A can do a work in 12 days and B can do it in 16 days. A and B started the work jointly and A left 2 days before the work is finished. Find the number of days they took to finish the work.
6 days
7 days
9 days
8 days
The correct Answer is:D
To solve the problem, we will follow these steps:
Step 1: Determine the work done by A and B in one day.
- A can complete the work in 12 days, so A's work rate is 112 of the work per day.
- B can complete the work in 16 days, so B's work rate is 116 of the work per day.
Step 2: Find the combined work rate of A and B.
- To find the combined work rate, we need to find a common denominator. The LCM of 12 and 16 is 48.
- A's work in 48 hours: 4812=4 units of work.
- B's work in 48 hours: 4816=3 units of work.
- Therefore, together they can do 4+3=7 units of work in one day.
Step 3: Determine the total work to be done.
- The total work is equivalent to 48 units (as calculated from the LCM).
Step 4: Calculate the time taken if A leaves 2 days before the work is finished.
- Let the total number of days taken to finish the work be x.
- Since A leaves 2 days before the work is finished, A works for x−2 days, while B works for the entire x days.
Step 5: Set up the equation for total work done.
- Work done by A in x−2 days: 4(x−2)
- Work done by B in x days: 3x
- Total work equation:
4(x−2)+3x=48
Step 6: Solve the equation.
1. Expand the equation:
4x−8+3x=48
2. Combine like terms:
7x−8=48
3. Add 8 to both sides:
7x=56
4. Divide by 7:
x=8
Conclusion:
- The total number of days taken to finish the work is 8 days.
---
- A can complete the work in 12 days, so A's work rate is 112 of the work per day.
- B can complete the work in 16 days, so B's work rate is 116 of the work per day.
- To find the combined work rate, we need to find a common denominator. The LCM of 12 and 16 is 48.
- A's work in 48 hours: 4812=4 units of work.
- B's work in 48 hours: 4816=3 units of work.
- Therefore, together they can do 4+3=7 units of work in one day.
- The total work is equivalent to 48 units (as calculated from the LCM).
- Let the total number of days taken to finish the work be x.
- Since A leaves 2 days before the work is finished, A works for x−2 days, while B works for the entire x days.
- Work done by A in x−2 days: 4(x−2)
- Work done by B in x days: 3x
- Total work equation:
4(x−2)+3x=48
1. Expand the equation:
4x−8+3x=48
2. Combine like terms:
7x−8=48
3. Add 8 to both sides:
7x=56
4. Divide by 7:
x=8
- The total number of days taken to finish the work is 8 days.
Topper's Solved these Questions
Similar Questions
A can do a work in 10 days and that of B in 15 days . B starts the work alone but after 3 days he left the work & A joined the work . In how many days will the total work be finished ?
View SolutionA can do a piece of work in 20 days and B can do same work in 25 days. Both A and B start the work and after 8 days A left. In how many days will the total work be completed ?
View Solution
Knowledge Check
A can do a work in 12 days and B can do it in 18 days. They started working together. But A leaves 3 days before the work gets over. For how many days did the two work together ?
A6B5C7D7.2A can do a work in 18 days, B in 9 days and C in 6 days. A and B start working together and after 2 days C joins them. What is the total number of days taken to finish the work ?
A4.33B4.5C4.66DNoneA can do a work in 10 days and B can do the same in 20 days. If they start the work together and A leaves that work 5 days before completion, in how many days the work will be finished?
A10B8C12D9
A and B together can complete a work in 12 days and B and C can do it in 16 days. A work for 5 days and B for 7 days then C complete the remaining work in 13 days. In how many days B can finish the work?
View SolutionA can do a work in 15 days and B can do the same in 25 days. If they start the work together and B leaves 7 days before completion of the work then the work will be completed in how many days?
View SolutionAnil can do a work in 10 days and Babu in 8 days. Anil and Babu can do the work on alternate days. If Anil begins the work, then the work can be finished in how many days?
View SolutionA can do a piece of work in 10 days, B can do it in 15 days working together they can finish the work in :
View SolutionA can do a piece of work in 4 days and B can do it in 12 days. In how many days will they finish the work, both working together ?
View Solution