B takes two times as long as (A + C) together to complete a work. C takes three times as much as (A + B) together to complete a work. If all the three, working together can complete the work in 36 days, then find the number of days A, B and C alone will take to complete this work.
The correct Answer is:A→8645 days, B→108 days, C→144 days
To solve the problem step by step, we will define the efficiencies of A, B, and C based on the information provided and then calculate the time each would take to complete the work alone.
Step 1: Define the efficiencies based on the given ratios
1. B takes two times as long as (A + C) together:
- Let the time taken by A + C together to complete the work be t.
- Then, time taken by B = 2t.
- Efficiency is inversely proportional to time. Therefore, if A + C's efficiency is 1, then B's efficiency is 12.
- Thus, the efficiency ratio of A + C to B is 1:2.
2. C takes three times as long as (A + B) together:
- Let the time taken by A + B together to complete the work be s.
- Then, time taken by C = 3s.
- Similarly, if A + B's efficiency is 1, then C's efficiency is 13.
- Thus, the efficiency ratio of A + B to C is 1:3.
Step 2: Set up the equations based on the efficiencies
1. From the above, we can denote the efficiencies as:
- Efficiency of A + C = eAC
- Efficiency of B = eB=12eAC
- Efficiency of A + B = eAB
- Efficiency of C = eC=13eAB
2. Since A + C's efficiency and B's efficiency must be consistent, we can express:
- eB=12eAC
- eC=13eAB
Step 3: Combine the efficiencies
1. Let’s denote the efficiencies of A, B, and C as eA,eB,eC:
- From the ratios, we can say:
- eB=4 (from the combined efficiency of A + C)
- eC=3 (from the combined efficiency of A + B)
- eA+eC=8 (from A + C)
- eA+eB=12 (from A + B)
2. Solving these equations:
- From eA+eC=8 and eC=3:
- eA+3=8
- eA=5
Step 4: Calculate total efficiency
1. Total efficiency of A, B, and C together:
- eA+eB+eC=5+4+3=12
Step 5: Calculate total work done
1. Since they can complete the work in 36 days:
- Total work = Total efficiency × Number of days
- Total work = 12×36=432 units of work.
Step 6: Calculate the time taken by A, B, and C to complete the work alone
1. Time taken by A:
- TA=Total workeA=4325=86.4 days.
2. Time taken by B:
- TB=Total workeB=4324=108 days.
3. Time taken by C:
- TC=Total workeC=4323=144 days.
Final Answer
- A takes 86.4 days,
- B takes 108 days,
- C takes 144 days to complete the work alone.
1. B takes two times as long as (A + C) together:
- Let the time taken by A + C together to complete the work be t.
- Then, time taken by B = 2t.
- Efficiency is inversely proportional to time. Therefore, if A + C's efficiency is 1, then B's efficiency is 12.
- Thus, the efficiency ratio of A + C to B is 1:2.
- Let the time taken by A + B together to complete the work be s.
- Then, time taken by C = 3s.
- Similarly, if A + B's efficiency is 1, then C's efficiency is 13.
- Thus, the efficiency ratio of A + B to C is 1:3.
1. From the above, we can denote the efficiencies as:
- Efficiency of A + C = eAC
- Efficiency of B = eB=12eAC
- Efficiency of A + B = eAB
- Efficiency of C = eC=13eAB
- eB=12eAC
- eC=13eAB
1. Let’s denote the efficiencies of A, B, and C as eA,eB,eC:
- From the ratios, we can say:
- eB=4 (from the combined efficiency of A + C)
- eC=3 (from the combined efficiency of A + B)
- eA+eC=8 (from A + C)
- eA+eB=12 (from A + B)
- From eA+eC=8 and eC=3:
- eA+3=8
- eA=5
1. Total efficiency of A, B, and C together:
- eA+eB+eC=5+4+3=12
1. Since they can complete the work in 36 days:
- Total work = Total efficiency × Number of days
- Total work = 12×36=432 units of work.
1. Time taken by A:
- TA=Total workeA=4325=86.4 days.
- TB=Total workeB=4324=108 days.
- TC=Total workeC=4323=144 days.
- A takes 86.4 days,
- B takes 108 days,
- C takes 144 days to complete the work alone.
Topper's Solved these Questions
Similar Questions
A takes three times as long as (B + C) together to complete a work. B takes four times as much as (A + C) together to complete a work. If all the three, working together can complete the work in 22 days, then find the number of days A, B and C alone will take to complete this work
View SolutionB takes two times time as long as (A + C) together take to complete a work C takes three times time as much as (A + B) together take to complete a work. If all three working together can complete the work in 25 days. Then find the number of days in which A, B and C can complete the work individually.
View Solution
Knowledge Check
A takes three times as long as B and C together to do a job. B takes four times as long as A and C together to do the work. If all the three, working together can complete the job in 24 days, then the number of days, A alone will take to finish the job is
A100B96C95D90A is twice as efficient as B and they together can complete a piece of work in 24 days. Find the number of days, that A alone takes to compelete the work.
A36B18C48D30A is twice as efficient as B and they together can complete a piece of work in 24 days. Find the number of days, that A alone takes to compelete the work.
A36B18C48D30
A takes 27 days more than (A + B) together to complete a work. B takes 3 days more than (A + B) together to complete a work. In how many days will (A + B) complete this work ?
View SolutionA takes 412 days more than (A + B) together to complete a work. B takes 8 days more than (A + B) together to complete a work. In how many days will (A + B) complete this work ?
View SolutionA is twice as efficient as B and they together can complete a piece of work in 24 days. Find the number of days, that A alone takes to compelete the work.
View SolutionA work three times as fast as B.B takes 56 days more than A to complete a work. Working together in how days can they complete the work?
View SolutionA and B together can complete a work in 8 days . B alone can complete that work in 12 days. B alone worked for four days. After that how long will A alone take to complete the work?
View Solution