Doubtnut Promotions Sticky

A and B together can do a piece of work in 20 days, while B and C together can do the same work in 15 days. If A ,B and C together can finish this work in 10 days, then find the number of days in which B alone can finish the work.

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:60


To solve the problem step by step, we will use the information given about the work done by A, B, and C together, and then find out how long B alone would take to finish the work.

Step 1: Determine the work done by A and B together
A and B can complete the work in 20 days. Therefore, the work done by A and B in one day is:
Work done by A and B in one day=120

Step 2: Determine the work done by B and C together
B and C can complete the work in 15 days. Therefore, the work done by B and C in one day is:
Work done by B and C in one day=115

Step 3: Determine the work done by A, B, and C together
A, B, and C can complete the work in 10 days. Therefore, the work done by A, B, and C in one day is:
Work done by A, B, and C in one day=110

Step 4: Set up the equations
Let:
- Work done by A in one day = A
- Work done by B in one day = B
- Work done by C in one day = C

From the information we have, we can write the following equations:
1. A+B=120 (Equation 1)
2. B+C=115 (Equation 2)
3. A+B+C=110 (Equation 3)

Step 5: Solve the equations
We can use Equations 1 and 3 to find A.

From Equation 3:
A+B+C=110
Substituting A+B from Equation 1 into this:
120+C=110
To isolate C, we can subtract 120 from both sides:
C=110120
Finding a common denominator (20):
C=220120=120

Now we have C=120.

Step 6: Substitute C back to find A and B
Now substitute C back into Equation 2:
B+120=115
Subtract 120 from both sides:
B=115120
Finding a common denominator (60):
B=460360=160

Step 7: Find A
Now substitute B back into Equation 1:
A+160=120
Subtract 160 from both sides:
A=120160
Finding a common denominator (60):
A=360160=260=130

Step 8: Conclusion
Now we have:
- A=130
- B=160
- C=120

Thus, B alone can finish the work in:
Days taken by B=1B=60 days

Final Answer
B can finish the work alone in 60 days.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A and B together can do a work in 10 days. B and C together can do the same work in 6 days. A and C together can do the work in 12 days. Then A, B and C together can do the work in

    A28 days
    B14 days
    C5 57 days
    D8 27 days
  • Question 2 - Select One

    A and B together can do a piece of work in 10 days, B and C together can do it in 15 days while C and A together can do it in 20 days. Together they will complete the work in:

    A12 days
    B315 days
    C16 days
    D9313 days
  • Question 3 - Select One

    A and B together can do a piece of work in 4 days and A alone can do it in 6 days, B alone can do the same work in :

    A1313 days
    B12 days
    C16 days
    D11 days