Ram can do a piece of work in 20 days and Shyam in 30 days. They work together for 10 days. After that Shyam leaves and rest of the work is completed by Ram alone. How long does it take Ram to finish the remaining work?

A

3 days

B

213 days

C

313 days

D

413 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, let's break it down:

Step 1: Determine the work done by Ram and Shyam in one day
- Ram can complete the work in 20 days, so his work rate (efficiency) is:
Ram's efficiency=120 of the work per day
- Shyam can complete the work in 30 days, so his work rate (efficiency) is:
Shyam's efficiency=130 of the work per day

Step 2: Find a common time frame to compare their efficiencies
To make calculations easier, we can find a common time frame. The least common multiple (LCM) of 20 and 30 is 60 days. Therefore, we can express their efficiencies in terms of 60 days:
- In 60 days, Ram would complete:
Work done by Ram=3 (since 60/20=3)
- In 60 days, Shyam would complete:
Work done by Shyam=2 (since 60/30=2)

Step 3: Calculate the total work done together in one day
When Ram and Shyam work together, their combined efficiency is:
Combined efficiency=Ram's efficiency+Shyam's efficiency=120+130
To add these fractions, we find a common denominator (which is 60):
Combined efficiency=360+260=560=112
This means together they complete 112 of the work in one day.

Step 4: Calculate the work done in 10 days
In 10 days, the work done by both Ram and Shyam is:
Work done in 10 days=10×112=1012=56

Step 5: Determine the remaining work
The total work is considered as 1 (or 100%). After 10 days, the remaining work is:
Remaining work=156=16

Step 6: Calculate how long it takes Ram to finish the remaining work
Now, Ram will complete the remaining 16 of the work alone. Since Ram's efficiency is 120 of the work per day, we can find the time taken by Ram to finish the remaining work:
Time taken by Ram=Remaining workRam's efficiency=16120=16×20=206=103 days
This simplifies to approximately 3.33 days.

Final Answer
Ram takes 103 days, or approximately 3 days and 8 hours, to finish the remaining work.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A alone can do a plece of work in 20 days and B alone in 30 days. They begin to work together. They will finish half of the work in :

    A8 days
    B9 days
    C12 days
    D6 days
  • Question 2 - Select One

    A can do a piece of work in 10 days, B can do it in 15 days working together they can finish the work in :

    A9
    B8
    C10
    D6
  • Question 3 - Select One

    A can do a piece of work in 20 days and B in 30 days. They work together for 7 days and then both leave the work. Then Calone finIshes the remaining work in 10 days. In how many days will finish the full work?

    A25 days
    B30 days
    C24 days
    D20 days