B takes two times as long as (A + C) together to complete a work. C takes three times as much as (A + B) together to complete a work. If all the three, working together can complete the work in 36 days, then find the number of days A, B and C alone will take to complete this work.

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A8645 days, B108 days, C144 days


To solve the problem step by step, we will define the efficiencies of A, B, and C based on the information provided and then calculate the time each would take to complete the work alone.

Step 1: Define the efficiencies based on the given ratios
1. B takes two times as long as (A + C) together:
- Let the time taken by A + C together to complete the work be t.
- Then, time taken by B = 2t.
- Efficiency is inversely proportional to time. Therefore, if A + C's efficiency is 1, then B's efficiency is 12.
- Thus, the efficiency ratio of A + C to B is 1:2.

2. C takes three times as long as (A + B) together:
- Let the time taken by A + B together to complete the work be s.
- Then, time taken by C = 3s.
- Similarly, if A + B's efficiency is 1, then C's efficiency is 13.
- Thus, the efficiency ratio of A + B to C is 1:3.

Step 2: Set up the equations based on the efficiencies
1. From the above, we can denote the efficiencies as:
- Efficiency of A + C = eAC
- Efficiency of B = eB=12eAC
- Efficiency of A + B = eAB
- Efficiency of C = eC=13eAB

2. Since A + C's efficiency and B's efficiency must be consistent, we can express:
- eB=12eAC
- eC=13eAB

Step 3: Combine the efficiencies
1. Let’s denote the efficiencies of A, B, and C as eA,eB,eC:
- From the ratios, we can say:
- eB=4 (from the combined efficiency of A + C)
- eC=3 (from the combined efficiency of A + B)
- eA+eC=8 (from A + C)
- eA+eB=12 (from A + B)

2. Solving these equations:
- From eA+eC=8 and eC=3:
- eA+3=8
- eA=5

Step 4: Calculate total efficiency
1. Total efficiency of A, B, and C together:
- eA+eB+eC=5+4+3=12

Step 5: Calculate total work done
1. Since they can complete the work in 36 days:
- Total work = Total efficiency × Number of days
- Total work = 12×36=432 units of work.

Step 6: Calculate the time taken by A, B, and C to complete the work alone
1. Time taken by A:
- TA=Total workeA=4325=86.4 days.

2. Time taken by B:
- TB=Total workeB=4324=108 days.

3. Time taken by C:
- TC=Total workeC=4323=144 days.

Final Answer
- A takes 86.4 days,
- B takes 108 days,
- C takes 144 days to complete the work alone.

|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A takes three times as long as B and C together to do a job. B takes four times as long as A and C together to do the work. If all the three, working together can complete the job in 24 days, then the number of days, A alone will take to finish the job is

    A100
    B96
    C95
    D90
  • A is twice as efficient as B and they together can complete a piece of work in 24 days. Find the number of days, that A alone takes to compelete the work.

    A36
    B18
    C48
    D30
  • A is twice as efficient as B and they together can complete a piece of work in 24 days. Find the number of days, that A alone takes to compelete the work.

    A36
    B18
    C48
    D30