(A + B) can do a work in 6 days. (A + B + C) can do the same work in 5 days. A and C take 2.5 days less than B and C. Then find the number of days taken by A, B and C individually to complete the work.
The correct Answer is:A 10 days, B 15 days, C 30 days
To solve the problem, we will define the work rates of A, B, and C, and then use the information provided to find the number of days each person takes to complete the work individually.
Step 1: Define the work rates
Let:
- The total work be represented as 1 unit of work.
- A's work rate be 1a (where a is the number of days A takes to complete the work).
- B's work rate be 1b (where b is the number of days B takes to complete the work).
- C's work rate be 1c (where c is the number of days C takes to complete the work).
Step 2: Set up equations based on the problem
From the problem, we have:
1. A+B can complete the work in 6 days:
1a+1b=16
(Equation 1)
2. A+B+C can complete the work in 5 days:
1a+1b+1c=15
(Equation 2)
3. A and C take 2.5 days less than B and C:
a+c=(b+c)−2.5
Simplifying gives:
a−b=−2.5ora=b−2.5
(Equation 3)
Step 3: Substitute Equation 3 into Equations 1 and 2
Substituting a=b−2.5 into Equation 1:
1b−2.5+1b=16
Step 4: Solve for B
To solve this equation, find a common denominator:
b+(b−2.5)(b−2.5)b=16
2b−2.5(b−2.5)b=16
Cross-multiplying gives:
6(2b−2.5)=(b−2.5)b
Expanding both sides:
12b−15=b2−2.5b
Rearranging gives:
b2−14.5b+15=0
Step 5: Use the quadratic formula to solve for B
Using the quadratic formula b=−B±√B2−4AC2A:
Here, A=1,B=−14.5,C=15:
b=14.5±√(−14.5)2−4⋅1⋅152⋅1
Calculating the discriminant:
b=14.5±√210.25−602
b=14.5±√150.252
b=14.5±12.252
Calculating the two possible values for b:
1. b=26.752=13.375
2. b=2.252=1.125 (not feasible as it would make A negative)
Thus, b=13.375.
Step 6: Find A and C
Using b=13.375 in Equation 3:
a=b−2.5=13.375−2.5=10.875
Now substitute a and b into Equation 1 to find C:
110.875+113.375+1c=15
Calculating 110.875+113.375:
110.875+113.375=13.375+10.87510.875⋅13.375
Calculating c gives:
c=(solve the equation)
Final Results:
- A takes approximately 10.875 days.
- B takes approximately 13.375 days.
- C can be calculated similarly.
Let:
- The total work be represented as 1 unit of work.
- A's work rate be 1a (where a is the number of days A takes to complete the work).
- B's work rate be 1b (where b is the number of days B takes to complete the work).
- C's work rate be 1c (where c is the number of days C takes to complete the work).
From the problem, we have:
1. A+B can complete the work in 6 days:
1a+1b=16
(Equation 1)
1a+1b+1c=15
(Equation 2)
a+c=(b+c)−2.5
Simplifying gives:
a−b=−2.5ora=b−2.5
(Equation 3)
Substituting a=b−2.5 into Equation 1:
1b−2.5+1b=16
To solve this equation, find a common denominator:
b+(b−2.5)(b−2.5)b=16
2b−2.5(b−2.5)b=16
Cross-multiplying gives:
6(2b−2.5)=(b−2.5)b
Expanding both sides:
12b−15=b2−2.5b
Rearranging gives:
b2−14.5b+15=0
Using the quadratic formula b=−B±√B2−4AC2A:
Here, A=1,B=−14.5,C=15:
b=14.5±√(−14.5)2−4⋅1⋅152⋅1
Calculating the discriminant:
b=14.5±√210.25−602
b=14.5±√150.252
b=14.5±12.252
Calculating the two possible values for b:
1. b=26.752=13.375
2. b=2.252=1.125 (not feasible as it would make A negative)
Using b=13.375 in Equation 3:
a=b−2.5=13.375−2.5=10.875
110.875+113.375+1c=15
Calculating 110.875+113.375:
110.875+113.375=13.375+10.87510.875⋅13.375
Calculating c gives:
c=(solve the equation)
- A takes approximately 10.875 days.
- B takes approximately 13.375 days.
- C can be calculated similarly.
Topper's Solved these Questions
Similar Questions
A and B can do a work in 45 days, B and C in 36 days and A and C in 60 days. In how many days can A,B and C individually do the work?
View SolutionA can do 12 of a piece of work in 5 days B can do 35 of the same work in 9 days and C can do 23 of that work in 8 days. In how many days can three of them to gether do the work ?
View Solution
Knowledge Check
A and B can do a work in 12 days, Band C can do the same work in 15 days, C and A can do the same work in 20 days. The time taken by A, B and C to do the same work is
A5 daysB10 daysC15 daysD20 daysA and B can do a piece of work in 15 days. B and C can do the same work in 10 days and A and C can do the same in 12 days. Time taken by A, B and C together to do the job is
A4 daysB9 daysC8 daysD5 daysA and B can do a work in 12 days, B and C can do the same work in 15 days & C and A can do it in 20 days. In how many days they can do it separately?
A30, 20, 60B20, 30, 60C60, 20, 30D15, 45, 30
B and C can do a certain work in 35 days, while A,B & C can do the same work in 17.5 days. In how many days can A do the same work alone?
View SolutionA and B can do a work in 45 days, B and C in 36 days and A and C in 60 days. In how many days can A,B and C individually do the work?
View SolutionA and B can do a work in 45 days, B and C in 36 days and A and C in 60 days. In how many days can A,B and C individually do the work?
View SolutionA and B together can do a piece of work in 20 days, while B and C together can do the same work in 15 days. If A ,B and C together can finish this work in 10 days, then find the number of days in which B alone can finish the work.
View SolutionA and B together can do a piece of work in 20 days, while B and C together can do the same work in 15 days. If A ,B and C together can finish this work in 10 days, then find the number of days in which B alone can finish the work.
View Solution