A and B together can complete a work in 12 days and B and C can do it in 16 days. A work for 5 days and B for 7 days then C complete the remaining work in 13 days. In how many days B can finish the work?
48
60
24
30
The correct Answer is:A
To solve the problem step by step, let's break down the information given and calculate the required values.
Step 1: Determine the total work
A and B together can complete the work in 12 days, and B and C can do it in 16 days. We can find the total work in terms of work units.
- Work done by A and B in one day = 112 of the work
- Work done by B and C in one day = 116 of the work
To find the total work, we can take the least common multiple (LCM) of 12 and 16.
LCM of 12 and 16 = 48 units of work.
Step 2: Calculate the efficiencies
Now, we can calculate the efficiencies of A, B, and C.
- Efficiency of A and B together = 4812=4 units/day
- Efficiency of B and C together = 4816=3 units/day
Step 3: Work done by A and B
A works for 5 days and B works for 7 days.
- Work done by A and B in 5 days = 5×4=20 units
Step 4: Work done by B and C
Now, since A has worked for 5 days, we need to find out how many days B and C worked together. B worked for 7 days, so they worked together for 2 days (7 - 5).
- Work done by B and C in 2 days = 2×3=6 units
Step 5: Total work done
Now, we can calculate the total work done so far:
- Total work done = Work done by A and B + Work done by B and C
- Total work done = 20+6=26 units
Step 6: Remaining work
Now, we can find the remaining work:
- Remaining work = Total work - Work done
- Remaining work = 48−26=22 units
Step 7: Work done by C
C completes the remaining work in 13 days. Therefore, we can find C's efficiency:
- Efficiency of C = 2213 units/day
Step 8: Calculate B's efficiency
From the previous steps, we know that the combined efficiency of B and C is 3 units/day. Let B's efficiency be b and C's efficiency be c.
- b+c=3
- We already found c=2213.
Substituting the value of c:
- b+2213=3
To solve for b:
- b=3−2213
- Convert 3 to a fraction: 3=3913
- b=3913−2213=1713 units/day
Step 9: Calculate the number of days B can finish the work
Now, we can find out how many days B can finish the total work:
- Total work = 48 units
- Efficiency of B = 1713 units/day
Number of days B can finish the work = 481713=48×1317=62417≈36.71 days.
Conclusion
B can finish the work in approximately 36.71 days, which can be rounded to 37 days.
---
A and B together can complete the work in 12 days, and B and C can do it in 16 days. We can find the total work in terms of work units.
- Work done by B and C in one day = 116 of the work
Now, we can calculate the efficiencies of A, B, and C.
- Efficiency of B and C together = 4816=3 units/day
A works for 5 days and B works for 7 days.
Now, since A has worked for 5 days, we need to find out how many days B and C worked together. B worked for 7 days, so they worked together for 2 days (7 - 5).
Now, we can calculate the total work done so far:
- Total work done = 20+6=26 units
Now, we can find the remaining work:
- Remaining work = 48−26=22 units
C completes the remaining work in 13 days. Therefore, we can find C's efficiency:
From the previous steps, we know that the combined efficiency of B and C is 3 units/day. Let B's efficiency be b and C's efficiency be c.
- We already found c=2213.
- Convert 3 to a fraction: 3=3913
- b=3913−2213=1713 units/day
Now, we can find out how many days B can finish the total work:
- Efficiency of B = 1713 units/day
B can finish the work in approximately 36.71 days, which can be rounded to 37 days.
Topper's Solved these Questions
Similar Questions
A and B can do a piece of work in 12 days and B and C can do the same piece of work in 16 days. A work for 5 days and B work for 7 days and C complete the remaining work in 13 days then in how many days C would complete the same work?
View Solution(A + B) can do a piece of work in 12 days. (B + C) can do same work in 16 days. A work for 5 days, B works for 7 days and C completed the remaining work in 13 days. In how many days will A, B and C do this work alone ?
View Solution
Knowledge Check
A and B together can complete a work in 12 days. A alone works for 8 days and B alone can complete the remaining work in 20 days. Then in how many days B alone can complete the whole work?
A60 daysB36 daysC45 daysD24 days(A + B) can do a piece of work in 12 days. (B + C) can do same work in 623 days. A work for 3 days, B works for 4 days and C completed the remaining work in 7 days. In how many days will A, B and C do this work alone ?
A18,15.,20B30,20,10C10,15,25D15,10,25A can do a piece of work in 34 days. He worked for 14 days and then left. B completed the remaining work in 30 days. In how many days can B alone complete the work?
A38B51C46D62
A and B can finish a work together in 12 days, and B and C together in 16 days. If A alone works for 5 days and then B alone continues for 7 days, then remaining work is done by C in 13 days. In how many days can C alone finish the complete work?
View Solution(A + B) working together can finish certain piece of work in 8 days and (B + C) can finish it in 12 days. If A works for 4 days and B works for 7 days, rest work is done by C in 9 days. In how many days C will finish the work working alone?
View SolutionA and B together can complete a work in 12 days and B and C can do it in 16 days. A work for 5 days and B for 7 days then C complete the remaining work in 13 days. In how many days B can finish the work?
View SolutionA can do a work in 12 days when he had worked for 3 days B joined him if they complete the work in 3 more days in how many days can B alone finish the work?
View SolutionA can do a work in 12 days. When he had worked for 3 days, B joined him. If they complete the work in 3 more days, in how many days can B alone finish the work?
View Solution