P alone can complete a work in 16 days and Q alone can complete the same work in 20 days. P and Q start the work together but Q leaves the work 7 days before the completion of work. In how many days the total work will be completed
9 days
14 days
12 days
18 days
The correct Answer is:C
To solve the problem step by step, we will follow these calculations:
Step 1: Determine the work done by P and Q
- P can complete the work in 16 days.
- Q can complete the work in 20 days.
Step 2: Calculate the amount of work done by P and Q in one day
- Work done by P in one day = Total work / Days taken by P = 1/16 of the work.
- Work done by Q in one day = Total work / Days taken by Q = 1/20 of the work.
Step 3: Find the LCM of the days taken by P and Q
- The LCM of 16 and 20 is 80.
- We will assume the total work is 80 units.
Step 4: Calculate the daily work output
- Work done by P in one day = 80 / 16 = 5 units.
- Work done by Q in one day = 80 / 20 = 4 units.
Step 5: Calculate the combined work done by P and Q in one day
- Combined work done by P and Q in one day = Work done by P + Work done by Q = 5 + 4 = 9 units.
Step 6: Determine the total work done before Q leaves
- Let the total number of days taken to complete the work be x.
- Q leaves 7 days before the work is completed, which means Q works for x−7 days.
Step 7: Calculate the work done by P and Q together
- Work done by P and Q together for x−7 days = 9 * (x - 7).
Step 8: Calculate the work done by P alone in the last 7 days
- Work done by P alone in the last 7 days = 5 * 7 = 35 units.
Step 9: Set up the equation for total work
- Total work done = Work done by P and Q together + Work done by P alone
- 80 = 9 * (x - 7) + 35
Step 10: Solve for x
1. Rearranging the equation:
80=9x−63+35
80=9x−28
9x=80+28
9x=108
x=12
Conclusion
The total work will be completed in 12 days.
---
- P can complete the work in 16 days.
- Q can complete the work in 20 days.
- Work done by P in one day = Total work / Days taken by P = 1/16 of the work.
- Work done by Q in one day = Total work / Days taken by Q = 1/20 of the work.
- The LCM of 16 and 20 is 80.
- We will assume the total work is 80 units.
- Work done by P in one day = 80 / 16 = 5 units.
- Work done by Q in one day = 80 / 20 = 4 units.
- Combined work done by P and Q in one day = Work done by P + Work done by Q = 5 + 4 = 9 units.
- Let the total number of days taken to complete the work be x.
- Q leaves 7 days before the work is completed, which means Q works for x−7 days.
- Work done by P and Q together for x−7 days = 9 * (x - 7).
- Work done by P alone in the last 7 days = 5 * 7 = 35 units.
- Total work done = Work done by P and Q together + Work done by P alone
- 80 = 9 * (x - 7) + 35
1. Rearranging the equation:
80=9x−63+35
80=9x−28
9x=80+28
9x=108
x=12
The total work will be completed in 12 days.
Similar Questions
A can complete a work in 20 days & B can complete the same work in 25 days. If they start the work together but After 5 days A left the work . In how many days the total work would be finished ?
View SolutionC alone can complete a work in 20 days and D alone can complete the same workin 30 days. In how many days C and D together can complete the same work?
View Solution
Knowledge Check
F alone can complete a work in 24 days and G alone can complete the same work in 32 days. F and G start the work together but G leaves the work 8 days before the completion of work. In how many days the total work will be completed?
A1305 daysB1067 daysC1147 daysD1207 daysK alone can complete a work in 20 days and M alone can complete the same work in 30 days. K and M start the work together but K leaves the work after 5 days of the starting of work. In how many days M will complete the remaining work?
A352 daysB252 daysC552 daysD452 daysA alone can complete a work in 12 days and B alone can complete the same work in 24 days. In how many days can A and B together complete the same work?
A6 daysB4 daysC10 daysD8 days
P can complete a work in 15 days and Q in 24 days. They began the work together, but Q left the work 2 days before its completion. In how many days, was the work completed?
View SolutionA alone can complete a work in 6 days and B alone can complete the same work in 8 days. In how many days both A and B together can complete the same work?
View SolutionA can do a work in 10 days and B can do the same in 20 days. If they start the work together and A leaves that work 5 days before completion, in how many days the work will be finished?
View SolutionA alone can complete a work in 10 days and B alone can complete the same work in 20 days. In how many days both 4 and B together can complete half of the total work?
View SolutionA and B alone can complete work in 9 days and 18 days respectively. They worked together, however 3 days before the completion of the work A left. In how many days was the work completed ?
View Solution