Efficiency of A is 34 of B's efficiency and B's efficiency is 80% of C's efficiency. If A takes 120 more days than that of B and C working together to finish a certain piece of work. Then in how many days working together they will finish the work?

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:45 days


To solve the problem step by step, let's denote the efficiencies of A, B, and C as follows:

1. Define the efficiencies:
- Let B's efficiency be b.
- Then A's efficiency is 34b.
- B's efficiency is 80% of C's efficiency, so b=0.8c or c=b0.8=54b.

2. Calculate combined efficiency of B and C:
- The efficiency of B is b.
- The efficiency of C is 54b.
- Therefore, the combined efficiency of B and C is:
b+54b=44b+54b=94b

3. Determine the time taken by A and B+C:
- Let T be the time taken by B and C to complete the work together.
- The work done by B and C in T days is:
Work=Efficiency×Time=94b×T
- A takes 120 days more than B and C, so the time taken by A is T+120.
- The work done by A in T+120 days is:
Work=Efficiency×Time=34b×(T+120)

4. Set the work equations equal:
- Since both expressions represent the same total work, we can set them equal:
94b×T=34b×(T+120)

5. Cancel b and simplify:
- Dividing both sides by 34b (assuming b0):
94T=T+120
- Multiply through by 4 to eliminate the fraction:
9T=4T+480
- Rearranging gives:
9T4T=4805T=480T=4805=96

6. Calculate total time working together:
- The total time taken by B and C working together is T=96 days.
- Therefore, the total time taken by A, B, and C working together is:
T+120=96+120=216 days

7. Final answer:
- The total time taken by A, B, and C working together to finish the work is 216 days.

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A is twice as good a workman as B and together they finish a piece of work in 7 days. In how many days can B alone finish the work?

    A10
    B21
    C12
    D11
  • A and B together finish a work in 4 day while Aalone finishes the work girl 12 day In how many days will B finish the san work ?

    A5
    B6
    C7
    D8
  • A is twice as efficient as B and together they finish a piece of work in 18 days. How many days will A take to complete the work alone?

    A27
    B24
    C36
    D42