A and B can do a piece of work in 12 days, B and C in 15 days and C and A in 20 days. In how many days can they do it, all working together?
The correct Answer is:10
To solve the problem, we need to find the individual work rates of A, B, and C based on the information given about their combined work rates. Here’s the step-by-step solution:
Step 1: Determine the work rates of A, B, and C
Let the total work be represented as 1 unit.
- A and B together can complete the work in 12 days.
- Work rate of A and B = 1/12 units of work per day.
- B and C together can complete the work in 15 days.
- Work rate of B and C = 1/15 units of work per day.
- C and A together can complete the work in 20 days.
- Work rate of C and A = 1/20 units of work per day.
Step 2: Set up equations based on work rates
Let the work rates of A, B, and C be represented as:
- Work rate of A = a
- Work rate of B = b
- Work rate of C = c
From the above information, we can set up the following equations:
1. a+b=112 (Equation 1)
2. b+c=115 (Equation 2)
3. c+a=120 (Equation 3)
Step 3: Solve the equations
To find the individual work rates, we can add all three equations together:
(a+b)+(b+c)+(c+a)=112+115+120
This simplifies to:
2a+2b+2c=112+115+120
Step 4: Calculate the right-hand side
To add the fractions, we need a common denominator. The least common multiple of 12, 15, and 20 is 60.
- Convert each fraction:
- 112=560
- 115=460
- 120=360
Now, add them:
560+460+360=1260=15
Step 5: Solve for a + b + c
Now we have:
2(a+b+c)=15
Dividing both sides by 2 gives:
a+b+c=110
Step 6: Calculate the total time for A, B, and C to work together
The combined work rate of A, B, and C is 110 units of work per day. Therefore, the time taken for all three to complete the work together is:
Time=Total WorkCombined Work Rate=1110=10 days
Final Answer
A, B, and C can complete the work together in 10 days.
---
Let the total work be represented as 1 unit.
- Work rate of A and B = 1/12 units of work per day.
- Work rate of B and C = 1/15 units of work per day.
- Work rate of C and A = 1/20 units of work per day.
Let the work rates of A, B, and C be represented as:
- Work rate of A = a
- Work rate of B = b
- Work rate of C = c
1. a+b=112 (Equation 1)
2. b+c=115 (Equation 2)
3. c+a=120 (Equation 3)
To find the individual work rates, we can add all three equations together:
(a+b)+(b+c)+(c+a)=112+115+120
This simplifies to:
2a+2b+2c=112+115+120
To add the fractions, we need a common denominator. The least common multiple of 12, 15, and 20 is 60.
- Convert each fraction:
- 112=560
- 115=460
- 120=360
560+460+360=1260=15
Now we have:
2(a+b+c)=15
Dividing both sides by 2 gives:
a+b+c=110
The combined work rate of A, B, and C is 110 units of work per day. Therefore, the time taken for all three to complete the work together is:
Time=Total WorkCombined Work Rate=1110=10 days
A, B, and C can complete the work together in 10 days.
Topper's Solved these Questions
- TIME AND WORK, PIPES AND CISTERNSBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK, PIPES AND CISTERNSEXERCISE - Essay Type Question
5 Videos
- TIME AND WORK, PIPES AND CISTERNSBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK, PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-1)
33 Videos
- TIME AND WORK, PIPES AND CISTERNSBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK, PIPES AND CISTERNSEXERCISE - TEST YOUR CONCEPTS (Very Short Answer Type Questions)
30 Videos
- TIME AND WORK PIPES AND CISTERNSBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-3)
7 Videos
Similar Questions
A can do a piece of work in 16 days and B can do the same work in 20 days. In how many days can they do the same work, working together?
View SolutionA and B can do piece of work in 12 days; B and C in 15 days; C and A in 20 days. In how many days will they finish it together and separately ?
View Solution
Knowledge Check
A and B can do a piece of work in 12 days, B and C in 15 days C and A in 20 days. In how many days can C alone do it ?
A60B50C25D24A and B can do a piece of work in 12 days, B and C in 15 days and A and C in 20 days. In how many days can each alone do the work?
A30,20,50B30,45,60C30,20,60D20,30,50A and B can do a piece of work in 10 days, B and C in 15 days and C and A in 20 days. C alone can do the work in :
A60 daysB120 daysC80 daysD30 days
A and B can do a piece of work in 10 days, B and C in 15 days and C and A in 20 days. Calone can do the work in :
View SolutionA and B can do a piece of work in 10 days, B and C in 15 days and C and A in 20 days. C alone can do the work in :
View SolutionA and B can do a piece of work in 12 days, B and C in 15 days, C and A in 20 days. In what time can A do it separately?
View SolutionA and B can do a piece of work in 12 days, B and C in 15 days, C and A in 20 days. In what time can A do it separately?
View SolutionA and B can do a piece of work in 72 days B and C can do it in 120 days. A and C can do it in 90 days. In how many days, all the three together can do the work?
View Solution