A and B together can complete a work in 8 days . B alone can complete that work in 12 days. B alone worked for four days. After that how long will A alone take to complete the work?

A

15 days

B

18 days

C

16 days

D

20 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, we will follow these calculations:

Step 1: Determine the work rates of A and B
- A and B together can complete the work in 8 days.
- Therefore, their combined work rate is:
Work rate of A and B=18 work per day

- B alone can complete the work in 12 days.
- Therefore, B's work rate is:
Work rate of B=112 work per day

Step 2: Find A's work rate
- To find A's work rate, we subtract B's work rate from the combined work rate:
Work rate of A=Work rate of A and BWork rate of B
Work rate of A=18112

- To perform this subtraction, we need a common denominator, which is 24:
18=324,112=224
Work rate of A=324224=124 work per day

Step 3: Calculate the work done by B in 4 days
- B worked alone for 4 days. The amount of work done by B in those 4 days is:
Work done by B=Work rate of B×Number of days worked
Work done by B=112×4=412=13

Step 4: Determine the remaining work
- The total work is considered as 1 unit. After B has completed 13 of the work, the remaining work is:
Remaining work=113=23

Step 5: Calculate the time A will take to complete the remaining work
- A's work rate is 124 work per day. To find out how long A will take to complete the remaining 23 of the work, we use:
Time taken by A=Remaining workWork rate of A
Time taken by A=23124=23×24=16 days

Final Answer
A will take 16 days to complete the remaining work.

---

|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A alone can complete a piece of work in 12 days. A and B together can complete it in 8 days. How long will B alone take to complete the work ?

    A18 days
    B24 days
    C16 days
    D20 days
  • A and B together can do a piece of work in 8 days. B alone can do it in 12 days. B alone works at it for 4 days. In how many more days after that could A alone complete it.

    A15 days
    B18 days
    C16 days
    D20 days
  • U, V and W together can complete a work in 10 days. If U alone can complete the work in 20 days and V alone can complete the work in 30 days, then in how many days W alone can complete the work?

    AA)30
    BB)40
    CC)60
    DD)80