A can complete a piece of work in 10 days, B in 15 days and C in 20 days. A and C worked together for two days and then A was replaced by B. In how many days, altogether, was the work completed ?

A

12 days

B

10 days

C

6 days

D

8 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem step by step, let's break down the work done by A, B, and C and how the work progresses over the days.

Step 1: Determine the work done by A, B, and C in one day.
- A can complete the work in 10 days, so in one day, A does:
Work done by A in one day=110 of the work
- B can complete the work in 15 days, so in one day, B does:
Work done by B in one day=115 of the work
- C can complete the work in 20 days, so in one day, C does:
Work done by C in one day=120 of the work

Step 2: Calculate the total work done by A and C together in one day.
- The combined work done by A and C in one day is:
Work done by A and C in one day=110+120
To add these fractions, we find a common denominator (which is 20):
=220+120=320

Step 3: Calculate the work done by A and C in 2 days.
- In 2 days, A and C together will complete:
Work done in 2 days=2×320=620=310

Step 4: Determine the remaining work after A and C have worked for 2 days.
- The total work is considered as 1 (or 100% of the work). Therefore, the remaining work after A and C have completed 310 of the work is:
Remaining work=1310=710

Step 5: Calculate the work done by B and C together in one day.
- Now, A is replaced by B. The combined work done by B and C in one day is:
Work done by B and C in one day=115+120
To add these fractions, we find a common denominator (which is 60):
=460+360=760

Step 6: Determine how many days B and C will take to complete the remaining work.
- The remaining work is 710. To find out how many days it will take for B and C to complete this work, we set up the equation:
Days=Remaining workWork done by B and C in one day=710760=710×607=6 days

Step 7: Calculate the total time taken to complete the work.
- The total time taken to complete the work is the time A and C worked together plus the time B and C worked together:
Total time=2 days+6 days=8 days

Final Answer:
The total time taken to complete the work is 8 days.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A can do a piece of work in 18 days and B in 12 days. They began the work together, but B left the work 3 days before its completion. In how many days, in all, was the work completed ?

    A12
    B10
    C9.6
    D9
  • A and B can complete a piece of work in 15 days and 10 days, respectively . They work together for 4 days and then B leavs. In how many days will A alone complete the remaining work ?

    A6
    B8
    C5
    D10
  • A can complete a piece of work in 18 days, B in 20 days and C in 30 days. B and C together start the work and are forced to leave after 2 days. The time taken by A alone to complete the remaining work is

    A10 days
    B12 days
    C15 days
    D16 days