A,B and C can do a work in 20,45 and 120 days respectively.They started the work. A left 10 days before and B left 5 days before the completion of work. In how many days is the total work completed ?

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:20


To solve the problem, we will follow these steps:

Step 1: Calculate the work done by A, B, and C in one day.
- A can complete the work in 20 days, so A's work in one day = 120.
- B can complete the work in 45 days, so B's work in one day = 145.
- C can complete the work in 120 days, so C's work in one day = 1120.

Step 2: Calculate the total work done by A, B, and C together in one day.
- Total work done in one day by A, B, and C together = 120+145+1120.

To add these fractions, we need a common denominator. The least common multiple (LCM) of 20, 45, and 120 is 180.

- Convert each fraction:
- 120=9180
- 145=4180
- 1120=1.5180=3180

Now, add them together:
- Total work done in one day = 9180+4180+3180=16180=890=445.

Step 3: Determine the work done before A and B leave.
Let the total number of days taken to complete the work be x.

- A works for x10 days (because A leaves 10 days before completion).
- B works for x5 days (because B leaves 5 days before completion).
- C works for all x days.

Step 4: Set up the equation for total work done.
The total work done can be expressed as:
Work done by A+Work done by B+Work done by C=1
This translates to:
(x10)120+(x5)145+x1120=1

Step 5: Simplify the equation.
Substituting the values:
x1020+x545+x120=1

To eliminate the fractions, multiply through by the LCM of 20, 45, and 120, which is 180:
180x1020+180x545+180x120=180
This simplifies to:
9(x10)+4(x5)+1.5x=180
Expanding this gives:
9x90+4x20+1.5x=180
Combining like terms:
14.5x110=180
Adding 110 to both sides:
14.5x=290
Dividing by 14.5:
x=20

Conclusion:
The total work is completed in 20 days.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A, B and C can complete a piece of work in 25, 30 and 50 days. Respectively. They started the work together But A and C left 2 days before the completion of the work. In how many days will the work is completed ?

    A14
    B12
    C18
    D10
  • A, B and C can complete a work in 16, 24 and 32 days, respectively. They started together but C left after 4 days of starting and A left 6 days before completion of the work. In how many days will the work be completed ?

    A9 days
    B15 days
    C12 days
    D14 days
  • A, B and C can do a piece of work in 20, 24 and 30 days respectively. All three of them began the work together but B left 3 days before completion of the work. In how many days was the work completed?

    A7
    B10
    C12
    D9