Three cooks have to make 80 idlis. They are known to make 20 pieces every minute working together. The first cook began working alone and made 20 pieces having worked for sometime more than three minutes. The remaining part of the work was done by the second and the third cook working together. It took a total of 8 minutes to complete the 80 idlis. How many minutes would it take the first cook alone to cook 160 idlis for a marriage party the next day?
16 minutes
24 minutes
32 minutes
40 minutes
The correct Answer is:C
To solve the problem step by step, let's break down the information provided and calculate accordingly.
Step 1: Understand the total work and rates
- The three cooks together can make 20 idlis per minute.
- They need to make a total of 80 idlis.
Step 2: Determine the time taken by the first cook
- The first cook worked alone and made 20 idlis.
- Since they make 20 idlis per minute together, the first cook must have taken a certain amount of time x to make those 20 idlis.
- We know that x must be slightly more than 3 minutes.
Step 3: Calculate the time taken by the first cook
- The first cook's rate can be calculated as follows:
Time taken by first cook=Number of idlis madeRate of making idlis
Since the first cook made 20 idlis:
x=2020=1 minute
However, since the question states that he worked for more than 3 minutes, we need to adjust our understanding.
Step 4: Calculate remaining work and time
- After the first cook made 20 idlis, there are 80−20=60 idlis left to be made.
- The total time taken to complete the work is 8 minutes. Therefore, the time taken by the second and third cooks together is:
8−x minutes
Step 5: Determine the time taken by the second and third cooks
- The second and third cooks together make 20 idlis per minute. Thus, in 8−x minutes, they can make:
20×(8−x) idlis
Setting this equal to the remaining 60 idlis:
20(8−x)=60
Simplifying gives:
8−x=3⟹x=5 minutes
Step 6: Calculate the first cook's efficiency
- The first cook takes 5 minutes to make 20 idlis, so his rate is:
Rate of first cook=20 idlis5 minutes=4 idlis per minute
Step 7: Calculate time for the first cook to make 160 idlis
- To find out how long it would take the first cook to make 160 idlis:
Time=160 idlis4 idlis per minute=40 minutes
Final Answer
The first cook would take 40 minutes to cook 160 idlis.
- The three cooks together can make 20 idlis per minute.
- They need to make a total of 80 idlis.
- The first cook worked alone and made 20 idlis.
- Since they make 20 idlis per minute together, the first cook must have taken a certain amount of time x to make those 20 idlis.
- We know that x must be slightly more than 3 minutes.
- The first cook's rate can be calculated as follows:
Time taken by first cook=Number of idlis madeRate of making idlis
Since the first cook made 20 idlis:
x=2020=1 minute
However, since the question states that he worked for more than 3 minutes, we need to adjust our understanding.
- After the first cook made 20 idlis, there are 80−20=60 idlis left to be made.
- The total time taken to complete the work is 8 minutes. Therefore, the time taken by the second and third cooks together is:
8−x minutes
- The second and third cooks together make 20 idlis per minute. Thus, in 8−x minutes, they can make:
20×(8−x) idlis
Setting this equal to the remaining 60 idlis:
20(8−x)=60
Simplifying gives:
8−x=3⟹x=5 minutes
- The first cook takes 5 minutes to make 20 idlis, so his rate is:
Rate of first cook=20 idlis5 minutes=4 idlis per minute
- To find out how long it would take the first cook to make 160 idlis:
Time=160 idlis4 idlis per minute=40 minutes
The first cook would take 40 minutes to cook 160 idlis.
Topper's Solved these Questions
- BOOK - DISHA PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - Test Yourself15videos
TIME AND WORK
- BOOK - DISHA PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - Practice Exercise (Standard Level)37videos
TIME AND WORK
- BOOK - DISHA PUBLICATIONCHAPTER - SET THEORYEXERCISE - Test Yourself15videos
SET THEORY
- BOOK - DISHA PUBLICATIONCHAPTER - TIME, SPEED AND DISTANCEEXERCISE - Test Yourself15videos
TIME, SPEED AND DISTANCE
Similar Questions
To complete a certain work, C working alone takes twice as long as A and B working together. A working alone takes 3 times as long as B and C working together. All the three together can complete the work in 5 days. How long would each take to complete th work individually?
View SolutionA can finish 80% of work done by B in 20% more time taken by B. Working together they can finish the work in 40 days. In how many days they will finish the work working alone?
View Solution
Knowledge Check
- Question 1 - Select One
A and B can together finish a work in 30 days. They worked for it for 20 days and then B left. The remaining work was done by A alone in 20 more days. A alone can finish the work in…
A48 daysB50 daysC54 daysD60 days - Question 2 - Select One
A can do a piece of work in 8 days, B can do it in 16 days, while C can do it in 80 days. In how many days they can complete the whole work, working together?
A5B6C823D2025 - Question 3 - Select One
U, V and W together can make a chair in 20 minutes. U and V together can make it in 25 minutes. How much time will (in minutes) W alone take to make the chair?
A100B90C60D120
The capacities of A,B and C to complete a piece of work is 1:2:3. By working together, the thre of them can complete the work in 24 days. In how many days can C alone complete it ?
View SolutionThe efficiencies of A, B and C are in the ratio 5: 3: 8. Working together they can complete a work in 30 days. A and B worked together for 20 days. The remaining work will be completed by C alone in:
View SolutionThe efficiences of A , B and C are in ratio 5 : 3 : 8. Working together they can complete a work in 30 days. A and B worked together for 20 days. The remaining work will be completed by C alone in :
A, B और C की कार्य क्षमता 5 : 3 : 8 है| एक साथ कार्य करते हुए, वे किसी कार्य को 30 दिनों में कर सकते हैं | A और B ने 20 दिनों तक कार्य किया | शेष कार्य पूरा करने में C को अकेले कितने दिन लगेंगे?View SolutionA can do a piece of work in 18 days and B in 12 days. They began the work together, but B left the work 3 days before its completion. In how many days, in all, was the work completed ?
View SolutionA can do a piece of work in certain number of days, while B takes three days more than A to complete the same work. Working together, A and B can complete the work in two days. How many days does B take to complete the work?
View Solution