A,B and C can do a work in 20,45 and 120 days respectively.They started the work. A left 10 days before and B left 5 days before the completion of work. In how many days is the total work completed ?
The correct Answer is:20
To solve the problem, we will follow these steps:
Step 1: Calculate the work done by A, B, and C in one day.
- A can complete the work in 20 days, so A's work in one day = 120.
- B can complete the work in 45 days, so B's work in one day = 145.
- C can complete the work in 120 days, so C's work in one day = 1120.
Step 2: Calculate the total work done by A, B, and C together in one day.
- Total work done in one day by A, B, and C together = 120+145+1120.
To add these fractions, we need a common denominator. The least common multiple (LCM) of 20, 45, and 120 is 180.
- Convert each fraction:
- 120=9180
- 145=4180
- 1120=1.5180=3180
Now, add them together:
- Total work done in one day = 9180+4180+3180=16180=890=445.
Step 3: Determine the work done before A and B leave.
Let the total number of days taken to complete the work be x.
- A works for x−10 days (because A leaves 10 days before completion).
- B works for x−5 days (because B leaves 5 days before completion).
- C works for all x days.
Step 4: Set up the equation for total work done.
The total work done can be expressed as:
Work done by A+Work done by B+Work done by C=1
This translates to:
(x−10)⋅120+(x−5)⋅145+x⋅1120=1
Step 5: Simplify the equation.
Substituting the values:
x−1020+x−545+x120=1
To eliminate the fractions, multiply through by the LCM of 20, 45, and 120, which is 180:
180⋅x−1020+180⋅x−545+180⋅x120=180
This simplifies to:
9(x−10)+4(x−5)+1.5x=180
Expanding this gives:
9x−90+4x−20+1.5x=180
Combining like terms:
14.5x−110=180
Adding 110 to both sides:
14.5x=290
Dividing by 14.5:
x=20
Conclusion:
The total work is completed in 20 days.
---
- A can complete the work in 20 days, so A's work in one day = 120.
- B can complete the work in 45 days, so B's work in one day = 145.
- C can complete the work in 120 days, so C's work in one day = 1120.
- Total work done in one day by A, B, and C together = 120+145+1120.
- 120=9180
- 145=4180
- 1120=1.5180=3180
- Total work done in one day = 9180+4180+3180=16180=890=445.
Let the total number of days taken to complete the work be x.
- B works for x−5 days (because B leaves 5 days before completion).
- C works for all x days.
The total work done can be expressed as:
Work done by A+Work done by B+Work done by C=1
This translates to:
(x−10)⋅120+(x−5)⋅145+x⋅1120=1
Substituting the values:
x−1020+x−545+x120=1
180⋅x−1020+180⋅x−545+180⋅x120=180
This simplifies to:
9(x−10)+4(x−5)+1.5x=180
Expanding this gives:
9x−90+4x−20+1.5x=180
Combining like terms:
14.5x−110=180
Adding 110 to both sides:
14.5x=290
Dividing by 14.5:
x=20
The total work is completed in 20 days.
Topper's Solved these Questions
- TIME AND WORK PIPES AND CISTERNSBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK PIPES AND CISTERNSEXERCISE - Essay Type Question
5 Videos
- TIME AND WORK PIPES AND CISTERNSBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-1)
33 Videos
- TIME AND WORK PIPES AND CISTERNSBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK PIPES AND CISTERNSEXERCISE - TEST YOUR CONCEPTS (Very Short Answer Type Questions)
30 Videos
- TIME AND DISTANCE BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND DISTANCE EXERCISE - Concept Application (Level 2 )
3 Videos
- TIME AND WORK, PIPES AND CISTERNSBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK, PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-3)
7 Videos
Similar Questions
A, B and C can do a work in 12, 15 and 18 days respectively. They started the work together but A left after 2 days and B left the work 3 days before the competition of work. Find the number of days it took them to complete the work.
View SolutionA, B and C can complete a piece of work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?
View Solution
Knowledge Check
A, B and C can complete a piece of work in 25, 30 and 50 days. Respectively. They started the work together But A and C left 2 days before the completion of the work. In how many days will the work is completed ?
A14B12C18D10A, B and C can complete a work in 16, 24 and 32 days, respectively. They started together but C left after 4 days of starting and A left 6 days before completion of the work. In how many days will the work be completed ?
A9 daysB15 daysC12 daysD14 daysA, B and C can do a piece of work in 20, 24 and 30 days respectively. All three of them began the work together but B left 3 days before completion of the work. In how many days was the work completed?
A7B10C12D9
A, B and C can complete a piece of-work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?
View SolutionA, B and C can do a piece of work in 24 days, 30 days and 40 days respectively. They began the work together but C left 4 days before the completion of the work. In how many days was the work completed?
View SolutionA, B and C can complete a work separately in 24, 36 and 48 days respectively. They started together but C left after 4 days of start and A left 3 days before the completion of work. In how many days will the work be completed?
View SolutionA,B andC can complete a piece of work in 6,12 and 18 days respectively. A and B started the work and C joined them after one day. B left just 2 days before the completion of the whole work.In how many days was the work completed?
View SolutionA, B and C can do a work separately in 16, 32 and 48 days respectively. They started the work together but B leaving off 8 days and C six days beofre the completion of the work. In what time is the work finished?
View Solution