A,B andC can complete a piece of work in 6,12 and 18 days respectively. A and B started the work and C joined them after one day. B left just 2 days before the completion of the whole work.In how many days was the work completed?
5
4
3
2
The correct Answer is:B
To solve the problem step by step, let's break it down:
Step 1: Determine the work done by A, B, and C in one day.
- A can complete the work in 6 days, so A's work per day = Total Work / Days = 36 units / 6 days = 6 units/day.
- B can complete the work in 12 days, so B's work per day = 36 units / 12 days = 3 units/day.
- C can complete the work in 18 days, so C's work per day = 36 units / 18 days = 2 units/day.
Step 2: Set up the scenario of work done.
- Let X be the total number of days taken to complete the work.
- A and B work together for the first day.
- C joins A and B after the first day.
- B leaves 2 days before the work is completed.
Step 3: Calculate the total work done.
- Work done by A and B in the first day = A's work + B's work = 6 units + 3 units = 9 units.
- After the first day, A, B, and C work together for X−2 days (since B leaves 2 days before completion).
- Work done by A, B, and C together in one day = A's work + B's work + C's work = 6 units + 3 units + 2 units = 11 units.
Step 4: Calculate the total work done in terms of X.
- Total work done in X−1 days (first day + X−2 days) = Work done on first day + Work done in X−2 days.
- Total work = 9 units (first day) + 11 units * (X - 2) days = 9 + 11(X - 2).
Step 5: Set up the equation for total work.
- Total work = 36 units (as assumed).
- Therefore, we can set up the equation:
9+11(X−2)=36
Step 6: Solve for X.
1. Expand the equation:
9+11X−22=36
2. Combine like terms:
11X−13=36
3. Add 13 to both sides:
11X=49
4. Divide by 11:
X=4911≈4.45
Since X must be a whole number, we round it up to the nearest whole number, which is 5.
Conclusion:
The work was completed in 5 days.
- A can complete the work in 6 days, so A's work per day = Total Work / Days = 36 units / 6 days = 6 units/day.
- B can complete the work in 12 days, so B's work per day = 36 units / 12 days = 3 units/day.
- C can complete the work in 18 days, so C's work per day = 36 units / 18 days = 2 units/day.
- Let X be the total number of days taken to complete the work.
- A and B work together for the first day.
- C joins A and B after the first day.
- B leaves 2 days before the work is completed.
- Work done by A and B in the first day = A's work + B's work = 6 units + 3 units = 9 units.
- After the first day, A, B, and C work together for X−2 days (since B leaves 2 days before completion).
- Work done by A, B, and C together in one day = A's work + B's work + C's work = 6 units + 3 units + 2 units = 11 units.
- Total work done in X−1 days (first day + X−2 days) = Work done on first day + Work done in X−2 days.
- Total work = 9 units (first day) + 11 units * (X - 2) days = 9 + 11(X - 2).
- Total work = 36 units (as assumed).
- Therefore, we can set up the equation:
9+11(X−2)=36
1. Expand the equation:
9+11X−22=36
2. Combine like terms:
11X−13=36
3. Add 13 to both sides:
11X=49
4. Divide by 11:
X=4911≈4.45
The work was completed in 5 days.
Topper's Solved these Questions
- TIME AND WORK, PIPES AND CISTERNSBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK, PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-3)
7 Videos
- TIME AND WORK, PIPES AND CISTERNSBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK, PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-1)
33 Videos
- TIME AND WORK PIPES AND CISTERNSBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-3)
7 Videos
Similar Questions
A, B and C can complete a work in 10, 12 and 15 days respectively. They started the work together. But A left the work 5 days before its completion. B also left the work 2 days after A left. In how many days was the work completed?
a.4
b. 15
c. 7
d. 8
View SolutionA,B and C can do a work in 20,45 and 120 days respectively.They started the work. A left 10 days before and B left 5 days before the completion of work. In how many days is the total work completed ?
View Solution
Knowledge Check
A, B and C can complete a piece of work in 27 days, 36 days, adn 45 days, respectively. B and C started the work. After 11 days. A joined them. If B left 12 days before its completion, in how many days will the work be completed?
A10B20C15D25A, B and C can complete a piece of work in 25, 30 and 50 days. Respectively. They started the work together But A and C left 2 days before the completion of the work. In how many days will the work is completed ?
A14B12C18D10A and B can do a piece of work in 30 days and 18 days respectively. A started the work alone and then after 6 days B joined him till the completion of the work. In how many days has the whole work completed?
A और B क्रमशः किसी काम को 30 दिन और 18 दिन में पूरा करते है | A किसी काम को अकेले शुरू करता है और छह दिन बाद B उसके साथ काम खत्म होने तक काम करता है | पूरा काम कितने दिन में खत्म होगा ?A12B9C15D17
A, B and C can complete a piece of-work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?
View SolutionA, B and C can complete a piece of work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?
View SolutionA, B and C can complete a work in 16, 24 and 32 days, respectively. They started together but C left after 4 days of starting and A left 6 days before completion of the work. In how many days will the work be completed ?
View SolutionA, B and C can complete a work separately in 24, 36 and 48 days respectively. They started together but C left after 4 days of start and A left 3 days before the completion of work. In how many days will the work be completed?
View SolutionA, B and C can complete a piece of work in 12, 24 and 36 days respectively. A and B will together complete the same work in how many days?
View Solution