A can do a work in 12 days. When he had worked for 3 days, B joined him. If they complete the work in 3 more days, in how many days can B alone finish the work?
6 days
12 days
4 days
8 days
The correct Answer is:A
To solve the problem step by step, we will break down the information given and use it to find out how many days B alone can finish the work.
Step 1: Determine A's work rate
A can complete the work in 12 days. Therefore, A's work rate is:
Work rate of A=112 (work per day)
Step 2: Calculate the work done by A in 3 days
In the first 3 days, A works alone. The amount of work done by A in 3 days is:
Work done by A in 3 days=3×112=312=14
Step 3: Determine the remaining work
After A has worked for 3 days, the remaining work is:
Remaining work=1−14=34
Step 4: Calculate the work done by A and B together in the next 3 days
A and B work together for the next 3 days to complete the remaining work. Let B's work rate be 1X (where X is the number of days B takes to complete the work alone). Therefore, the combined work rate of A and B is:
Combined work rate=112+1X
In 3 days, the amount of work they complete together is:
3(112+1X)
Step 5: Set up the equation for the remaining work
Since they complete the remaining work of 34 in 3 days, we can set up the equation:
3(112+1X)=34
Step 6: Simplify the equation
Dividing both sides by 3 gives:
112+1X=14
Step 7: Solve for 1X
Subtract 112 from both sides:
1X=14−112
To subtract these fractions, find a common denominator (which is 12):
14=312
Thus,
1X=312−112=212=16
Step 8: Find the value of X
Taking the reciprocal gives:
X=6
Conclusion
B can finish the work alone in 6 days.
A can complete the work in 12 days. Therefore, A's work rate is:
Work rate of A=112 (work per day)
In the first 3 days, A works alone. The amount of work done by A in 3 days is:
Work done by A in 3 days=3×112=312=14
After A has worked for 3 days, the remaining work is:
Remaining work=1−14=34
A and B work together for the next 3 days to complete the remaining work. Let B's work rate be 1X (where X is the number of days B takes to complete the work alone). Therefore, the combined work rate of A and B is:
Combined work rate=112+1X
3(112+1X)
Since they complete the remaining work of 34 in 3 days, we can set up the equation:
3(112+1X)=34
Dividing both sides by 3 gives:
112+1X=14
Subtract 112 from both sides:
1X=14−112
14=312
Thus,
1X=312−112=212=16
Taking the reciprocal gives:
X=6
B can finish the work alone in 6 days.
Similar Questions
(A + B) can do a piece of work in 12 days. (B + C) can do same work in 16 days. A work for 5 days, B works for 7 days and C completed the remaining work in 13 days. In how many days will A, B and C do this work alone ?
View SolutionBy working together, A and B can finish a work in 15 days. If B alone can finish the work in 20 days, in how many days can A alone finish the work?
View Solution
Knowledge Check
A can do a piece of work in 34 days. He worked for 14 days and then left. B completed the remaining work in 30 days. In how many days can B alone complete the work?
A38B51C46D62A can do a piece of work in 6 days. B can do it in 9 days. With the assistance of C they completed the work in 3 days. In how many days can C alone do the work? /
A 6 दिनों में एक काम कर सकता है। B इसे 9 दिनों में कर सकता हैं। C की सहायता से उन्होंने 3 दिनों में काम पूरा कर लिया। तो C अकेले कितने दिनों में यह काम करेगा?A18B16C12D8A and B together can complete a work in 12 days and B and C can do it in 16 days. A work for 5 days and B for 7 days then C complete the remaining work in 13 days. In how many days B can finish the work?
A48B60C24D30
By working together, A and B can finish a work in 15 days. If B alone can finish the work in 20 days, in how many days can A alone finish the work?
View SolutionA and B complete a work in 6 days. A alone can complete the work in 10 days. In how many days can B alone complete the work ?
View SolutionB is twice efficient as A and A can do a piece of work in 15 days. A started the work and after a few days B joined him. They completed the work in 11 days, from the starting. For how many days they worked together?
View SolutionB is twice efficient as A and A can do a piece of work in 15 days. A started the work and after a few days B joined him. They completed the work in 11 days, from the starting. For how many days they worked together?
View SolutionA and B together can complete a work in 12 days. A alone works for 8 days and B alone can complete the remaining work in 20 days. Then in how many days B alone can complete the whole work?
View Solution