A can do a piece of work in 10 days while B can do it in 15 days. They begin together but 5 days before the completion of the work, B leaves off. Find the total number of days for the work to be completed .
The correct Answer is:8 days
To solve the problem step by step, we need to find out how long A and B worked together and how long A worked alone after B left.
Step 1: Determine the work rates of A and B.
- A can complete the work in 10 days. Therefore, A's work rate is:
Work rate of A=110 of the work per day
- B can complete the work in 15 days. Therefore, B's work rate is:
Work rate of B=115 of the work per day
Step 2: Find the combined work rate of A and B.
- To find the combined work rate, we add their individual work rates:
Combined work rate=110+115
- To add these fractions, we find a common denominator, which is 30:
110=330,115=230
- Therefore,
Combined work rate=330+230=530=16 of the work per day
Step 3: Let’s denote the number of days they worked together as X.
- In X days, the amount of work they complete together is:
Work done in X days=16×X=X6
Step 4: Determine the work left after X days.
- The total work is 1 (the whole work). The work left after X days is:
Work left=1−X6
Step 5: Calculate how long A works alone after B leaves.
- B leaves 5 days before the work is completed, which means A works alone for 5 days. In 5 days, A can complete:
Work done by A in 5 days=110×5=510=12
Step 6: Set up the equation for the work left.
- The work left after X days is equal to the work A does in 5 days:
1−X6=12
Step 7: Solve for X.
- Rearranging the equation gives:
1−12=X6
12=X6
- Cross-multiplying gives:
X=3
Step 8: Calculate the total number of days for the work to be completed.
- They worked together for X=3 days, and then A worked alone for 5 days:
Total days=X+5=3+5=8
Final Answer:
The total number of days for the work to be completed is 8 days.
---
- A can complete the work in 10 days. Therefore, A's work rate is:
Work rate of A=110 of the work per day
- B can complete the work in 15 days. Therefore, B's work rate is:
Work rate of B=115 of the work per day
- To find the combined work rate, we add their individual work rates:
Combined work rate=110+115
- To add these fractions, we find a common denominator, which is 30:
110=330,115=230
- Therefore,
Combined work rate=330+230=530=16 of the work per day
- In X days, the amount of work they complete together is:
Work done in X days=16×X=X6
- The total work is 1 (the whole work). The work left after X days is:
Work left=1−X6
- B leaves 5 days before the work is completed, which means A works alone for 5 days. In 5 days, A can complete:
Work done by A in 5 days=110×5=510=12
- The work left after X days is equal to the work A does in 5 days:
1−X6=12
- Rearranging the equation gives:
1−12=X6
12=X6
- Cross-multiplying gives:
X=3
- They worked together for X=3 days, and then A worked alone for 5 days:
Total days=X+5=3+5=8
The total number of days for the work to be completed is 8 days.
Topper's Solved these Questions
- WORK AND TIME BOOK - ARIHANT SSCCHAPTER - WORK AND TIME EXERCISE - EXERCISE BASE LEVEL QUESTION
68 Videos
- WORK AND TIME BOOK - ARIHANT SSCCHAPTER - WORK AND TIME EXERCISE - EXERCISE HIGHER SKILL LEVEL QUESTION
16 Videos
- VOLUME AND SURFACE AREA BOOK - ARIHANT SSCCHAPTER - VOLUME AND SURFACE AREA EXERCISE - FAST TRACK PRACTICE
111 Videos
- WORK AND WAGES BOOK - ARIHANT SSCCHAPTER - WORK AND WAGES EXERCISE - EXERCISE (HIGHER SKILL LEVEL QUESTIONS)
7 Videos
Similar Questions
A can do a piece of work in 10 days and B in 20 days. They begin together but A leaves 2 days before the completion of the work. The whole work will be done in?
View SolutionRajan can do a piece of work in 24 days while Amit can do it in 30 days. In how many days can they complete it they work together?
View Solution
Knowledge Check
A can do a piece of work in 14 days which B can do in 21 days. They begin together but 3 days before the completion of the work, A leaves off. The total number of days to complete the work is 635 b. 812 c. 1015 d. 1312
A635daysB812daysC1015daysD1312daysRaja can do a piece of work in 14 days, while Rani can do the same work in 21 days. They started the work together but 3 days before the completion of the work, Raja left the work. The total number of days to complete the work is :
A7B8.5C5D1015A can do a piece of work in 10 days, B can do it in 15 days working together they can finish the work in :
A9B8C10D6
A can do a piece of work in 14 days while B can do it in 21 days. In how many days, working together they will complete the whole work?
View SolutionA can do a piece of work in 14 days while B can do it in 28 days. In how many days, working together will they complete the whole work?
View SolutionA and B can do a piece of work together in 15 days while A alone can do it in 25 days. They start working together but B leaves 5 days before the completion of the work. For how many days did A and B work together?
View SolutionA can do a piece of work in 15 days and B in 20 days. If they together work on it for 4 days, then the fraction of the work that is left is :
View SolutionA can do a piece of work in 30 days while B can do it in 40 days. In how many days can A and B working together do it?
View Solution