A and B can do a work in 10 days .B and C can do the same work in 15 days . C and A can complete the same work in 20 days . In how many days can C alone complete the work ?
120 days
118 days
115 days
110 days
The correct Answer is:A
To solve the problem, we need to find out how many days C alone can complete the work given the efficiencies of A, B, and C working together in pairs. Let's break it down step by step.
Step 1: Understand the given information
- A and B can complete the work in 10 days.
- B and C can complete the work in 15 days.
- C and A can complete the work in 20 days.
Step 2: Calculate the total work
We can assume the total work to be a common multiple of the days taken by each pair. The least common multiple (LCM) of 10, 15, and 20 is 60. Thus, we can say:
- Total work = 60 units.
Step 3: Calculate the efficiencies of each pair
1. Efficiency of A and B:
A+B=60 units10 days=6 units/day
2. Efficiency of B and C:
B+C=60 units15 days=4 units/day
3. Efficiency of C and A:
C+A=60 units20 days=3 units/day
Step 4: Set up the equations
From the above calculations, we have:
1. A+B=6 (Equation 1)
2. B+C=4 (Equation 2)
3. C+A=3 (Equation 3)
Step 5: Solve the equations
To find the individual efficiencies, we can add all three equations:
(A+B)+(B+C)+(C+A)=6+4+3
This simplifies to:
2A+2B+2C=13⟹A+B+C=132=6.5 units/day
Step 6: Find the efficiency of C
Now, we can find C's efficiency using the total efficiency:
C=(A+B+C)−(A+B)=6.5−6=0.5 units/day
Step 7: Calculate the time taken by C alone
To find the time taken by C to complete the work alone, we use the formula:
Time=Total WorkEfficiency of C=60 units0.5 units/day=120 days
Conclusion
C alone can complete the work in 120 days.
---
- A and B can complete the work in 10 days.
- B and C can complete the work in 15 days.
- C and A can complete the work in 20 days.
We can assume the total work to be a common multiple of the days taken by each pair. The least common multiple (LCM) of 10, 15, and 20 is 60. Thus, we can say:
- Total work = 60 units.
1. Efficiency of A and B:
A+B=60 units10 days=6 units/day
B+C=60 units15 days=4 units/day
C+A=60 units20 days=3 units/day
From the above calculations, we have:
1. A+B=6 (Equation 1)
2. B+C=4 (Equation 2)
3. C+A=3 (Equation 3)
To find the individual efficiencies, we can add all three equations:
(A+B)+(B+C)+(C+A)=6+4+3
This simplifies to:
2A+2B+2C=13⟹A+B+C=132=6.5 units/day
Now, we can find C's efficiency using the total efficiency:
C=(A+B+C)−(A+B)=6.5−6=0.5 units/day
To find the time taken by C to complete the work alone, we use the formula:
Time=Total WorkEfficiency of C=60 units0.5 units/day=120 days
C alone can complete the work in 120 days.
Similar Questions
A and B can do a piece of work in 8 days, B and C can do the same work in 12 days. If A, B and C can complete the same work in 6 days, in how many days can A and C complete the same work?
View SolutionA and B can do a piece of work in 8 days, B and C can do the same work in 12 days. If A, B and C can complete the same work in 6 days, in how many days can A and C complete the same work?
View Solution
Knowledge Check
B and C can do a work in 12 days. C and D can do the same work in 18 days. D and B can do the same work in 24 days. In how many days can B, C and D together complete the work?
A14B134/11C144/13D12A and B can do a piece of work in 8 days, B and C can do the same work in 12 days and A and C complete it in 8 days. In how many days A, B and C can complete the whole work, working together?
A8B10C12D16A and B complete a work in 6 days. A alone can complete the work in 10 days. In how many days can B alone complete the work ?
A4B15C154D16
A and B can do a work in 12 days, B and C can do the same work in 15 days & C and A can do it in 20 days. In how many days they can do it separately?
View SolutionA and B can do a piece of work in 8 days, B and C can do the same work in 12 days and A and C complete it in 8 days. In how many days A, B and C can complete the whole work, working together?
View SolutionA alone can complete a work in 12 days and B alone can complete the same work in 24 days. In how many days can A and B together complete the same work?
View SolutionA and B can do a work in 12 days, Band C can do the same work in 15 days, C and A can do the same work in 20 days. The time taken by A, B and C to do the same work is
View SolutionA and B can do a work in 30 days, B and C can do it in 36 days and C and A can do the same work in 45 days. In how many days A, B and C can do this work together?
View Solution