A and B can do a work in 12 days, Band C can do the same work in 15 days, C and A can do the same work in 20 days. The time taken by A, B and C to do the same work is
5 days
10 days
15 days
20 days
The correct Answer is:B
To solve the problem, we need to find the time taken by A, B, and C to complete the work together. We will start by determining the work done by each pair of workers and then find the combined work rate of A, B, and C.
Step 1: Determine the work rates of each pair
1. A and B can complete the work in 12 days. Therefore, their combined work rate is:
Work rate of A and B=112 (work per day)
2. B and C can complete the work in 15 days. Therefore, their combined work rate is:
Work rate of B and C=115 (work per day)
3. C and A can complete the work in 20 days. Therefore, their combined work rate is:
Work rate of C and A=120 (work per day)
Step 2: Set up equations for individual work rates
Let the work rates of A, B, and C be a, b, and c respectively. We can write the following equations based on the work rates calculated above:
1. a+b=112 (Equation 1)
2. b+c=115 (Equation 2)
3. c+a=120 (Equation 3)
Step 3: Solve the equations
We will add all three equations:
(a+b)+(b+c)+(c+a)=112+115+120
This simplifies to:
2a+2b+2c=112+115+120
Now, we need to find a common denominator for the right side. The least common multiple of 12, 15, and 20 is 60. We convert each fraction:
112=560,115=460,120=360
Adding these gives:
560+460+360=1260=15
Thus, we have:
2a+2b+2c=15
Dividing by 2:
a+b+c=110 (Equation 4)
Step 4: Find the time taken by A, B, and C together
The combined work rate of A, B, and C is 110 of the work per day. Therefore, the time taken by A, B, and C to complete the work together is:
Time=1Work rate=1110=10 days
Final Answer
The time taken by A, B, and C to do the same work is 10 days.
1. A and B can complete the work in 12 days. Therefore, their combined work rate is:
Work rate of A and B=112 (work per day)
Work rate of B and C=115 (work per day)
Work rate of C and A=120 (work per day)
Let the work rates of A, B, and C be a, b, and c respectively. We can write the following equations based on the work rates calculated above:
1. a+b=112 (Equation 1)
2. b+c=115 (Equation 2)
3. c+a=120 (Equation 3)
We will add all three equations:
(a+b)+(b+c)+(c+a)=112+115+120
This simplifies to:
2a+2b+2c=112+115+120
Now, we need to find a common denominator for the right side. The least common multiple of 12, 15, and 20 is 60. We convert each fraction:
112=560,115=460,120=360
Adding these gives:
560+460+360=1260=15
Thus, we have:
2a+2b+2c=15
Dividing by 2:
a+b+c=110 (Equation 4)
The combined work rate of A, B, and C is 110 of the work per day. Therefore, the time taken by A, B, and C to complete the work together is:
Time=1Work rate=1110=10 days
The time taken by A, B, and C to do the same work is 10 days.
Similar Questions
A can do a work in x days and B can do the same work in y days. If x>y , then who can do more work in 6 days?
View SolutionA and B can do a certain work in 12 days, B & C can do the same work in 15 days, while A and C can do the same work in 36 days. In how many days will all three together complete that work ?
View Solution
Knowledge Check
A and B can do a piece of work in 15 days. B and C can do the same work in 10 days and A and C can do the same in 12 days. Time taken by A, B and C together to do the job is
A4 daysB9 daysC8 daysD5 daysIf A, B and C can do a piece of work in 5 days, B, C and D can do the same work in 10 days, C, D, and A can do the same work in 15 days, D, A and B can do the same work in 30 days. Find the time taken by A+B+C+D ?
AA)9 daysBB)7 daysCC)9.5 daysDD)7.5 daysA and B can do a work in 10 days .B and C can do the same work in 15 days . C and A can complete the same work in 20 days . In how many days can C alone complete the work ?
A120 daysB118 daysC115 daysD110 days
A and B can do a work in 12 days, B and C can do the same work in 15 days & C and A can do it in 20 days. In how many days they can do it separately?
View SolutionA and B can do a work in 30 days, B and C can do it in 36 days and C and A can do the same work in 45 days. In how many days A, B and C can do this work together?
View SolutionB and C can do a work in 12 days. C and D can do the same work in 18 days. D and B can do the same work in 24 days. In how many days can B, C and D together complete the work?
View SolutionA and B together can do a work in 10 days. B and C together can do the same work in 6 days. A and C together can do the work in 12 days. Then A, B and C together can do the work in
View SolutionA and B can do a piece of work in 8 days, B and C can do the same work in 12 days and A and C complete it in 8 days. In how many days A, B and C can complete the whole work, working together?
View Solution