A and B can do a piece of work in 15 days. B and C can do the same work in 10 days and A and C can do the same in 12 days. Time taken by A, B and C together to do the job is
4 days
9 days
8 days
5 days
The correct Answer is:C
To solve the problem, we need to determine the time taken by A, B, and C together to complete the work based on the information given about their individual and pair work rates.
1. Understanding the Work Rates:
- Let the total work be represented in units. We can assume the total work is 1 unit for simplicity.
- A and B can complete the work in 15 days, so their combined work rate is:
Work rate of A and B=115 units/day
- B and C can complete the work in 10 days, so their combined work rate is:
Work rate of B and C=110 units/day
- A and C can complete the work in 12 days, so their combined work rate is:
Work rate of A and C=112 units/day
2. Setting Up the Equations:
- Let the work rates of A, B, and C be a, b, and c respectively. We can set up the following equations based on the combined work rates:
a+b=115(1)
b+c=110(2)
a+c=112(3)
3. Adding the Equations:
- Adding equations (1), (2), and (3) gives:
(a+b)+(b+c)+(a+c)=115+110+112
- This simplifies to:
2a+2b+2c=115+110+112
- Dividing everything by 2:
a+b+c=12(115+110+112)(4)
4. Finding a Common Denominator:
- The least common multiple (LCM) of 15, 10, and 12 is 60. We can convert the fractions:
115=460,110=660,112=560
- Thus:
115+110+112=4+6+560=1560=14
5. Substituting Back:
- Substituting back into equation (4):
a+b+c=12⋅14=18
6. Calculating Time Taken by A, B, and C Together:
- The combined work rate of A, B, and C is 18 units/day. Therefore, the time taken by A, B, and C together to complete the work is:
Time=Total WorkCombined Work Rate=118=8 days
Final Answer:
The time taken by A, B, and C together to do the job is 8 days.
- Let the total work be represented in units. We can assume the total work is 1 unit for simplicity.
- A and B can complete the work in 15 days, so their combined work rate is:
Work rate of A and B=115 units/day
Work rate of B and C=110 units/day
Work rate of A and C=112 units/day
- Let the work rates of A, B, and C be a, b, and c respectively. We can set up the following equations based on the combined work rates:
a+b=115(1)
b+c=110(2)
a+c=112(3)
- Adding equations (1), (2), and (3) gives:
(a+b)+(b+c)+(a+c)=115+110+112
- This simplifies to:
2a+2b+2c=115+110+112
- Dividing everything by 2:
a+b+c=12(115+110+112)(4)
- The least common multiple (LCM) of 15, 10, and 12 is 60. We can convert the fractions:
115=460,110=660,112=560
- Thus:
115+110+112=4+6+560=1560=14
- Substituting back into equation (4):
a+b+c=12⋅14=18
- The combined work rate of A, B, and C is 18 units/day. Therefore, the time taken by A, B, and C together to complete the work is:
Time=Total WorkCombined Work Rate=118=8 days
The time taken by A, B, and C together to do the job is 8 days.
Topper's Solved these Questions
- BOOK - KIRAN PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - TYPE-II45videos
TIME AND WORK
- BOOK - KIRAN PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - TYPE-III31videos
TIME AND WORK
- BOOK - KIRAN PUBLICATIONCHAPTER - TIME AND DISTANCEEXERCISE - Type -XI74videos
TIME AND DISTANCE
- BOOK - KIRAN PUBLICATIONCHAPTER - TRIGONOMETRY EXERCISE - TEST YOURSELF25videos
TRIGONOMETRY
Similar Questions
A and B can do a piece of work in 3 days. B and C can do the same workin 9days, while C and A can do it in 12 days. Find the time in which A, B and C can finish the work, working together.
View SolutionA and B can do a piece of work in 8 days, B and C can do the same work in 12 days. If A, B and C can complete the same work in 6 days, in how many days can A and C complete the same work?
View Solution
Knowledge Check
- Question 1 - Select One
A and B can do a work in 12 days, Band C can do the same work in 15 days, C and A can do the same work in 20 days. The time taken by A, B and C to do the same work is
A5 daysB10 daysC15 daysD20 days - Question 2 - Select One
A and B together can do a work in 10 days. B and C together can do the same work in 6 days. A and C together can do the work in 12 days. Then A, B and C together can do the work in
A28 daysB14 daysC5 57 daysD8 27 days - Question 3 - Select One
If A, B and C can do a piece of work in 5 days, B, C and D can do the same work in 10 days, C, D, and A can do the same work in 15 days, D, A and B can do the same work in 30 days. Find the time taken by A+B+C+D ?
AA)9 daysBB)7 daysCC)9.5 daysDD)7.5 days
A and B can do a piece of work in 10 days.B and C can do it in 12 days. A and C can do it in 15 days. How long will A take to do it alone?
View SolutionA and B can do a piece of work in 12 days, B and C in 15 days, C and A in 20 days. In what time can A do it separately?
View SolutionB and C can do a work in 12 days. C and D can do the same work in 18 days. D and B can do the same work in 24 days. In how many days can B, C and D together complete the work?
View SolutionA and B can do a piece of work in 8 days, B and C can do the same work in 12 days and A and C complete it in 8 days. In how many days A, B and C can complete the whole work, working together?
View SolutionA and B can do a piece of work in 10 days, B and C in 15 days and C and A in 20 days. C alone can do the work in :
View Solution