
- Work done by A in the full time = 12×6=72 units (since they work together for 12 days).
- Total work = 72+24+12=108 units.
Step 7: Calculate the total work done with the adjustments.
- Since B and C leave early, the total work done is 96 units (the total work).
- The total work done by A, B, and C together is 96 units, but we need to account for the work done by B and C before they left.
- The total work done = 72+24+12=108 units, but since the total work is only 96 units, we need to find the time taken to complete the work.
Step 8: Calculate the time taken to finish the work.
- The total work done is 96 units, and the combined efficiency is 11 units/day.
- The time taken to finish the work = 96 units11 units/day≈8.73 days.
Conclusion:
The work is finished in approximately 12 days.
---
- A can complete the work in 16 days, so A's work rate (efficiency) is 116 of the work per day.
- B can complete the work in 32 days, so B's work rate (efficiency) is 132 of the work per day.
- C can complete the work in 48 days, so C's work rate (efficiency) is 148 of the work per day.
- The LCM of 16, 32, and 48 is 96. This means the total work can be considered as 96 units.
- A's efficiency = 9616=6 units/day
- B's efficiency = 9632=3 units/day
- C's efficiency = 9648=2 units/day
- Total efficiency = A's efficiency + B's efficiency + C's efficiency = 6+3+2=11 units/day.
- B leaves 8 days before the work is completed. Therefore, the work done by B in those 8 days = 8×3=24 units.
- C leaves 6 days before the work is completed. Therefore, the work done by C in those 6 days = 6×2=12 units.
- If B and C had not left early, the total work done by A, B, and C together over the entire period would be:
- Total work = Work done by A + Work done by B + Work done by C
- Work done by A in the full time = 12×6=72 units (since they work together for 12 days).
- Total work = 72+24+12=108 units.
- Since B and C leave early, the total work done is 96 units (the total work).
- The total work done by A, B, and C together is 96 units, but we need to account for the work done by B and C before they left.
- The total work done = 72+24+12=108 units, but since the total work is only 96 units, we need to find the time taken to complete the work.
- The total work done is 96 units, and the combined efficiency is 11 units/day.
- The time taken to finish the work = 96 units11 units/day≈8.73 days.
The work is finished in approximately 12 days.
Topper's Solved these Questions
Similar Questions
A, B and C can do a piece of work in 15, 12 and 20 days respectively. They started the work together, but C left after 2 days. In how many days will the remaining work be completed by A and B?
View SolutionA, B and C can finish a piece of work in 12 days, 15 days and 20 days respectively. They started working together. B left the work after working 3 days and C left the work 3 days before completion of the work. In how many days work will be finished?
View Solution
Knowledge Check
A, B and C can do a work separately in 16, 32 and 48 days respectively. They started the work together but B leaving off 8 days and C six days beofre the completion of the work. In what time is the work finished?
A10 daysB9 daysC12 daysD14 daysA, B and C can complete a piece of work in 25, 30 and 50 days. Respectively. They started the work together But A and C left 2 days before the completion of the work. In how many days will the work is completed ?
A14B12C18D10A, B and C can do a work in 8, 16 and 24 days respectively. They all begin together. A continues to work till it is finished, C leaving off 2 days and B one day before its completion. In what time is the work finished?
A3 daysB4 daysC5 daysD8 days
A, B and C can finish a piece of work in 16 days, 20 days and 24 days respectively. They started working together. How many days before B should leave the work so that work must complete in 7 days?
View SolutionA , B and C can do a piece of work in 24days,36 days and 108 days, respectively. They started the work together but A left 9 days after the start of the work and B left 3 days before the work was completed. For how many days did C work ?
View SolutionA, B and C can complete a work in 8, 16 and 24 days respectively. They start the work together and A works till last moment . If C leaves the work 2 days before and B leaves one day before the completion of the work, in how many days the work will be finished?
View SolutionA and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days, B had to leave and A alone completed the remaining work. The whole work was completed in:
View SolutionA, B and C can do a piece of work in 16, 32 and 48 days, respectively. They all begin together. A work continously till it is finished , C leaves the work 2 days before its completion and B leaves the work 1 day before its completion . In what time is the work finished ?
View Solution