P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how man days can they complete the work ?
5511
5611
6511
6611
The correct Answer is:A
To solve the problem step by step, let's break it down:
Step 1: Calculate the total work done by P and Q in hours.
- P can complete the work in 12 days, working 8 hours a day.
- Total hours worked by P = 12 days * 8 hours/day = 96 hours.
- Q can complete the work in 8 days, working 10 hours a day.
- Total hours worked by Q = 8 days * 10 hours/day = 80 hours.
Step 2: Determine the work done by P and Q in one hour.
- Work done by P in one hour = 1/96 (since he completes the work in 96 hours).
- Work done by Q in one hour = 1/80 (since he completes the work in 80 hours).
Step 3: Calculate the combined work done by P and Q in one hour.
- Combined work done by P and Q in one hour = (1/96 + 1/80).
- To add these fractions, we need a common denominator. The least common multiple (LCM) of 96 and 80 is 480.
Calculating the fractions:
- Work done by P in one hour = 1/96 = 5/480.
- Work done by Q in one hour = 1/80 = 6/480.
Now, adding these:
- Combined work = (5/480 + 6/480) = 11/480.
Step 4: Calculate the total time taken to complete the work when they work together for 8 hours a day.
- In one hour, P and Q together complete 11/480 of the work.
- In 8 hours, they complete:
8×11480=88480=1160 of the work.
Step 5: Calculate the total days required to complete the work.
- To find out how many days it will take to complete the entire work (1 unit of work), we set up the equation:
Total days=1 (total work)1160 (work done in one day)
Total days=6011 days.
Step 6: Convert the total days into mixed fraction.
- Dividing 60 by 11 gives us 5 with a remainder of 5.
- Therefore, the answer in mixed fraction form is:
5511 days.
Final Answer:
P and Q can complete the work together in 6011 days or 5511 days.
---
- P can complete the work in 12 days, working 8 hours a day.
- Total hours worked by P = 12 days * 8 hours/day = 96 hours.
- Q can complete the work in 8 days, working 10 hours a day.
- Total hours worked by Q = 8 days * 10 hours/day = 80 hours.
- Work done by P in one hour = 1/96 (since he completes the work in 96 hours).
- Work done by Q in one hour = 1/80 (since he completes the work in 80 hours).
- Combined work done by P and Q in one hour = (1/96 + 1/80).
- To add these fractions, we need a common denominator. The least common multiple (LCM) of 96 and 80 is 480.
- Work done by P in one hour = 1/96 = 5/480.
- Work done by Q in one hour = 1/80 = 6/480.
- Combined work = (5/480 + 6/480) = 11/480.
- In one hour, P and Q together complete 11/480 of the work.
- In 8 hours, they complete:
8×11480=88480=1160 of the work.
- To find out how many days it will take to complete the entire work (1 unit of work), we set up the equation:
Total days=1 (total work)1160 (work done in one day)
Total days=6011 days.
- Dividing 60 by 11 gives us 5 with a remainder of 5.
- Therefore, the answer in mixed fraction form is:
5511 days.
P and Q can complete the work together in 6011 days or 5511 days.
Topper's Solved these Questions
Similar Questions
Uday working 4 hours a day completes a work in 10 days, while Subhash working 8 hours a day can complete the same work in 15 days. How many days will it take for both of them working together 10 hours a day to complete the work ?
View SolutionWorking 5 hours a day. A can complete a work in 8 days and working 6 hours a day, B can complete the same work in 10 days. Working 8 hours a day, they can jointly complete the work in
View Solution
Knowledge Check
A can complete a work in 12 days with a working of 8 hours per day. B can complete the same work in 8 days when working 10 hours a day. If Both start the work together, working 8 hours a day, the work can be completed in __ days.
A5511B4511C6411D6511Working 2 hours in a day, P can complete a work in 10 days and working 5 hours in a day, Q can complete the same work in 6 days. Working 3 hours in a day, in how many days both P and Q together can complete the same work?
A3 daysB6 daysC4 daysD5 daysWorking 5 hours a day. A can' complete a work in 8 days and working 6 hours a day, B can complete the same work in 10 days. Working 8 hours a day, they can jointly complete the work in
A3 daysB4 daysC4.5 daysD5.4 days
A can do a piece of work in 6 days working 8 hours a day while B can do the same work in 4 days working 10 hours a day. If the work has to be completed in 5 days, so how many hours do they need to work together in a days?
View SolutionA can do a piece of work in 6 days working 8 hours a day while B can do the same work in 4 days working 10 hours a day. If the work has to be completed in 5 days, so how many hours do they need to work together in a days?
View SolutionMohan can complete a job in 8 days working 9 hourse a day. Sohan can complte it in I daays wrorking 10 hours a day. In how many days can Mohan and Sohan together complete it working 8 hours a day ?
View SolutionA alone can complete a work in 6 days and B alone can complete the same work in 8 days. In how many days both A and B together can complete the same work?
View SolutionA man working 8 hours a day takes 5 days to complete a project. How many hours a day must he work to complete. It in 4 days?
View Solution