A and B together can complete a work in 12 days and B and C can do it in 16 days. A work for 5 days and B for 7 days then C complete the remaining work in 13 days. In how many days B can finish the work?

A

48

B

60

C

24

D

30

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step by step, let's break down the information given and calculate the required values.

Step 1: Determine the total work
A and B together can complete the work in 12 days, and B and C can do it in 16 days. We can find the total work in terms of work units.

- Work done by A and B in one day = 112 of the work
- Work done by B and C in one day = 116 of the work

To find the total work, we can take the least common multiple (LCM) of 12 and 16.

LCM of 12 and 16 = 48 units of work.

Step 2: Calculate the efficiencies
Now, we can calculate the efficiencies of A, B, and C.

- Efficiency of A and B together = 4812=4 units/day
- Efficiency of B and C together = 4816=3 units/day

Step 3: Work done by A and B
A works for 5 days and B works for 7 days.

- Work done by A and B in 5 days = 5×4=20 units

Step 4: Work done by B and C
Now, since A has worked for 5 days, we need to find out how many days B and C worked together. B worked for 7 days, so they worked together for 2 days (7 - 5).

- Work done by B and C in 2 days = 2×3=6 units

Step 5: Total work done
Now, we can calculate the total work done so far:

- Total work done = Work done by A and B + Work done by B and C
- Total work done = 20+6=26 units

Step 6: Remaining work
Now, we can find the remaining work:

- Remaining work = Total work - Work done
- Remaining work = 4826=22 units

Step 7: Work done by C
C completes the remaining work in 13 days. Therefore, we can find C's efficiency:

- Efficiency of C = 2213 units/day

Step 8: Calculate B's efficiency
From the previous steps, we know that the combined efficiency of B and C is 3 units/day. Let B's efficiency be b and C's efficiency be c.

- b+c=3
- We already found c=2213.

Substituting the value of c:

- b+2213=3

To solve for b:

- b=32213
- Convert 3 to a fraction: 3=3913
- b=39132213=1713 units/day

Step 9: Calculate the number of days B can finish the work
Now, we can find out how many days B can finish the total work:

- Total work = 48 units
- Efficiency of B = 1713 units/day

Number of days B can finish the work = 481713=48×1317=6241736.71 days.

Conclusion
B can finish the work in approximately 36.71 days, which can be rounded to 37 days.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A and B together can complete a work in 12 days. A alone works for 8 days and B alone can complete the remaining work in 20 days. Then in how many days B alone can complete the whole work?

    A60 days
    B36 days
    C45 days
    D24 days
  • (A + B) can do a piece of work in 12 days. (B + C) can do same work in 623 days. A work for 3 days, B works for 4 days and C completed the remaining work in 7 days. In how many days will A, B and C do this work alone ?

    A18,15.,20
    B30,20,10
    C10,15,25
    D15,10,25
  • A can do a piece of work in 34 days. He worked for 14 days and then left. B completed the remaining work in 30 days. In how many days can B alone complete the work?

    A38
    B51
    C46
    D62