A can do a piece of work in 20 days while B can do it in 30 days. Both of them start the work together and work for some time, then B leaves. If A completes the remaining work in 10 days, then find the number of days for which they worked together.

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:6


To solve the problem, we will follow these steps:

Step 1: Calculate the work done by A and B in one day.
- A can complete the work in 20 days, so A's work rate is 120 of the work per day.
- B can complete the work in 30 days, so B's work rate is 130 of the work per day.

Step 2: Calculate the combined work rate of A and B.
- The combined work rate of A and B when they work together is:
Combined work rate=120+130
- To add these fractions, we need a common denominator. The least common multiple of 20 and 30 is 60.
- Converting the fractions:
120=360,130=260
- Now adding them:
Combined work rate=360+260=560=112
- This means A and B together can complete 112 of the work in one day.

Step 3: Determine the amount of work A completes alone in 10 days.
- After B leaves, A completes the remaining work in 10 days.
- The amount of work A can complete in 10 days is:
Work done by A in 10 days=10×120=1020=12
- This means A completes half of the total work alone.

Step 4: Calculate the total work done before B leaves.
- Since A completed 12 of the work alone, the remaining work done by A and B together before B left is also 12.
- Let x be the number of days they worked together. The work done by A and B together in x days is:
Work done together=x×112
- Setting this equal to the remaining work:
x×112=12

Step 5: Solve for x.
- To find x, we can multiply both sides by 12:
x=12×12=6

Conclusion:
- Therefore, A and B worked together for 6 days.

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A can do a piece of work in 30 days while B can do it in 40 days. In how many days can A and B working together do it?

    A70 days
    B4234 days
    C2717days
    D1717 days
  • A can do a piece of work in 14 days while B can do it in 28 days. In how many days, working together will they complete the whole work?

    A10.5
    B8
    C283
    D9
  • A can do a piece of work in 14 days while B can do it in 21 days. In how many days, working together they will complete the whole work?

    A10.5
    B8
    C8.4
    D9