A can complete a work in 24 days, B in 32 days and C in 64 days. They start together. A works for 6 days and leaves and B leaves 6 days before the work is finished. In how many days was the work finished?
20 days
21 days
22 days
25 days
The correct Answer is:A
To solve the problem step by step, we will calculate the work done by A, B, and C, and determine how long it takes to finish the work under the given conditions.
Step 1: Determine the work rates of A, B, and C
- A can complete the work in 24 days, so A's work rate is 124 of the work per day.
- B can complete the work in 32 days, so B's work rate is 132 of the work per day.
- C can complete the work in 64 days, so C's work rate is 164 of the work per day.
Step 2: Calculate the combined work rate of A, B, and C
To find the combined work rate, we sum their individual rates:
Combined work rate=124+132+164
To add these fractions, we need a common denominator. The least common multiple (LCM) of 24, 32, and 64 is 192. We convert each fraction:
- 124=8192
- 132=6192
- 164=3192
Now, adding them together:
Combined work rate=8+6+3192=17192
So, together they can complete 17192 of the work in one day.
Step 3: Calculate the work done in the first 6 days
A works for 6 days, so the work done by A, B, and C in those 6 days is:
Work done in 6 days=6×17192=102192
This simplifies to:
102192=5196
Step 4: Calculate the remaining work
The total work is considered as 1 (or 192 units). The remaining work after 6 days is:
Remaining work=1−5196=96−5196=4596=1532
Step 5: Determine who works after A leaves
After 6 days, A leaves, and B leaves 6 days before the work is finished. This means C will work alone for the last 6 days.
Step 6: Calculate the work done by C in the last 6 days
C's work rate is 164 of the work per day. Therefore, in 6 days, C will do:
Work done by C in 6 days=6×164=664=332
Step 7: Calculate the remaining work after C's contribution
The remaining work after C works for 6 days is:
Remaining work=1532−332=1232=38
Step 8: Determine how long B and C will work together to finish the remaining work
B and C will work together to complete the remaining 38 of the work. Their combined work rate is:
B's work rate+C's work rate=132+164
Finding a common denominator (64):
132=264
Thus,
Combined work rate of B and C=264+164=364
Step 9: Calculate the time taken by B and C to finish the remaining work
To find the time t taken to finish 38 of the work:
38=t×364
Solving for t:
t=3/83/64=38×643=8 days
Step 10: Calculate the total time taken to finish the work
The total time taken to complete the work is:
Total time=6 (days A worked)+8 (days B and C worked)=14 days
Final Answer
The work was finished in 14 days.
---
- A can complete the work in 24 days, so A's work rate is 124 of the work per day.
- B can complete the work in 32 days, so B's work rate is 132 of the work per day.
- C can complete the work in 64 days, so C's work rate is 164 of the work per day.
To find the combined work rate, we sum their individual rates:
Combined work rate=124+132+164
- 124=8192
- 132=6192
- 164=3192
Combined work rate=8+6+3192=17192
So, together they can complete 17192 of the work in one day.
A works for 6 days, so the work done by A, B, and C in those 6 days is:
Work done in 6 days=6×17192=102192
This simplifies to:
102192=5196
The total work is considered as 1 (or 192 units). The remaining work after 6 days is:
Remaining work=1−5196=96−5196=4596=1532
After 6 days, A leaves, and B leaves 6 days before the work is finished. This means C will work alone for the last 6 days.
C's work rate is 164 of the work per day. Therefore, in 6 days, C will do:
Work done by C in 6 days=6×164=664=332
The remaining work after C works for 6 days is:
Remaining work=1532−332=1232=38
B and C will work together to complete the remaining 38 of the work. Their combined work rate is:
B's work rate+C's work rate=132+164
Finding a common denominator (64):
132=264
Thus,
Combined work rate of B and C=264+164=364
To find the time t taken to finish 38 of the work:
38=t×364
Solving for t:
t=3/83/64=38×643=8 days
The total time taken to complete the work is:
Total time=6 (days A worked)+8 (days B and C worked)=14 days
The work was finished in 14 days.
Topper's Solved these Questions
Similar Questions
A can do a piece of work in 10 days , B in 12 days and C in 15 days.All begin together but A leaves the work after 2 days and B leaves 3 days before the work is finished.How long did the work last?
View SolutionA can complete a work in 16 days, B in 12 days and C in l5 days. All of them began the work together, but A had to leave the work after 2 days of the start and B 3 days before the completion of the work. How long did the work last?
View Solution
Knowledge Check
Raju can do a piece of work in 10 days, Vicky in 12 days and Tinku in 15 days. They all start the work together, but Raju leaves after 2 days and Vicky leaves 3 days before the work is completed. In how many days is the work completed?
A5 daysB6 daysC7 daysD8 daysA, B and C can complete a work in 16, 24 and 32 days, respectively. They started together but C left after 4 days of starting and A left 6 days before completion of the work. In how many days will the work be completed ?
A9 daysB15 daysC12 daysD14 daysA can do a work in 12 days and B can do it in 16 days. A and B started the work jointly and A left 2 days before the work is finished. Find the number of days they took to finish the work.
A6 daysB7 daysC9 daysD8 days
A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work was done by A in:
View SolutionA can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work was done by A in:
View SolutionA can do a work in 12 days and B can do it in 18 days. They started working together. But A leaves 3 days before the work gets over. For how many days did the two work together ?
View SolutionA can complete a work in 18 days, B in 20 days and C in 30 days. B and C together start the work but after 2 days, they left the work. How many days will a take to complete the remaining work ?
View SolutionA can do a work in 10 days and B can do the same in 20 days. If they start the work together and A leaves that work 5 days before completion, in how many days the work will be finished?
View Solution