Ram can do a piece of work in 20 days and Shyam in 30 days. They work together for 10 days. After that Shyam leaves and rest of the work is completed by Ram alone. How long does it take Ram to finish the remaining work?
3 days
213 days
313 days
413 days
The correct Answer is:C
To solve the problem step by step, let's break it down:
Step 1: Determine the work done by Ram and Shyam in one day
- Ram can complete the work in 20 days, so his work rate (efficiency) is:
Ram's efficiency=120 of the work per day
- Shyam can complete the work in 30 days, so his work rate (efficiency) is:
Shyam's efficiency=130 of the work per day
Step 2: Find a common time frame to compare their efficiencies
To make calculations easier, we can find a common time frame. The least common multiple (LCM) of 20 and 30 is 60 days. Therefore, we can express their efficiencies in terms of 60 days:
- In 60 days, Ram would complete:
Work done by Ram=3 (since 60/20=3)
- In 60 days, Shyam would complete:
Work done by Shyam=2 (since 60/30=2)
Step 3: Calculate the total work done together in one day
When Ram and Shyam work together, their combined efficiency is:
Combined efficiency=Ram's efficiency+Shyam's efficiency=120+130
To add these fractions, we find a common denominator (which is 60):
Combined efficiency=360+260=560=112
This means together they complete 112 of the work in one day.
Step 4: Calculate the work done in 10 days
In 10 days, the work done by both Ram and Shyam is:
Work done in 10 days=10×112=1012=56
Step 5: Determine the remaining work
The total work is considered as 1 (or 100%). After 10 days, the remaining work is:
Remaining work=1−56=16
Step 6: Calculate how long it takes Ram to finish the remaining work
Now, Ram will complete the remaining 16 of the work alone. Since Ram's efficiency is 120 of the work per day, we can find the time taken by Ram to finish the remaining work:
Time taken by Ram=Remaining workRam's efficiency=16120=16×20=206=103 days
This simplifies to approximately 3.33 days.
Final Answer
Ram takes 103 days, or approximately 3 days and 8 hours, to finish the remaining work.
---
- Ram can complete the work in 20 days, so his work rate (efficiency) is:
Ram's efficiency=120 of the work per day
- Shyam can complete the work in 30 days, so his work rate (efficiency) is:
Shyam's efficiency=130 of the work per day
To make calculations easier, we can find a common time frame. The least common multiple (LCM) of 20 and 30 is 60 days. Therefore, we can express their efficiencies in terms of 60 days:
- In 60 days, Ram would complete:
Work done by Ram=3 (since 60/20=3)
- In 60 days, Shyam would complete:
Work done by Shyam=2 (since 60/30=2)
When Ram and Shyam work together, their combined efficiency is:
Combined efficiency=Ram's efficiency+Shyam's efficiency=120+130
To add these fractions, we find a common denominator (which is 60):
Combined efficiency=360+260=560=112
This means together they complete 112 of the work in one day.
In 10 days, the work done by both Ram and Shyam is:
Work done in 10 days=10×112=1012=56
The total work is considered as 1 (or 100%). After 10 days, the remaining work is:
Remaining work=1−56=16
Now, Ram will complete the remaining 16 of the work alone. Since Ram's efficiency is 120 of the work per day, we can find the time taken by Ram to finish the remaining work:
Time taken by Ram=Remaining workRam's efficiency=16120=16×20=206=103 days
This simplifies to approximately 3.33 days.
Ram takes 103 days, or approximately 3 days and 8 hours, to finish the remaining work.
Topper's Solved these Questions
Similar Questions
A can do a piece of work in 20 days and B in 15 days. With help of C, they finish the work in 5 days. C can alone do the work in
View SolutionA can do a piece of work in 10 days and B in 20 days. They begin together but A leaves 2 days before the completion of the work. The whole work will be done in?
View Solution
Knowledge Check
- Question 1 - Select One
A alone can do a plece of work in 20 days and B alone in 30 days. They begin to work together. They will finish half of the work in :
A8 daysB9 daysC12 daysD6 days - Question 2 - Select One
A can do a piece of work in 10 days, B can do it in 15 days working together they can finish the work in :
A9B8C10D6 - Question 3 - Select One
A can do a piece of work in 20 days and B in 30 days. They work together for 7 days and then both leave the work. Then Calone finIshes the remaining work in 10 days. In how many days will finish the full work?
A25 daysB30 daysC24 daysD20 days
A can do a piece of work in 25 days and B can finish it in 20 days. They work together for 5 days and then A goes away. In how many days will B finish the remaining work ?
View SolutionA can do a piece of work in 12 days and B in 20 days. If they together work on it for 5 days, and remaining work is completed by C in 3 days, then in how many days can C do the same work alone?
View SolutionA can do a piece of work in 120 days and B can do it in 150 days. They work together for 20 days. Then B leaves and A alone continues the work. 12 days after that C joins A and the work is completed in 48 days more. In how many days can C do it if he works alone?
View SolutionP can do a piece of work in 20 days and Q can do the same piece of work in 60 days. They start working together and work for 5 days and then both leave the work. R alone finishes the remaining work in 10 days. In how many days will R alone finish the whole work?
View SolutionA can do a piece of work in 10 days and B can do it in 12 days. They work together for 3 days. Then B leaves and A alone continues. 2 days after that C joins and the work is completed in 2 days more. In how many days can C do it, if he works alone ?
View Solution