A and B can complete a piece of work in 45 and 40 days respectively. Both started to work together, but after some days A left and B alone completed the rest work in 23 days. For how many days did A work?
12 days
10 days
8 days
9 days
The correct Answer is:D
To solve the problem step by step, we will follow these calculations:
Step 1: Determine the total work
A can complete the work in 45 days, and B can complete it in 40 days. We can find the total work in terms of work units. The least common multiple (LCM) of 45 and 40 will give us the total work.
- LCM of 45 and 40 = 360 units of work.
Step 2: Calculate the work efficiency of A and B
Next, we calculate the work efficiency of A and B.
- A's efficiency = Total work / Time taken by A = 360 / 45 = 8 units/day.
- B's efficiency = Total work / Time taken by B = 360 / 40 = 9 units/day.
Step 3: Calculate the work done by B alone
B worked alone for 23 days. We can calculate how much work B completed during this time.
- Work done by B in 23 days = B's efficiency * Number of days = 9 units/day * 23 days = 207 units.
Step 4: Calculate the remaining work
Now, we need to find out how much work is left after B has completed his part.
- Remaining work = Total work - Work done by B = 360 - 207 = 153 units.
Step 5: Calculate the combined efficiency of A and B
When A and B work together, their combined efficiency is:
- Combined efficiency = A's efficiency + B's efficiency = 8 units/day + 9 units/day = 17 units/day.
Step 6: Calculate the time taken by A and B together to finish the remaining work
Now we can find out how many days A and B worked together to complete the remaining work.
- Time taken to complete remaining work = Remaining work / Combined efficiency = 153 units / 17 units/day = 9 days.
Step 7: Conclusion
Since A and B worked together for 9 days, we conclude that A worked for 9 days before leaving the work to B.
Final Answer:
A worked for 9 days.
---
A can complete the work in 45 days, and B can complete it in 40 days. We can find the total work in terms of work units. The least common multiple (LCM) of 45 and 40 will give us the total work.
Next, we calculate the work efficiency of A and B.
- B's efficiency = Total work / Time taken by B = 360 / 40 = 9 units/day.
B worked alone for 23 days. We can calculate how much work B completed during this time.
Now, we need to find out how much work is left after B has completed his part.
When A and B work together, their combined efficiency is:
Now we can find out how many days A and B worked together to complete the remaining work.
Since A and B worked together for 9 days, we conclude that A worked for 9 days before leaving the work to B.
A worked for 9 days.
Topper's Solved these Questions
Similar Questions
A and B can do a piece of work in 45 and 40 days respectively. They began the work together, but A leaves after some days and B finished the remaining work in 23 days. After how many days did A leave
View SolutionA and B can do a piece of work in 45 and 40 days respectively. They began the work together, but A leaves after some days and B finished the remaining work in 23 days. After how many days did A leave
View Solution
Knowledge Check
A and B can do a piece of work in 28 and 35 days respectively. They began to work together but A leaves after some time and B completed the remaining work in 17 days. After how many days did A leave ?
A1425 daysB9daysC8daysD759 daysA and B can do a piece of work in 20 and 25 days respectively. They began to work together but A leaves after sometime and B completed remaining work in 17 days. After how many days did A leave?
A1425 daysB9 daysC8 daysD359 daysA, B and C can complete a piece of work in 25, 30 and 50 days. Respectively. They started the work together But A and C left 2 days before the completion of the work. In how many days will the work is completed ?
A14B12C18D10
A and B can do a piece of work in 45 and 40 days respectively. They began the work together but A leaves after some days and B finished the remaining work in 23 days. After how many days did A leave?
View SolutionA and B can do a piece of work in 45 and 40 days repectively. They began the work together but A left after some days and B finished the remaining work in 23 days. A left after
View SolutionA and B can do a piece of work in 45 and 40 days respectively. They began the work together but A leaves after some das and B finished the remaining work in 23 days. After how many days did A leave?
View SolutionA and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days, B had to leave and A alone completed the remaining work. The whole work was completed in:
View SolutionA, B and C can complete a work in 10, 12 and 15 days respectively. They started the work together. But A left the work 5 days before its completion. B also left the work 2 days after A left. In how many days was the work completed? 4 b. 15 c. 7 d. 8
View Solution