A can do a work in 10 days and B can do the same in 20 days. If they start the work together and A leaves that work 5 days before completion, in how many days the work will be finished?

A

10

B

8

C

12

D

9

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step by step, we will first determine the work rates of A and B, then calculate how long they work together, and finally find out how many days it takes to complete the work after A leaves.

Step 1: Determine the work rates of A and B
- A can complete the work in 10 days, so A's work rate is:
Rate of A=1 work10 days=110 work/day
- B can complete the work in 20 days, so B's work rate is:
Rate of B=1 work20 days=120 work/day

Step 2: Calculate the combined work rate of A and B
- When A and B work together, their combined work rate is:
Combined Rate=Rate of A+Rate of B=110+120
- To add these fractions, we find a common denominator (which is 20):
Combined Rate=220+120=320 work/day

Step 3: Determine how long they work together before A leaves
- Let x be the number of days they work together. Since A leaves 5 days before the work is completed, B will work alone for 5 days after A leaves.
- Therefore, the total time taken to complete the work can be expressed as:
Total time=x+5

Step 4: Calculate the total work done
- The total work done by A and B together for x days is:
Work done by A and B=Combined Rate×x=320×x
- The work done by B alone for 5 days is:
Work done by B alone=Rate of B×5=120×5=520=14

Step 5: Set up the equation for total work
- The total work done by both A and B together and B alone must equal 1 (the whole work):
320x+14=1

Step 6: Solve for x
- Convert 14 to a fraction with a denominator of 20:
14=520
- Substitute this back into the equation:
320x+520=1
- Multiply through by 20 to eliminate the denominator:
3x+5=20
- Solve for x:
3x=205
3x=15
x=5

Step 7: Calculate the total time to finish the work
- Since x=5, the total time taken to finish the work is:
Total time=x+5=5+5=10 days

Final Answer
The work will be finished in 10 days.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A can do a work in 15 days and B can do the same in 25 days. If they start the work together and B leaves 7 days before completion of the work then the work will be completed in how many days?

    A12 days
    B8 days
    C9 days
    D1012 days
  • Question 2 - Select One

    A can do a work in 40 days and B can do the same work in 60 days. In how many days they can do it together?

    A12
    B10
    C15
    D24
  • Question 3 - Select One

    A can do a work in 12 days and B can do it in 18 days. They started working together. But A leaves 3 days before the work gets over. For how many days did the two work together ?

    A6
    B5
    C7
    D7.2