Anil can do a work in 10 days and Babu in 8 days. Anil and Babu can do the work on alternate days. If Anil begins the work, then the work can be finished in how many days?
9 days
12 days
7 days
8 days
The correct Answer is:A
To solve the problem step by step, we will first determine how much work Anil and Babu can complete in a day, then calculate the total work done over a period of days, and finally find out how many days it takes to complete the work.
Step 1: Determine the total work
Anil can complete the work in 10 days, and Babu can complete it in 8 days. To find a common measure of work, we can take the Least Common Multiple (LCM) of their working days.
- LCM of 10 and 8 = 40
So, we will consider the total work as 40 units.
Step 2: Calculate work done per day
Now, we need to find out how much work Anil and Babu can do in one day.
- Work done by Anil in one day = Total work / Days taken by Anil = 40 / 10 = 4 units
- Work done by Babu in one day = Total work / Days taken by Babu = 40 / 8 = 5 units
Step 3: Work done in two days
Since Anil and Babu work on alternate days, we can calculate the total work done in a 2-day cycle.
- Day 1: Anil works and completes 4 units.
- Day 2: Babu works and completes 5 units.
Total work done in 2 days = Work done by Anil + Work done by Babu = 4 + 5 = 9 units.
Step 4: Calculate total cycles needed
Now, we need to find out how many such 2-day cycles are needed to complete the total work of 40 units.
- Total work = 40 units
- Work done in 2 days = 9 units
Number of complete 2-day cycles = Total work / Work done in 2 days = 40 / 9 ≈ 4.44 cycles.
Since we can only complete whole cycles, we will complete 4 full cycles.
Step 5: Calculate work done in 4 cycles
In 4 cycles (which is 8 days), the total work done will be:
- Total work done in 4 cycles = 4 cycles * 9 units = 36 units.
Step 6: Calculate remaining work
After 8 days, the total work done is 36 units. Therefore, the remaining work is:
- Remaining work = Total work - Work done = 40 - 36 = 4 units.
Step 7: Determine who will work next
Since Anil starts the work, he will work on the 9th day.
On the 9th day, Anil will work and complete 4 units of work.
Step 8: Conclusion
Thus, the total time taken to finish the work is:
- Total days = 8 days (from the 4 cycles) + 1 day (Anil's work on the 9th day) = 9 days.
Therefore, Anil and Babu can finish the work in 9 days.
---
Anil can complete the work in 10 days, and Babu can complete it in 8 days. To find a common measure of work, we can take the Least Common Multiple (LCM) of their working days.
Now, we need to find out how much work Anil and Babu can do in one day.
- Work done by Babu in one day = Total work / Days taken by Babu = 40 / 8 = 5 units
Since Anil and Babu work on alternate days, we can calculate the total work done in a 2-day cycle.
- Day 2: Babu works and completes 5 units.
Now, we need to find out how many such 2-day cycles are needed to complete the total work of 40 units.
- Work done in 2 days = 9 units
In 4 cycles (which is 8 days), the total work done will be:
After 8 days, the total work done is 36 units. Therefore, the remaining work is:
Since Anil starts the work, he will work on the 9th day.
Thus, the total time taken to finish the work is:
Topper's Solved these Questions
Similar Questions
A can do a work in 10 days and that of B in 15 days . B starts the work alone but after 3 days he left the work & A joined the work . In how many days will the total work be finished ?
View SolutionA can do a piece of work in 20 days and B in 15 days. With help of C, they finish the work in 5 days. C can alone do the work in
View Solution
Knowledge Check
A can do a work in 6 days, B can do it in 8 days and C can complete it in 12 days. If A starts the work and they work in alternatively, then in how many days, the work will be completed?
A635B723C525D623If P can do a work in 6 days and Q Can do the same work in
8 days. R can do the same work in 12 days. If they are
woeking together then the work will be completed in how
many days?A73daysB83daysC103daysD113daysA can do a work in 12 days and B can do it in 16 days. A and B started the work jointly and A left 2 days before the work is finished. Find the number of days they took to finish the work.
A6 daysB7 daysC9 daysD8 days
A and B can do a work in 30 days and 10 days respectively. If they work on alternate days beginning with A, in how many days will the work be completed?
View SolutionAnil can do a piece of work in 5 days and ankur in 4 days. How long will they take to do the same work, if they work together?
View SolutionA and B can do a work in 30 days and 10 days respectively. If they work on alternate days beginning with A, in how many days will the work be completed?
View SolutionA and B can do a work in 30 days and 10 days respectively. If they work on alternate days beginning with A, in how many days will the work be completed?
View SolutionA can do a work in 36 days and B in 12 days. If they work to gether in how many days will they be able to do the work?
View Solution