A can complete a work in 24 days, B in 32 days and C in 64 days. They start together. A works for 6 days and leaves and B leaves 6 days before the work is finished. In how many days was the work finished?

A

20 days

B

21 days

C

22 days

D

25 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step by step, we will calculate the work done by A, B, and C, and determine how long it takes to finish the work under the given conditions.

Step 1: Determine the work rates of A, B, and C
- A can complete the work in 24 days, so A's work rate is 124 of the work per day.
- B can complete the work in 32 days, so B's work rate is 132 of the work per day.
- C can complete the work in 64 days, so C's work rate is 164 of the work per day.

Step 2: Calculate the combined work rate of A, B, and C
To find the combined work rate, we sum their individual rates:
Combined work rate=124+132+164

To add these fractions, we need a common denominator. The least common multiple (LCM) of 24, 32, and 64 is 192. We convert each fraction:
- 124=8192
- 132=6192
- 164=3192

Now, adding them together:
Combined work rate=8+6+3192=17192
So, together they can complete 17192 of the work in one day.

Step 3: Calculate the work done in the first 6 days
A works for 6 days, so the work done by A, B, and C in those 6 days is:
Work done in 6 days=6×17192=102192
This simplifies to:
102192=5196

Step 4: Calculate the remaining work
The total work is considered as 1 (or 192 units). The remaining work after 6 days is:
Remaining work=15196=965196=4596=1532

Step 5: Determine who works after A leaves
After 6 days, A leaves, and B leaves 6 days before the work is finished. This means C will work alone for the last 6 days.

Step 6: Calculate the work done by C in the last 6 days
C's work rate is 164 of the work per day. Therefore, in 6 days, C will do:
Work done by C in 6 days=6×164=664=332

Step 7: Calculate the remaining work after C's contribution
The remaining work after C works for 6 days is:
Remaining work=1532332=1232=38

Step 8: Determine how long B and C will work together to finish the remaining work
B and C will work together to complete the remaining 38 of the work. Their combined work rate is:
B's work rate+C's work rate=132+164
Finding a common denominator (64):
132=264
Thus,
Combined work rate of B and C=264+164=364

Step 9: Calculate the time taken by B and C to finish the remaining work
To find the time t taken to finish 38 of the work:
38=t×364
Solving for t:
t=3/83/64=38×643=8 days

Step 10: Calculate the total time taken to finish the work
The total time taken to complete the work is:
Total time=6 (days A worked)+8 (days B and C worked)=14 days

Final Answer
The work was finished in 14 days.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Raju can do a piece of work in 10 days, Vicky in 12 days and Tinku in 15 days. They all start the work together, but Raju leaves after 2 days and Vicky leaves 3 days before the work is completed. In how many days is the work completed?

    A5 days
    B6 days
    C7 days
    D8 days
  • A, B and C can complete a work in 16, 24 and 32 days, respectively. They started together but C left after 4 days of starting and A left 6 days before completion of the work. In how many days will the work be completed ?

    A9 days
    B15 days
    C12 days
    D14 days
  • A can do a work in 12 days and B can do it in 16 days. A and B started the work jointly and A left 2 days before the work is finished. Find the number of days they took to finish the work.

    A6 days
    B7 days
    C9 days
    D8 days