Efficiency of A is 34 of B's efficiency and B's efficiency is 80% of C's efficiency. If A takes 120 more days than that of B and C working together to finish a certain piece of work. Then in how many days working together they will finish the work?
The correct Answer is:45 days
To solve the problem step by step, let's denote the efficiencies of A, B, and C as follows:
1. Define the efficiencies:
- Let B's efficiency be b.
- Then A's efficiency is 34b.
- B's efficiency is 80% of C's efficiency, so b=0.8c or c=b0.8=54b.
2. Calculate combined efficiency of B and C:
- The efficiency of B is b.
- The efficiency of C is 54b.
- Therefore, the combined efficiency of B and C is:
b+54b=44b+54b=94b
3. Determine the time taken by A and B+C:
- Let T be the time taken by B and C to complete the work together.
- The work done by B and C in T days is:
Work=Efficiency×Time=94b×T
- A takes 120 days more than B and C, so the time taken by A is T+120.
- The work done by A in T+120 days is:
Work=Efficiency×Time=34b×(T+120)
4. Set the work equations equal:
- Since both expressions represent the same total work, we can set them equal:
94b×T=34b×(T+120)
5. Cancel b and simplify:
- Dividing both sides by 34b (assuming b≠0):
94T=T+120
- Multiply through by 4 to eliminate the fraction:
9T=4T+480
- Rearranging gives:
9T−4T=480⟹5T=480⟹T=4805=96
6. Calculate total time working together:
- The total time taken by B and C working together is T=96 days.
- Therefore, the total time taken by A, B, and C working together is:
T+120=96+120=216 days
7. Final answer:
- The total time taken by A, B, and C working together to finish the work is 216 days.
- Let B's efficiency be b.
- Then A's efficiency is 34b.
- B's efficiency is 80% of C's efficiency, so b=0.8c or c=b0.8=54b.
- The efficiency of B is b.
- The efficiency of C is 54b.
- Therefore, the combined efficiency of B and C is:
b+54b=44b+54b=94b
- Let T be the time taken by B and C to complete the work together.
- The work done by B and C in T days is:
Work=Efficiency×Time=94b×T
- A takes 120 days more than B and C, so the time taken by A is T+120.
- The work done by A in T+120 days is:
Work=Efficiency×Time=34b×(T+120)
- Since both expressions represent the same total work, we can set them equal:
94b×T=34b×(T+120)
- Dividing both sides by 34b (assuming b≠0):
94T=T+120
- Multiply through by 4 to eliminate the fraction:
9T=4T+480
- Rearranging gives:
9T−4T=480⟹5T=480⟹T=4805=96
- The total time taken by B and C working together is T=96 days.
- Therefore, the total time taken by A, B, and C working together is:
T+120=96+120=216 days
- The total time taken by A, B, and C working together to finish the work is 216 days.
Topper's Solved these Questions
Similar Questions
Knowledge Check
A is twice as good a workman as B and together they finish a piece of work in 7 days. In how many days can B alone finish the work?
A10B21C12D11A and B together finish a work in 4 day while Aalone finishes the work girl 12 day In how many days will B finish the san work ?
A5B6C7D8A is twice as efficient as B and together they finish a piece of work in 18 days. How many days will A take to complete the work alone?
A27B24C36D42
A is twice as good a workman as B and together they finish a piece of work in 20 days. In how many days will A alone finish the work?
View SolutionA takes 4 days more to finish certain piece of work than that of B. If working together they can finish the work in 889 days. Then in how many days working alone each can finish the work?
View SolutionA can finish 80% of work done by B in 20% more time taken by B. Working together they can finish the work in 40 days. In how many days they will finish the work working alone?
View SolutionP is 20% more efficient than Q. If Q alone can finish a work in 10 days, then in how many days will P alone finish the work?
View SolutionThe efficiency of A is thrice as that of B and efficiency of B is twice as that of C. If B alone can finish a work in 15 days, in how many days A and C together will complete that work?
View Solution