A and B can do a work in 12 days, Band C can do the same work in 15 days, C and A can do the same work in 20 days. The time taken by A, B and C to do the same work is

A

5 days

B

10 days

C

15 days

D

20 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem, we need to find the time taken by A, B, and C to complete the work together. We will start by determining the work done by each pair of workers and then find the combined work rate of A, B, and C.

Step 1: Determine the work rates of each pair
1. A and B can complete the work in 12 days. Therefore, their combined work rate is:
Work rate of A and B=112 (work per day)

2. B and C can complete the work in 15 days. Therefore, their combined work rate is:
Work rate of B and C=115 (work per day)

3. C and A can complete the work in 20 days. Therefore, their combined work rate is:
Work rate of C and A=120 (work per day)

Step 2: Set up equations for individual work rates
Let the work rates of A, B, and C be a, b, and c respectively. We can write the following equations based on the work rates calculated above:
1. a+b=112 (Equation 1)
2. b+c=115 (Equation 2)
3. c+a=120 (Equation 3)

Step 3: Solve the equations
We will add all three equations:
(a+b)+(b+c)+(c+a)=112+115+120
This simplifies to:
2a+2b+2c=112+115+120
Now, we need to find a common denominator for the right side. The least common multiple of 12, 15, and 20 is 60. We convert each fraction:
112=560,115=460,120=360
Adding these gives:
560+460+360=1260=15
Thus, we have:
2a+2b+2c=15
Dividing by 2:
a+b+c=110 (Equation 4)

Step 4: Find the time taken by A, B, and C together
The combined work rate of A, B, and C is 110 of the work per day. Therefore, the time taken by A, B, and C to complete the work together is:
Time=1Work rate=1110=10 days

Final Answer
The time taken by A, B, and C to do the same work is 10 days.

Updated on:7/8/2024
|


Similar Questions


Knowledge Check

  • A and B can do a piece of work in 15 days. B and C can do the same work in 10 days and A and C can do the same in 12 days. Time taken by A, B and C together to do the job is

    A4 days
    B9 days
    C8 days
    D5 days
  • If A, B and C can do a piece of work in 5 days, B, C and D can do the same work in 10 days, C, D, and A can do the same work in 15 days, D, A and B can do the same work in 30 days. Find the time taken by A+B+C+D ?

    AA)9 days
    BB)7 days
    CC)9.5 days
    DD)7.5 days
  • A and B can do a work in 10 days .B and C can do the same work in 15 days . C and A can complete the same work in 20 days . In how many days can C alone complete the work ?

    A120 days
    B118 days
    C115 days
    D110 days