Ashish, Binay and Joseph can do a job in 20, 30 and 40 days respectively. The three started the job together, Ashish left the job 4 days before it was completed and Binay left the job 3 days before it was completed. In how many days was the job completed?

A

14

B

12

C

16

D

15

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step by step, we will first determine the work done by each person per day, then calculate the total work, and finally find out how many days the job was completed.

Step 1: Determine the work done by each person per day
- Ashish can complete the job in 20 days, so his work rate is:
Work rate of Ashish=120 of the job per day
- Binay can complete the job in 30 days, so his work rate is:
Work rate of Binay=130 of the job per day
- Joseph can complete the job in 40 days, so his work rate is:
Work rate of Joseph=140 of the job per day

Step 2: Find the total work done by all three in one day
To find the combined work rate of Ashish, Binay, and Joseph, we need to find the least common multiple (LCM) of their completion times (20, 30, and 40 days). The LCM of these numbers is 120 days.

Now, we calculate the amount of work each person can do in one day based on the LCM:
- Ashish's daily work:
12020=6 units of work
- Binay's daily work:
12030=4 units of work
- Joseph's daily work:
12040=3 units of work

Total work done by all three in one day:
Total work per day=6+4+3=13 units of work

Step 3: Set up the equation based on the problem statement
Let x be the total number of days the job took to complete. According to the problem:
- Ashish left 4 days before completion, so he worked for x4 days.
- Binay left 3 days before completion, so he worked for x3 days.
- Joseph worked for the entire x days.

The total work done can be expressed as:
Work done by Ashish+Work done by Binay+Work done by Joseph=Total work
6(x4)+4(x3)+3x=120

Step 4: Solve the equation
Expanding the equation:
6x24+4x12+3x=120
Combining like terms:
(6x+4x+3x)36=120
13x36=120
Adding 36 to both sides:
13x=156
Dividing by 13:
x=12

Conclusion
The job was completed in 12 days.

Updated on:8/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • M and N can complete a job in 120 days and 180 days respectively. M started the job and after 60 days N joined M and they completed the remaining part of the job working together.In how many days was the job completed?

    A88
    B84
    C96
    D82
  • M and N can complete a job in 120 days and 180 days respectively. M started the job and after 60 days N joined M and they completed the remaining part of the job working together.In how many days was the job completed?

    A88
    B84
    C96
    D82
  • M and N can complete a job in 120 days and 180 days respectively. M started the job and after 60 days N joined M and they completed the remaining part of the job working together.In how many days was the job completed?

    A88
    B84
    C96
    D82