A takes 412 days more than (A + B) together to complete a work. B takes 8 days more than (A + B) together to complete a work. In how many days will (A + B) complete this work ?
The correct Answer is:6 days
To solve the problem step by step, we will denote the number of days taken by A and B together to complete the work as X days.
Step 1: Define the time taken by A and B
Let:
- A takes X+4.5 days to complete the work alone.
- B takes X+8 days to complete the work alone.
Step 2: Calculate the work done by A and B
The work done by A in one day is 1X+4.5 and the work done by B in one day is 1X+8.
The work done by A and B together in one day is:
1X+4.5+1X+8=(X+8)+(X+4.5)(X+4.5)(X+8)
This simplifies to:
2X+12.5(X+4.5)(X+8)
Step 3: Set up the equation
Since A and B together can complete the work in X days, the total work can also be expressed as:
1X (work done by A and B together in one day)
Thus, we can set up the equation:
2X+12.5(X+4.5)(X+8)=1X
Step 4: Cross-multiply to eliminate the fraction
Cross-multiplying gives us:
X(2X+12.5)=(X+4.5)(X+8)
Step 5: Expand both sides
Expanding both sides:
- Left side: 2X2+12.5X
- Right side: X2+8X+4.5X+36=X2+12.5X+36
Step 6: Rearrange the equation
Now, rearranging the equation gives:
2X2+12.5X=X2+12.5X+36
Subtract X2+12.5X from both sides:
X2=36
Step 7: Solve for X
Taking the square root of both sides gives:
X=6
Conclusion
Thus, A and B together will complete the work in 6 days.
---
Let:
- A takes X+4.5 days to complete the work alone.
- B takes X+8 days to complete the work alone.
The work done by A in one day is 1X+4.5 and the work done by B in one day is 1X+8.
1X+4.5+1X+8=(X+8)+(X+4.5)(X+4.5)(X+8)
This simplifies to:
2X+12.5(X+4.5)(X+8)
Since A and B together can complete the work in X days, the total work can also be expressed as:
1X (work done by A and B together in one day)
2X+12.5(X+4.5)(X+8)=1X
Cross-multiplying gives us:
X(2X+12.5)=(X+4.5)(X+8)
Expanding both sides:
- Left side: 2X2+12.5X
- Right side: X2+8X+4.5X+36=X2+12.5X+36
Now, rearranging the equation gives:
2X2+12.5X=X2+12.5X+36
Subtract X2+12.5X from both sides:
X2=36
Taking the square root of both sides gives:
X=6
Thus, A and B together will complete the work in 6 days.
Topper's Solved these Questions
Similar Questions
A takes 27 days more than (A + B) together to complete a work. B takes 3 days more than (A + B) together to complete a work. In how many days will (A + B) complete this work ?
View SolutionA takes 513 days more than (A + B) together to complete a work. B takes 813 days more than (A + B) together to complete a work. In how many days will A and B alone complete this work ?
View SolutionA takes 6 hours more than (A + B + C) together to complete a work. B takes 1 hours more than (A + B + C) together to complete a work. C takes twice as (A + B + C) together to complete a work. In how many days will A and B together complete this work ?
View SolutionA takes 7 days more than B and 16 days more than C to complete a work. C works as much as (A + B) works together. In how many days will A, B and C alone complete this work ?
View SolutionB works four times as much as A. If B takes 15 days less than A to complete this work. In how many days will A and B alone complete this work ?
View SolutionA takes 5 days more than B and 9 days more than C to complete a work. C works as much as (A + B) works together. In how many days will B and C together complete this work ?
View SolutionA takes 24 days more than B and 32 days more than C to complete a work. C works as much as (A + B) works together. In how many days will A, B and C alone complete this work ?
View SolutionB takes two times as long as (A + C) together to complete a work. C takes three times as much as (A + B) together to complete a work. If all the three, working together can complete the work in 36 days, then find the number of days A, B and C alone will take to complete this work.
View SolutionA is twice as fast as B and together they can complete a work in 20 days. In how many days can A alone complete the work?
View SolutionA is twice as fast as B and together they can complete a work in 20 days. In how many days can A alone complete the work?
View Solution