P,Q and R can do a piece of work in 18 days, 36 days and 54 day respectively. They start the work together but Q and R leave 1 day and 5 days respectively, before the completion of work. In how many days has the work been completed ?
10
11
10711
10911
The correct Answer is:B
To solve the problem step by step, we will calculate the efficiency of each worker and then determine how long they worked together before Q and R left.
Step 1: Calculate the efficiency of P, Q, and R
- P can complete the work in 18 days, so his efficiency is:
Efficiency of P=118 of the work per day
- Q can complete the work in 36 days, so his efficiency is:
Efficiency of Q=136 of the work per day
- R can complete the work in 54 days, so his efficiency is:
Efficiency of R=154 of the work per day
Step 2: Find a common total work unit
To make calculations easier, we can assume the total work is 108 units (the least common multiple of 18, 36, and 54).
Step 3: Calculate the daily work done by each worker
- P's daily work:
Work done by P in one day=10818=6 units
- Q's daily work:
Work done by Q in one day=10836=3 units
- R's daily work:
Work done by R in one day=10854=2 units
Step 4: Set up the equation for total work done
Let x be the total number of days they worked together.
- P works for x days.
- Q works for x−1 days (leaves 1 day before completion).
- R works for x−5 days (leaves 5 days before completion).
The total work done can be expressed as:
Total Work=Work by P+Work by Q+Work by R
6x+3(x−1)+2(x−5)=108
Step 5: Simplify the equation
Expanding the equation:
6x+3x−3+2x−10=108
Combining like terms:
(6x+3x+2x)−13=108
11x−13=108
Step 6: Solve for x
Adding 13 to both sides:
11x=121
Dividing by 11:
x=12111=11
Conclusion
The work has been completed in 11 days.
---
- P can complete the work in 18 days, so his efficiency is:
Efficiency of P=118 of the work per day
- Q can complete the work in 36 days, so his efficiency is:
Efficiency of Q=136 of the work per day
- R can complete the work in 54 days, so his efficiency is:
Efficiency of R=154 of the work per day
To make calculations easier, we can assume the total work is 108 units (the least common multiple of 18, 36, and 54).
- P's daily work:
Work done by P in one day=10818=6 units
- Q's daily work:
Work done by Q in one day=10836=3 units
- R's daily work:
Work done by R in one day=10854=2 units
Let x be the total number of days they worked together.
- P works for x days.
- Q works for x−1 days (leaves 1 day before completion).
- R works for x−5 days (leaves 5 days before completion).
Total Work=Work by P+Work by Q+Work by R
6x+3(x−1)+2(x−5)=108
Expanding the equation:
6x+3x−3+2x−10=108
Combining like terms:
(6x+3x+2x)−13=108
11x−13=108
Adding 13 to both sides:
11x=121
Dividing by 11:
x=12111=11
The work has been completed in 11 days.
Topper's Solved these Questions
- TIME AND WORK, PIPES AND CISTERNSBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK, PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-3)
7 Videos
- TIME AND WORK, PIPES AND CISTERNSBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK, PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-1)
33 Videos
- TIME AND WORK PIPES AND CISTERNSBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-3)
7 Videos
Similar Questions
A, B and C can finish a piece of work in 12 days, 15 days and 20 days respectively. They started working together. B left the work after working 3 days and C left the work 3 days before completion of the work. In how many days work will be finished?
View SolutionA and B can do a piece of work in 20 days and 30 days respectively. A start the work and they do this work in alternate days. In how many days will this work be completed ?
View Solution
Knowledge Check
A, B and C can complete a piece of work in 25, 30 and 50 days. Respectively. They started the work together But A and C left 2 days before the completion of the work. In how many days will the work is completed ?
A14B12C18D10A, B and C can complete a piece of work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?
A7310B1025C10730Dnone of theseA, B and C can complete a piece of-work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?
A7310B10215C10730Dnone of these
Raju can do a piece of work in 10 days, Vicky in 12 days and Tinku in 15 days. They all start the work together, but Raju leaves after 2 days and Vicky leaves 3 days before the work is completed. In how many days is the work completed?
View SolutionA, B and C can complete a piece of work in 27 days, 36 days, adn 45 days, respectively. B and C started the work. After 11 days. A joined them. If B left 12 days before its completion, in how many days will the work be completed?
View SolutionA , B and C can do a piece of work in 24days,36 days and 108 days, respectively. They started the work together but A left 9 days after the start of the work and B left 3 days before the work was completed. For how many days did C work ?
View SolutionA and B can do a piece of work together in 15 days while A alone can do it in 25 days. They start working together but B leaves 5 days before the completion of the work. For how many days did A and B work together?
View SolutionP alone can complete a work in 16 days and Q alone can complete the same work in 20 days. P and Q start the work together but Q leaves the work 7 days before the completion of work. In how many days the total work will be completed
View Solution