(A + B) can do a piece of work in 12 days. (B + C) can do same work in 623 days. A work for 3 days, B works for 4 days and C completed the remaining work in 7 days. In how many days will A, B and C do this work alone ?
18,15.,20
30,20,10
10,15,25
15,10,25
The correct Answer is:A→ 30 days, B→ 20 days, C→ 10 days
To solve the problem step by step, we will first determine the efficiencies of A, B, and C based on the given information.
Step 1: Determine the total work done by A + B and B + C
- A + B can complete the work in 12 days.
- B + C can complete the work in 623 days, which is equal to 203 days.
Step 2: Calculate the efficiencies of A + B and B + C
- The efficiency of A + B:
Efficiency of A + B=Total WorkTime=112
- The efficiency of B + C:
Efficiency of B + C=Total WorkTime=320
Step 3: Find a common total work
To find a common total work, we can use the least common multiple (LCM) of the denominators:
- LCM of 12 and 203 is 60.
Step 4: Calculate the work done by A + B and B + C
- If the total work is 60:
- Work done by A + B in 12 days:
Efficiency of A + B=6012=5 units/day
- Work done by B + C in 623 days:
Efficiency of B + C=60203=9 units/day
Step 5: Set up equations for A, B, and C
Let the efficiencies of A, B, and C be a, b, and c respectively. We have:
1. a+b=5
2. b+c=9
Step 6: Calculate the work done by A, B, and C
- A works for 3 days:
Work done by A=3a
- B works for 4 days:
Work done by B=4b
- C completes the remaining work in 7 days:
Work done by C=7c
Step 7: Total work equation
The total work done by A, B, and C is equal to the total work:
3a+4b+7c=60
Step 8: Substitute values from previous equations
From a+b=5, we can express a as:
a=5−b
Substituting a into the total work equation:
3(5−b)+4b+7c=60
15−3b+4b+7c=60
15+b+7c=60
b+7c=45(Equation 1)
From b+c=9, we can express c as:
c=9−b
Substituting c into Equation 1:
b+7(9−b)=45
b+63−7b=45
−6b+63=45
−6b=45−63
−6b=−18
b=3
Step 9: Find values of a and c
Using b=3:
- From a+b=5:
a+3=5⟹a=2
- From b+c=9:
3+c=9⟹c=6
Step 10: Calculate the number of days each can complete the work alone
- Days taken by A:
Days by A=60a=602=30 days
- Days taken by B:
Days by B=60b=603=20 days
- Days taken by C:
Days by C=60c=606=10 days
Final Answer
A can complete the work in 30 days, B in 20 days, and C in 10 days.
- A + B can complete the work in 12 days.
- B + C can complete the work in 623 days, which is equal to 203 days.
- The efficiency of A + B:
Efficiency of A + B=Total WorkTime=112
Efficiency of B + C=Total WorkTime=320
To find a common total work, we can use the least common multiple (LCM) of the denominators:
- LCM of 12 and 203 is 60.
- If the total work is 60:
- Work done by A + B in 12 days:
Efficiency of A + B=6012=5 units/day
Efficiency of B + C=60203=9 units/day
Let the efficiencies of A, B, and C be a, b, and c respectively. We have:
1. a+b=5
2. b+c=9
- A works for 3 days:
Work done by A=3a
Work done by B=4b
Work done by C=7c
The total work done by A, B, and C is equal to the total work:
3a+4b+7c=60
From a+b=5, we can express a as:
a=5−b
3(5−b)+4b+7c=60
15−3b+4b+7c=60
15+b+7c=60
b+7c=45(Equation 1)
c=9−b
b+7(9−b)=45
b+63−7b=45
−6b+63=45
−6b=45−63
−6b=−18
b=3
Using b=3:
- From a+b=5:
a+3=5⟹a=2
3+c=9⟹c=6
- Days taken by A:
Days by A=60a=602=30 days
Days by B=60b=603=20 days
Days by C=60c=606=10 days
A can complete the work in 30 days, B in 20 days, and C in 10 days.
Topper's Solved these Questions
Similar Questions
(A + B) can do a piece of work in 12 days. (B + C) can do same work in 16 days. A work for 5 days, B works for 7 days and C completed the remaining work in 13 days. In how many days will A, B and C do this work alone ?
View SolutionA and B can do a piece of work in 12 days and B and C can do the same piece of work in 16 days. A work for 5 days and B work for 7 days and C complete the remaining work in 13 days then in how many days C would complete the same work?
View Solution
Knowledge Check
A and B together can complete a work in 12 days and B and C can do it in 16 days. A work for 5 days and B for 7 days then C complete the remaining work in 13 days. In how many days B can finish the work?
A48B60C24D30A can do a piece of work in 34 days. He worked for 14 days and then left. B completed the remaining work in 30 days. In how many days can B alone complete the work?
A38B51C46D62A can do 25 of a work in 12 days while B can do 6623% of the same work in 16 days. They work together for 10 days. B alone will complete the remaining work in
A6 daysB4 daysC8 daysD9 days
(A + B) can do a piece of work in 20 days and A can do same work in 60 days. In how many days will B do this work ?
View SolutionA work for 2 days, then B complete the remaining work in 9 days. If A work for 3 days, then B complete the remaining work in 6 days. In how many days will A and B do this work alone ?
View SolutionA and B can do a piece of work in 8 days, B and C can do the same work in 12 days. If A, B and C can complete the same work in 6 days, in how many days can A and C complete the same work?
View SolutionA and C can do a work in 12 days while A,B and C can do the work in 4 days. In how many days can B do the work alone?
View SolutionA and B can do a piece of work in 8 days, B and C can do the same work in 12 days and A and C complete it in 8 days. In how many days A, B and C can complete the whole work, working together?
View Solution