M and N can complete a job in 120 days and 180 days respectively. M started the job and after 60 days N joined M and they completed the remaining part of the job working together.In how many days was the job completed?
88
84
96
82
The correct Answer is:C
M works for the first 60 days. Part of the job completed in the first 60 days
Remaining part =1/2.This will be completed by M and N, part of the job completed by M and N in 1 day
Time taken by them to complete the remaining part
days
The total time taken =96 days.
Topper's Solved these Questions
- TIME AND WORK, PIPES AND CISTERNSBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK, PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-3)
7 Videos
- TIME AND WORK, PIPES AND CISTERNSBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK, PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-1)
33 Videos
- TIME AND WORK PIPES AND CISTERNSBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-3)
7 Videos
Similar Questions
5 men can complete a job in 8 days. How many days will it take if 12 men do the job?
View SolutionMurali and Sai can complete a job in 20 days and 30 days respectively. Two days after they start the job, Murali leaves and Sai completes the remining job. In how many days can Sai complete the remaining job ?
View Solution
Knowledge Check
Murali and Sai can complete a job in 20 days and 30 days respectively. Two days after they start the job, Murali leaves and Sai completes the remining job. In how many days can Sai complete the remaining job ?
A20B25C15D18M and N can complete a job in 18 days and 20 days, respectively. They worked on it on alternative days starting with M. Find the time taken to comlete it (in day)
A18910B19C1835D18310Murali and Sai can complete a job in 20 days and 30 days respectively. Two days after they start the job, Murali leaves and Sai completes the remining job. In how many days can Sai complete the remaining job ?
A20B25C15D18
P,Q and R can complete a job in 18 days,24 days and 36 days respectively. P started it and worked for 3 days. P then left Q then worked on it for 8 days. Q then left. R completed the remaining part of the job in 12 days. Find the time for which R worked (in days).
View SolutionP,Q and R can complete a job in 18 days,24 days and 36 days respectively. P started it and worked for 3 days. P then left Q then worked on it for 8 days. Q then left. R completed the remaining part of the job in 12 days. Find the time for which R worked (in days).
View SolutionX can complete a job in 12 days. If X and Y work together, they can complete the job in 6 days. Y alone can complete the job in
View SolutionAshish, Binay and Joseph can do a job in 20, 30 and 40 days respectively. The three started the job together, Ashish left the job 4 days before it was completed and Binay left the job 3 days before it was completed. In how many days was the job completed?
View SolutionP,Q and R can complete a job in 18 days,24 days and 36 days respectively. P started it and worked for 3 days. P then left Q then worked on it for 8 days. Q then left. R completed the remaining part of the job in 12 days. Find the time for which R worked (in days).
View Solution