Reshmi can do a piece of work in 16 days. Ravina can do the same work in 1245days , while gitika can do it in 32 days. All of them started to work together but reshmi leaves after 4 days. Ravina leaves the job 3 days before the completion of the work . how long would the work last ?

A

9 days

B

6 days

C

16 days

D

5 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem, we will follow these steps:

Step 1: Determine the work done by each person in one day.
- Reshmi can complete the work in 16 days. Therefore, her work rate is:
Reshmi's work rate=1 work16 days=116 work/day

- Ravina can complete the work in 1245 days. First, convert 1245 into an improper fraction:
1245=12×5+45=60+45=645 days
Therefore, her work rate is:
Ravina's work rate=1 work645 days=564 work/day

- Gitika can complete the work in 32 days. Therefore, her work rate is:
Gitika's work rate=1 work32 days=132 work/day

Step 2: Calculate the total work done by all three in one day.
Now we will add their work rates together to find the total work done by all three in one day:
Total work rate=Reshmi's work rate+Ravina's work rate+Gitika's work rate
=116+564+132

To add these fractions, we need a common denominator. The least common multiple (LCM) of 16, 64, and 32 is 64. We convert each fraction:
116=464,564=564,132=264
Now, adding them together:
Total work rate=464+564+264=1164 work/day

Step 3: Calculate the work done in the first 4 days.
In the first 4 days, the total work done by all three is:
Work done in 4 days=4×1164=4464=1116 work

Step 4: Calculate the remaining work.
The total work is 1 (the whole work), so the remaining work after 4 days is:
Remaining work=11116=516 work

Step 5: Determine how many days Ravina and Gitika work.
Ravina leaves 3 days before the completion of the work. Let X be the total number of days the work lasts. Therefore, Ravina works for X3 days.

Since Reshmi leaves after 4 days, only Ravina and Gitika work for the remaining days. The work done by Ravina and Gitika in one day is:
Ravina's work rate+Gitika's work rate=564+132=564+264=764 work/day

Step 6: Set up the equation for the remaining work.
The remaining work is done by Ravina and Gitika:
Remaining work=Work rate×Days worked
516=764×(X43)
516=764×(X7)

Step 7: Solve for X.
Cross-multiply to solve for X:
5×64=7×16×(X7)
320=112(X7)
320=112X784
112X=320+784
112X=1104
X=1104112=9.857 days10 days

Final Answer:
The work lasts approximately 10 days.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A can do a piece of work in 8 days, B can do it in 16 days, while C can do it in 80 days. In how many days they can complete the whole work, working together?

    A5
    B6
    C823
    D2025
  • A can do a piece of work in 16 days and B can do the same work in 20 days. In how many days can they do the same work, working together?

    A819
    B989
    C889
    D918
  • A and B can do a piece of work in 15 days. B and C can do the same work in 10 days and A and C can do the same in 12 days. Time taken by A, B and C together to do the job is

    A4 days
    B9 days
    C8 days
    D5 days