A and B can do a work in 30 days and 10 days respectively. If they work on alternate days beginning with A, in how many days will the work be completed?
The correct Answer is:1613 days
To solve the problem step by step, we will analyze the work done by A and B, who work on alternate days, starting with A.
Step 1: Determine the work done by A and B in one day.
- A can complete the work in 30 days. Therefore, A's work in one day is:
Work done by A in one day=130 of the work
- B can complete the work in 10 days. Therefore, B's work in one day is:
Work done by B in one day=110 of the work
Step 2: Calculate the total work done in two days (one cycle of A and B).
- In the first day, A works:
Work done by A=130
- In the second day, B works:
Work done by B=110
- Therefore, the total work done in two days is:
Total work in 2 days=130+110
To add these fractions, we need a common denominator (which is 30):
110=330
So,
Total work in 2 days=130+330=430=215
Step 3: Determine how many complete cycles are needed to finish the work.
- The total work is considered as 1 unit. To find out how many cycles (2 days) are needed to complete the work, we can set up the equation:
Number of cycles=1 unit of work215 unit of work per cycle=152=7.5 cycles
Step 4: Calculate the total days taken.
- Each cycle takes 2 days, so:
Total days for 7 complete cycles=7×2=14 days
- In 14 days, the work done is:
Work done in 14 days=7×215=1415
Step 5: Calculate the remaining work and the last day.
- The remaining work after 14 days is:
Remaining work=1−1415=115
- On the 15th day, A will work again (since they alternate days). A can complete:
Work done by A on 15th day=130
- However, A can only complete 115 of the work, which is less than 130. Thus, A will finish the remaining work.
Step 6: Total days to complete the work.
- The total days taken to complete the work is:
Total days=14+1=15 days
Final Answer:
The work will be completed in 15 days.
---
- A can complete the work in 30 days. Therefore, A's work in one day is:
Work done by A in one day=130 of the work
- B can complete the work in 10 days. Therefore, B's work in one day is:
Work done by B in one day=110 of the work
- In the first day, A works:
Work done by A=130
- In the second day, B works:
Work done by B=110
Total work in 2 days=130+110
110=330
So,
Total work in 2 days=130+330=430=215
- The total work is considered as 1 unit. To find out how many cycles (2 days) are needed to complete the work, we can set up the equation:
Number of cycles=1 unit of work215 unit of work per cycle=152=7.5 cycles
- Each cycle takes 2 days, so:
Total days for 7 complete cycles=7×2=14 days
Work done in 14 days=7×215=1415
- The remaining work after 14 days is:
Remaining work=1−1415=115
Work done by A on 15th day=130
- However, A can only complete 115 of the work, which is less than 130. Thus, A will finish the remaining work.
- The total days taken to complete the work is:
Total days=14+1=15 days
The work will be completed in 15 days.
Topper's Solved these Questions
- TIME AND WORK PIPES AND CISTERNSBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK PIPES AND CISTERNSEXERCISE - Essay Type Question
5 Videos
- TIME AND WORK PIPES AND CISTERNSBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-1)
33 Videos
- TIME AND WORK PIPES AND CISTERNSBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK PIPES AND CISTERNSEXERCISE - TEST YOUR CONCEPTS (Very Short Answer Type Questions)
30 Videos
- TIME AND DISTANCE BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND DISTANCE EXERCISE - Concept Application (Level 2 )
3 Videos
- TIME AND WORK, PIPES AND CISTERNSBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK, PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-3)
7 Videos
Similar Questions
A and B working separately can do a piece of work in 10 days and 15 days respectively. If they work on alternate days beginning with A, in how many days will the work be complete?
View SolutionVianay and Vikram can complete a work in 48 and 36 days, respectively . If they work on alternate days beginning with Vinay, in how many days will the work be completed?
View Solution
Knowledge Check
Vinay and Varma can do a work in 30 days and 60 days respectively. If they work on alternate days beginning with Vinay, in how many days will the work be completed?
A45B35C40D50Vinay and Varma can do a work in 30 days and 60 days respectively. If they work on alternate days beginning with Vinay, in how many days will the work be completed?
A45B35C40D50Vinay and Varma can do a work in 30 days and 60 days respectively. If they work on alternate days beginning with Vinay, in how many days will the work be completed?
A45B35C49D50
A and B can do a piece of work in 6 days and 9 days respectively, they work on alternative days starting with A on the first day. In how many days will the work be completed ?
View SolutionA and B can do a piece of work in 6 days and 9 days respectively, they work on alternative days starting with A on the first day. In how many days will the work be completed ?
View SolutionA and B working separately can do a piece of work in 10 days and 15 days respectively. If they work on alternate days beginning with A, in how many days will the work be complete?
View SolutionP and Q can do piece of work in 10 days in 10 days and 35 days. Respectively. If they work on alternate days begnining wit Q, in how may will the work be completed?
View SolutionChandni and Divakar can do a piece of work in 9 days and 12 days respectively. If they work for a day alternatively, Chandni beginning, in how many days, the work will be completed?
View Solution