A and B can do a work in 12 days, B and C in 15 days, C and A in 20 days. If A, B and C Work together, they will complete the work in :
5 days
756 days
10 days
1523 days
The correct Answer is:C
To solve the problem, we need to find out how long it will take for A, B, and C to complete the work together based on the information given about their pairs.
1. Understanding the Work Rates:
- A and B can complete the work in 12 days.
- B and C can complete the work in 15 days.
- C and A can complete the work in 20 days.
2. Finding the Work Done in Units:
- Let's assume the total work is 60 units (this is a common multiple of 12, 15, and 20).
- Therefore, the work rates for each pair can be calculated as follows:
- A + B = 60 units in 12 days → (60/12) = 5 units/day
- B + C = 60 units in 15 days → (60/15) = 4 units/day
- C + A = 60 units in 20 days → (60/20) = 3 units/day
3. Setting Up the Equations:
- From the above, we can set up the following equations based on the work rates:
- (1) A + B = 5 (units/day)
- (2) B + C = 4 (units/day)
- (3) C + A = 3 (units/day)
4. Solving the Equations:
- To find the individual work rates, we can add all three equations:
(A+B)+(B+C)+(C+A)=5+4+3
This simplifies to:
2A+2B+2C=12
Dividing by 2:
A+B+C=6(4)
5. Finding Individual Work Rates:
- Now, we can use equation (4) to find the individual work rates:
- From (1): A + B = 5 → C = 6 - 5 = 1
- From (2): B + C = 4 → B = 4 - 1 = 3
- From (3): C + A = 3 → A = 3 - 1 = 2
6. Final Work Rates:
- A = 2 units/day
- B = 3 units/day
- C = 1 unit/day
7. Combined Work Rate:
- Now, we can find the combined work rate of A, B, and C:
A+B+C=2+3+1=6 units/day
8. Calculating Total Time:
- Since the total work is 60 units and their combined work rate is 6 units/day, the time taken to complete the work together is:
Time=Total WorkCombined Work Rate=606=10 days
Conclusion:
A, B, and C will complete the work together in 10 days.
- A and B can complete the work in 12 days.
- B and C can complete the work in 15 days.
- C and A can complete the work in 20 days.
- Let's assume the total work is 60 units (this is a common multiple of 12, 15, and 20).
- Therefore, the work rates for each pair can be calculated as follows:
- A + B = 60 units in 12 days → (60/12) = 5 units/day
- B + C = 60 units in 15 days → (60/15) = 4 units/day
- C + A = 60 units in 20 days → (60/20) = 3 units/day
- From the above, we can set up the following equations based on the work rates:
- (1) A + B = 5 (units/day)
- (2) B + C = 4 (units/day)
- (3) C + A = 3 (units/day)
- To find the individual work rates, we can add all three equations:
(A+B)+(B+C)+(C+A)=5+4+3
This simplifies to:
2A+2B+2C=12
Dividing by 2:
A+B+C=6(4)
- Now, we can use equation (4) to find the individual work rates:
- From (1): A + B = 5 → C = 6 - 5 = 1
- From (2): B + C = 4 → B = 4 - 1 = 3
- From (3): C + A = 3 → A = 3 - 1 = 2
- A = 2 units/day
- B = 3 units/day
- C = 1 unit/day
- Now, we can find the combined work rate of A, B, and C:
A+B+C=2+3+1=6 units/day
- Since the total work is 60 units and their combined work rate is 6 units/day, the time taken to complete the work together is:
Time=Total WorkCombined Work Rate=606=10 days
A, B, and C will complete the work together in 10 days.
Topper's Solved these Questions
Similar Questions
A and B can do a piece of work in 12 days, B and C in 15 days and C and A in 20 days. In how many days can they do it, all working together?
View SolutionA and B can do a piece of work in 12 days, B and C in 15 days and C and A in 20 days. In how many days can they do it, all working together?
View Solution
Knowledge Check
A and B can do a work in 12 days, B and C in 15 days and C and A in 20 days. If A, B and C work together, they will complete the work in :
A5 daysB756 daysC10 daysD1523 daysA and B can do a piece of work in 12 days, B and C in 15 days, C and A in 20 days. In what time can A do it separately?
A1523B24 daysC30 daysD40 daysA and B can do a piece of work in 10 days, B and C in 15 days and C and A in 20 days. Calone can do the work in :
A60 daysB120 daysC80 daysD30 days
A and B can do a piece of work in 12 days, B and C in 15 days and C and A in 20 days. In how many days can they do it, all working together?
View SolutionA and B can do a piece of work in 10 days, B and C in 15 days and C and A in 20 days. C alone can do the work in :
View SolutionA and B can do a piece of work in 10 days, B and C in 15 days and C and A in 20 days. C alone can do the work in :
View SolutionA and B can do a piece of work in 12 days, B and C in 15 days and A and C in 20 days. In how many days can each alone do the work?
View SolutionA and B can complete a piece of work in 8 days, B and C can do it in 12 days, C and A can do it in 8 days. A, B and C together can complete it in
View Solution