A and B can do a work in 12 days, B and C in 15 days and C and A in 20 days. If A, B and C work together, they will complete the work in :

A

5 days

B

756 days

C

10 days

D

1523 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, we will first determine the work rates of A, B, and C based on the information given.

Step 1: Determine the work rates of A and B, B and C, and C and A.

- A and B can complete the work in 12 days. Therefore, their combined work rate is:
Work rate of A and B=112 (work per day)

- B and C can complete the work in 15 days. Therefore, their combined work rate is:
Work rate of B and C=115 (work per day)

- C and A can complete the work in 20 days. Therefore, their combined work rate is:
Work rate of C and A=120 (work per day)

Step 2: Set up equations for the work rates.

Let the work rates of A, B, and C be represented as a, b, and c respectively. We can write the following equations based on the work rates:

1. a+b=112 (Equation 1)
2. b+c=115 (Equation 2)
3. c+a=120 (Equation 3)

Step 3: Add all three equations.

Adding all three equations together gives us:
(a+b)+(b+c)+(c+a)=112+115+120
This simplifies to:
2a+2b+2c=112+115+120

Step 4: Calculate the right-hand side.

To add the fractions on the right-hand side, we need a common denominator. The least common multiple of 12, 15, and 20 is 60.

Converting each fraction:
- 112=560
- 115=460
- 120=360

Now, adding these fractions:
560+460+360=1260=15

Step 5: Substitute back into the equation.

Now substituting back, we have:
2(a+b+c)=15
Dividing both sides by 2:
a+b+c=110

Step 6: Find the time taken by A, B, and C to complete the work together.

If A, B, and C together can complete 110 of the work in one day, then the time taken to complete the entire work is the reciprocal of their combined work rate:
Time=1110=10 days

Final Answer:
If A, B, and C work together, they will complete the work in 10 days.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A and B can do a work in 12 days, B and C in 15 days, C and A in 20 days. If A, B and C Work together, they will complete the work in :

    A5 days
    B756 days
    C10 days
    D1523 days
  • A and B can do a work in 12 days .B and C in 15 days .C and A in 20 days. If A,B and C work together ,they will complete the work in :

    A5 days
    B756 days
    C10 days
    D1523days
  • A and B can do a piece of work in 10 days, B and C in 15 days and C and A in 20 days. C alone can do the work in :

    A60 days
    B120 days
    C80 days
    D30 days