A can complete a work in 20 days and B in 30 days. A worked alone for 4 days and then B completed the remaining work along with C in 18 days . In how many days can C working alone complete the work ?
12
68
72
90
The correct Answer is:D
To solve the problem, we need to determine how much work A, B, and C can do individually and then find out how long C would take to complete the entire work alone.
Step 1: Determine the work done by A in 4 days.
A can complete the work in 20 days. Therefore, the work done by A in one day is:
Work done by A in 1 day=120
In 4 days, A will complete:
Work done by A in 4 days=4×120=420=15
Step 2: Calculate the remaining work after A's contribution.
The total work can be considered as 1 (the whole work). After A has completed 15 of the work, the remaining work is:
Remaining work=1−15=45
Step 3: Determine the combined work rate of B and C.
B can complete the work in 30 days, so the work done by B in one day is:
Work done by B in 1 day=130
Let C's work rate be 1C (where C can complete the work in C days). The combined work done by B and C in one day is:
Work done by B and C in 1 day=130+1C
Step 4: Calculate the work done by B and C together in 18 days.
In 18 days, B and C together complete the remaining work of 45:
Work done by B and C in 18 days=18(130+1C)=45
Step 5: Set up the equation.
Now we can set up the equation:
18(130+1C)=45
Step 6: Solve for C.
First, simplify the left side:
1830+18C=45
This simplifies to:
35+18C=45
Subtract 35 from both sides:
18C=45−35=15
Now, cross-multiply to solve for C:
18⋅5=1⋅C⟹C=90
Conclusion:
C can complete the work alone in 90 days.
Topper's Solved these Questions
- BOOK - ARIHANT SSCCHAPTER - WORK AND TIME EXERCISE - EXERCISE BASE LEVEL QUESTION68videos
WORK AND TIME
- BOOK - ARIHANT SSCCHAPTER - VOLUME AND SURFACE AREA EXERCISE - FAST TRACK PRACTICE111videos
VOLUME AND SURFACE AREA
- BOOK - ARIHANT SSCCHAPTER - WORK AND WAGES EXERCISE - EXERCISE (HIGHER SKILL LEVEL QUESTIONS)7videos
WORK AND WAGES
Similar Questions
A can complete a work in 20 days and B, in 30 days. A worked alone for 4 days and B completed the remaining work along with C in 18 days. In how many days 'C’ can working, alone complete the work?
A किसी काम को 20 दिन में समाप्त कर सकता है, और B, 30 दिन में, A अकेला 4 दिन तक काम करता है, और शेष कार्य B, C के साथ मिलकर 18 दिन में करता है। C अकेला उस काम को कितने दिन में कर सकता है।View SolutionA and B can do a piece of work in 12 days and B and C can do the same piece of work in 16 days. A work for 5 days and B work for 7 days and C complete the remaining work in 13 days then in how many days C would complete the same work?
View Solution
Knowledge Check
- Question 1 - Select One
A can do a piece of work in 34 days. He worked for 14 days and then left. B completed the remaining work in 30 days. In how many days can B alone complete the work?
A38B51C46D62 - Question 2 - Select One
A and B complete a work in 6 days. A alone can complete the work in 10 days. In how many days can B alone complete the work ?
A4B15C154D16 - Question 3 - Select One
A and B can do a work in 10 days .B and C can do the same work in 15 days . C and A can complete the same work in 20 days . In how many days can C alone complete the work ?
A120 daysB118 daysC115 daysD110 days
A and B can finish a work together in 12 days, and B and C together in 16 days. If A alone works for 5 days and then B alone continues for 7 days, then remaining work is done by C in 13 days. In how many days can C alone finish the complete work?
View SolutionA work for 2 days, then B complete the remaining work in 9 days. If A work for 3 days, then B complete the remaining work in 6 days. In how many days will A and B do this work alone ?
View Solution(A + B) can do a piece of work in 12 days. (B + C) can do same work in 16 days. A work for 5 days, B works for 7 days and C completed the remaining work in 13 days. In how many days will A, B and C do this work alone ?
View Solution(A + B) can do a piece of work in 12 days. (B + C) can do same work in 623 days. A work for 3 days, B works for 4 days and C completed the remaining work in 7 days. In how many days will A, B and C do this work alone ?
View SolutionA and B together can complete a work in 12 days. A alone works for 8 days and B alone can complete the remaining work in 20 days. Then in how many days B alone can complete the whole work?
View Solution