A and B can do a piece of work together in 15 days while A alone can do it in 25 days. They start working together but B leaves 5 days before the completion of the work. For how many days did A and B work together?
10
12
9
11
To solve the problem, we need to find out how many days A and B worked together before B left 5 days before the work was completed. Let's break it down step by step.
Step 1: Determine the work rates of A and B
- A can complete the work in 25 days. Therefore, A's work rate is:
Work rate of A=125 (work per day)
- A and B together can complete the work in 15 days. Therefore, their combined work rate is:
Work rate of A and B=115 (work per day)
Step 2: Calculate B's work rate
- We know A's work rate, so we can find B's work rate by subtracting A's work rate from their combined work rate:
Work rate of B=Work rate of A and B−Work rate of A
Work rate of B=115−125
Step 3: Find a common denominator and calculate B's work rate
- The common denominator of 15 and 25 is 75. Thus:
Work rate of A and B=575,Work rate of A=375
Work rate of B=575−375=275 (work per day)
Step 4: Calculate the total work
- The total work can be considered as 1 unit of work.
Step 5: Determine the total time taken to complete the work
- Let x be the number of days A and B worked together. After x days, B leaves, and A continues to work alone for 5 days.
- The work done by A and B together in x days is:
Work done by A and B=x(115)
- The work done by A alone in the next 5 days is:
Work done by A alone=5(125)
Step 6: Set up the equation for total work
- The total work done is equal to 1:
x(115)+5(125)=1
Step 7: Solve the equation
- Simplifying the second term:
5(125)=525=15
- Now the equation becomes:
x15+15=1
- To eliminate the fractions, multiply through by 15:
x+3=15
- Solving for x:
x=15−3=12
Conclusion
A and B worked together for 12 days.
- A can complete the work in 25 days. Therefore, A's work rate is:
Work rate of A=125 (work per day)
- A and B together can complete the work in 15 days. Therefore, their combined work rate is:
Work rate of A and B=115 (work per day)
- We know A's work rate, so we can find B's work rate by subtracting A's work rate from their combined work rate:
Work rate of B=Work rate of A and B−Work rate of A
Work rate of B=115−125
- The common denominator of 15 and 25 is 75. Thus:
Work rate of A and B=575,Work rate of A=375
Work rate of B=575−375=275 (work per day)
- The total work can be considered as 1 unit of work.
- Let x be the number of days A and B worked together. After x days, B leaves, and A continues to work alone for 5 days.
- The work done by A and B together in x days is:
Work done by A and B=x(115)
- The work done by A alone in the next 5 days is:
Work done by A alone=5(125)
- The total work done is equal to 1:
x(115)+5(125)=1
- Simplifying the second term:
5(125)=525=15
- Now the equation becomes:
x15+15=1
- To eliminate the fractions, multiply through by 15:
x+3=15
- Solving for x:
x=15−3=12
A and B worked together for 12 days.
Similar Questions
A can do a piece of work in 10 days while B can do it in 15 days. They begin together but 5 days before the completion of the work, B leaves off. Find the total number of days for the work to be completed .
View SolutionA can do a piece of work in 10 days and B in 20 days. They begin together but A leaves 2 days before the completion of the work. The whole work will be done in?
View Solution
Knowledge Check
A and B can complete a task together in 15 days, while A alone can complete it in 18.75 days. They start working together but A leaves 12.5 days before the completion of the work. For how many days did A and B work together ?
A10B13.75C12.5D11.25A can do a work in 12 days and B can do it in 18 days. They started working together. But A leaves 3 days before the work gets over. For how many days did the two work together ?
A6B5C7D7.2A can do a piece of work in 30 days while B can do it in 40 days. In how many days can A and B working together do it?
A70 daysB4234 daysC2717daysD1717 days
Kiran alone can do a piece of work in 15 days and Aman can do the same in 10 days. If they start working together, in how many days can the work be completed?
View SolutionA and B together do a piece of work in 15 days. B can do it alone in 20 days. In how many days can A do it alone.
View SolutionA can do a work in 15 days and B can do the same in 25 days. If they start the work together and B leaves 7 days before completion of the work then the work will be completed in how many days?
View SolutionA can do a piece of work in 14 days while B can do it in 21 days. In how many days, working together they will complete the whole work?
View SolutionA can do a piece of work in 14 days while B can do it in 28 days. In how many days, working together will they complete the whole work?
View Solution