A can do a piece of work in 10 days while B can do it in 15 days. They begin together but 5 days before the completion of the work, B leaves off. Find the total number of days for the work to be completed .

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:8 days


To solve the problem step by step, we need to find out how long A and B worked together and how long A worked alone after B left.

Step 1: Determine the work rates of A and B.
- A can complete the work in 10 days. Therefore, A's work rate is:
Work rate of A=110 of the work per day
- B can complete the work in 15 days. Therefore, B's work rate is:
Work rate of B=115 of the work per day

Step 2: Find the combined work rate of A and B.
- To find the combined work rate, we add their individual work rates:
Combined work rate=110+115
- To add these fractions, we find a common denominator, which is 30:
110=330,115=230
- Therefore,
Combined work rate=330+230=530=16 of the work per day

Step 3: Let’s denote the number of days they worked together as X.
- In X days, the amount of work they complete together is:
Work done in X days=16×X=X6

Step 4: Determine the work left after X days.
- The total work is 1 (the whole work). The work left after X days is:
Work left=1X6

Step 5: Calculate how long A works alone after B leaves.
- B leaves 5 days before the work is completed, which means A works alone for 5 days. In 5 days, A can complete:
Work done by A in 5 days=110×5=510=12

Step 6: Set up the equation for the work left.
- The work left after X days is equal to the work A does in 5 days:
1X6=12

Step 7: Solve for X.
- Rearranging the equation gives:
112=X6
12=X6
- Cross-multiplying gives:
X=3

Step 8: Calculate the total number of days for the work to be completed.
- They worked together for X=3 days, and then A worked alone for 5 days:
Total days=X+5=3+5=8

Final Answer:
The total number of days for the work to be completed is 8 days.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A can do a piece of work in 14 days which B can do in 21 days. They begin together but 3 days before the completion of the work, A leaves off. The total number of days to complete the work is 635 b. 812 c. 1015 d. 1312

    A635days
    B812days
    C1015days
    D1312days
  • Raja can do a piece of work in 14 days, while Rani can do the same work in 21 days. They started the work together but 3 days before the completion of the work, Raja left the work. The total number of days to complete the work is :

    A7
    B8.5
    C5
    D1015
  • A can do a piece of work in 10 days, B can do it in 15 days working together they can finish the work in :

    A9
    B8
    C10
    D6