Reshmi can do a piece of work in 16 days. Ravina can do the same work in 1245days , while gitika can do it in 32 days. All of them started to work together but reshmi leaves after 4 days. Ravina leaves the job 3 days before the completion of the work . how long would the work last ?
9 days
6 days
16 days
5 days
The correct Answer is:A
To solve the problem, we will follow these steps:
Step 1: Determine the work done by each person in one day.
- Reshmi can complete the work in 16 days. Therefore, her work rate is:
Reshmi's work rate=1 work16 days=116 work/day
- Ravina can complete the work in 1245 days. First, convert 1245 into an improper fraction:
1245=12×5+45=60+45=645 days
Therefore, her work rate is:
Ravina's work rate=1 work645 days=564 work/day
- Gitika can complete the work in 32 days. Therefore, her work rate is:
Gitika's work rate=1 work32 days=132 work/day
Step 2: Calculate the total work done by all three in one day.
Now we will add their work rates together to find the total work done by all three in one day:
Total work rate=Reshmi's work rate+Ravina's work rate+Gitika's work rate
=116+564+132
To add these fractions, we need a common denominator. The least common multiple (LCM) of 16, 64, and 32 is 64. We convert each fraction:
116=464,564=564,132=264
Now, adding them together:
Total work rate=464+564+264=1164 work/day
Step 3: Calculate the work done in the first 4 days.
In the first 4 days, the total work done by all three is:
Work done in 4 days=4×1164=4464=1116 work
Step 4: Calculate the remaining work.
The total work is 1 (the whole work), so the remaining work after 4 days is:
Remaining work=1−1116=516 work
Step 5: Determine how many days Ravina and Gitika work.
Ravina leaves 3 days before the completion of the work. Let X be the total number of days the work lasts. Therefore, Ravina works for X−3 days.
Since Reshmi leaves after 4 days, only Ravina and Gitika work for the remaining days. The work done by Ravina and Gitika in one day is:
Ravina's work rate+Gitika's work rate=564+132=564+264=764 work/day
Step 6: Set up the equation for the remaining work.
The remaining work is done by Ravina and Gitika:
Remaining work=Work rate×Days worked
516=764×(X−4−3)
516=764×(X−7)
Step 7: Solve for X.
Cross-multiply to solve for X:
5×64=7×16×(X−7)
320=112(X−7)
320=112X−784
112X=320+784
112X=1104
X=1104112=9.857 days≈10 days
Final Answer:
The work lasts approximately 10 days.
---
- Reshmi can complete the work in 16 days. Therefore, her work rate is:
Reshmi's work rate=1 work16 days=116 work/day
1245=12×5+45=60+45=645 days
Therefore, her work rate is:
Ravina's work rate=1 work645 days=564 work/day
Gitika's work rate=1 work32 days=132 work/day
Now we will add their work rates together to find the total work done by all three in one day:
Total work rate=Reshmi's work rate+Ravina's work rate+Gitika's work rate
=116+564+132
116=464,564=564,132=264
Now, adding them together:
Total work rate=464+564+264=1164 work/day
In the first 4 days, the total work done by all three is:
Work done in 4 days=4×1164=4464=1116 work
The total work is 1 (the whole work), so the remaining work after 4 days is:
Remaining work=1−1116=516 work
Ravina leaves 3 days before the completion of the work. Let X be the total number of days the work lasts. Therefore, Ravina works for X−3 days.
Ravina's work rate+Gitika's work rate=564+132=564+264=764 work/day
The remaining work is done by Ravina and Gitika:
Remaining work=Work rate×Days worked
516=764×(X−4−3)
516=764×(X−7)
Cross-multiply to solve for X:
5×64=7×16×(X−7)
320=112(X−7)
320=112X−784
112X=320+784
112X=1104
X=1104112=9.857 days≈10 days
The work lasts approximately 10 days.
Topper's Solved these Questions
- WORK AND TIME BOOK - ARIHANT SSCCHAPTER - WORK AND TIME EXERCISE - EXERCISE BASE LEVEL QUESTION
68 Videos
- VOLUME AND SURFACE AREA BOOK - ARIHANT SSCCHAPTER - VOLUME AND SURFACE AREA EXERCISE - FAST TRACK PRACTICE
111 Videos
- WORK AND WAGES BOOK - ARIHANT SSCCHAPTER - WORK AND WAGES EXERCISE - EXERCISE (HIGHER SKILL LEVEL QUESTIONS)
7 Videos
Similar Questions
A can complete a work in 16 days, B in 12 days and C in l5 days. All of them began the work together, but A had to leave the work after 2 days of the start and B 3 days before the completion of the work. How long did the work last?
View SolutionA can do a piece of work in 9 days and B can do the same in 12 days. In how days can the work be completed if A and B work together?
View Solution
Knowledge Check
A can do a piece of work in 8 days, B can do it in 16 days, while C can do it in 80 days. In how many days they can complete the whole work, working together?
A5B6C823D2025A can do a piece of work in 16 days and B can do the same work in 20 days. In how many days can they do the same work, working together?
A819B989C889D918A and B can do a piece of work in 15 days. B and C can do the same work in 10 days and A and C can do the same in 12 days. Time taken by A, B and C together to do the job is
A4 daysB9 daysC8 daysD5 days
A can do a piece of work in 16 days and B can do the same work in 20 days. In how many days can they do the same work, working together?
View SolutionA and B together can do a piece of work in 12 days; B and C can do it in 20 days while C and A can do it in 15 days. A, B and C all working together can do it in
View SolutionA can do a piece of work in 4 days. B and C together can do it in 3 days, while A and C together can do it in 2 days. How many days will B take to do the work alone?
View SolutionA can do a piece of work in 4 days and B can complete the same work in 12 days. What is the number of days required to do the same work together?
View SolutionRaju can do a piece of work in 10 days, Vicky in 12 days and Tinku in 15 days. They all start the work together, but Raju leaves after 2 days and Vicky leaves 3 days before the work is completed. In how many days is the work completed?
View Solution